Installed target 89 GW! Inner Mongolia Releases Action Plan for Photovoltaic Sand Control

2023-11-07 18:23:27

By 2030, the installed capacity of photovoltaic sand control will be 89 million kilowatts, and the annual power generation will be 150 billion kilowatt-hours.

On November 7, the People's Government of Inner Mongolia issued the Notice on the Implementation Plan of Photovoltaic Sand Control Action in the Autonomous Region. According to the document notice, in order to cooperate with the "Three North" Phase VI and other ecological control projects, the large-scale development of photovoltaic sand control in desert and sandy land in the whole region will be implemented. It is planned that by 2025, the installed capacity of photovoltaic sand control will exceed 21.4 million kilowatts , and the area of photovoltaic sand control will be 640000 mu; By 2030, the installed capacity of photovoltaic sand control will be 89 million kilowatts , and the area of photovoltaic sand control will be about 2.3 million mu.

From the point of view of the photovoltaic sand control projects put into operation in the 14th Five-Year Plan, the guaranteed grid-connected photovoltaic planning is 3.55 GW, the national 123 large base planning is 7.65 GW, the Shagohuang base planning is 4G W, the market-oriented project planning is 1 G W, and 5.2G W has been completed. Master Plan 21.

: October 23

, 2007 (this document is released publicly)"

The implementation plan

of photovoltaic sand control action in Inner Mongolia Autonomous Region is to carry out Xi Jinping's ecological civilization thought in depth, earnestly implement the important instructions and important speech spirit of General Secretary Xi Jinping during his visit to Inner Mongolia, and promote the organic integration of photovoltaic development and comprehensive desert control. This plan is formulated in light of the actual situation of the autonomous region to help fight the battle of annihilation in the two sandy lands of Horqin and Hunshandake, the battle of "a few words bend" in the Yellow River and the battle of blocking the edge of the Hexi Corridor-Taklimakan Desert.

I. Development Basis

Inner Mongolia has obvious advantages in developing photovoltaic sand control resources, and the amount of onshore solar energy resources in the whole region is about 94. In recent years, the autonomous region has vigorously developed

Xi Jinping endowed Inner Mongolia with the strategic positioning of the important ecological security barrier in the north, the important national energy and strategic resource base, especially the important instructions and speeches made by General Secretary Xi Jinping during his visit to Inner Mongolia in June 2023, so as to make every effort to fight the "Three North" battle for the autonomous region, prevent and control desertification scientifically, and promote the development of Inner Mongolia. A new blueprint has been drawn for the vigorous development of new energy. During the "14th Five-Year Plan" and "15th Five-Year Plan", large-scale wind power and photovoltaic bases will be built on the edge of Kubuqi, Ulan Buh, Tengger and Badain Jilin deserts and their surrounding areas, and supporting power transmission channels will be built, which will expand the new space for the development of photovoltaic in desert and desert areas in the autonomous region. Focusing on building a "model autonomous region" in an all-round way, the autonomous region has actively promoted the experience of Kubuqi desert control, which has injected new impetus into the integration of new energy development and ecological protection. The whole region is making great efforts to optimize the economic layout, adjust the industrial structure in depth, promote rural revitalization, change the way of energy development and utilization, and provide a new opportunity for innovative mechanisms to mobilize farmers, herdsmen, enterprises and other parties to participate in photovoltaic sand control. At the same time, the water resources in the autonomous region are relatively scarce, and the insufficient carrying capacity of water resources has become a rigid constraint for photovoltaic sand control. Desert areas are far away from load centers, lack of self-absorption space, difficult to construct transmission channels, low income of photovoltaic power generation, and increased cost of artificial irrigation, resulting in large project investment, long cycle, slow effect, low enthusiasm of social capital to participate in photovoltaic sand control, and no complete formation of a diversified investment mechanism among the government, enterprises, society and the masses.

2. General requirements

(1) Basic principles.

-Adhering to ecological priority and green development. Determine the green with water, measure the amount of water, take measures according to the area and classification, select grass and tree species scientifically, determine the restoration mode and task arrangement reasonably, and promote "-adhere to systematic management and highlight the key points. Various ecological protection and restoration measures should be taken scientifically, and efforts should be concentrated on photovoltaic sand control projects in key areas to give full play to the ecological and environmental benefits of photovoltaic projects.

-- Insisting on large-scale development and intensive utilization. We should adhere to centralized and continuous development, coordinate land use, wind and solar resources and absorption conditions, plan and lay out photovoltaic bases of more than one million kilowatts, make intensive use of land, and enhance land value-added and comprehensive utilization benefits.

-Adhering to the government's leading role and social participation. Highlighting the leading role of the government, strengthening the guarantee of water, land, capital and other factors, comprehensively building a new mechanism of government-led, enterprise-oriented, public participation and social coordination, and forming a joint force of ecological protection and restoration of photovoltaic sand control.

(2) Overall objectives. In cooperation with the "Three North" Phase VI and other ecological control projects, the large-scale development of photovoltaic sand control in deserts and sandy lands in the whole region will be implemented to help the key areas such as Kubuqi Desert, Ulan Buh Desert and Maowusu Sandy Land to be systematically harnessed, the two sandy lands of Horqin and Hunshandake to be fully covered, and the two deserts of Badain Jilin and Tengger to be harnessed. The trend of desert invasion has been effectively curbed. By 2025, the installed capacity of photovoltaic sand control will exceed 21.4 million kilowatts, the annual power generation will be about 36 billion kilowatt hours, and the completed area of photovoltaic sand control will be 640,000 mu; by 2030, the installed capacity of photovoltaic sand control will be 89 million kilowatts, the annual power generation will be 150 billion kilowatt hours, the completed area of photovoltaic sand control will be about 2.3 million mu, and the economy under the board will grow rapidly.

(5) Developing photovoltaic sand control industry to enhance the economic benefits of sandy areas. Establish market-oriented and industrialized thinking, and closely integrate photovoltaic sand control with the development of local economy. Relying on abundant land for photovoltaic construction in sandy areas and abundant psammophyte resources, we will promote the development of facility agriculture and animal husbandry, water-saving planting in sandy areas and traditional Chinese medicines under the boards, and help the ecological industry of characteristic forests and grasses grow. Relying on the vast market demand and abundant land resources, we will promote the development of the whole industry chain of photovoltaic equipment manufacturing, expand the level of employment and improve economic efficiency. Give full play to the advantages of "photovoltaic plus" tourism, tap the potential of desert tourism, increase the construction of tourism routes, help upgrade the service industry in desert areas, and promote economic income growth.

(7) Improve the policy support system and promote the implementation of photovoltaic sand control. We should adhere to the government's leading role, the main body of enterprises and the participation of farmers and herdsmen, effectively stimulate the enthusiasm of the whole society for desertification prevention and control, formulate incentive policies, mobilize the enthusiasm of social capital for photovoltaic desertification control, form a diversified investment mechanism among the government, enterprises, society and the masses, and carry out regional centralized control in combination with the layout of desertification control in the autonomous region, so as to help prevent desertification and control and improve the efficiency of photovoltaic power generation. Strengthen scientific and technological innovation, support photovoltaic sand control, actively strive for the establishment of national photovoltaic sand control and sand industry technology innovation center in the autonomous region from relevant ministries and commissions of the state, increase investment in scientific and technological research and development in the field of photovoltaic sand control, and promote cooperation between scientific research institutes, universities and sand industry and new energy development enterprises. Give full play to the role of Kubuqi International Desert Forum platform, share the experience of all parties in photovoltaic desertification control, vigorously promote the Kubuqi model, and actively participate in international cooperation in photovoltaic desertification control. Innovation of green power cooperation mode, with photovoltaic sand control as the starting point, to promote the industrial transformation of sandy areas, promote the industrial development of sandy areas, with photovoltaic sand control to promote shrub processing industry, forage processing industry, Chinese herbal medicine processing industry to use materials and electricity nearby, photovoltaic sand control projects and supporting industries to promote in coordination, attract enterprises with demand for green power in the surrounding layout of sandy areas, and enhance the level of green power consumption in the region. To formulate competition rules for guaranteed photovoltaic sand control projects, guide new energy development enterprises to actively carry out photovoltaic sand control, and take the promised desert control area as the main competition standard.

4. Safeguard measures

(1) Strengthen organizational leadership. We should adhere to the overall planning of the government, work together, study and improve policies, establish a working mechanism for promoting the development of photovoltaic desertification control in the autonomous region, solve major problems as a whole, and promote the effectiveness of photovoltaic desertification control.

(2) Strengthen the implementation of responsibilities. The competent energy departments at all levels in the autonomous region should strengthen supervision over the construction and operation of photovoltaic sand control projects. Development and reform, natural resources, ecological environment, water conservancy, agriculture and animal husbandry, forestry and grass and other relevant departments should coordinate and work together to promote the implementation of key tasks, carry out joint site selection of photovoltaic sand control projects, optimize and streamline the approval process, and create favorable conditions for project landing. The competent departments at all levels, such as forestry and grass, agriculture and animal husbandry, and natural resources, should implement the nature of land used for the construction of photovoltaic sand control projects, and guide the implementation of the ecological control model. Taking into account the carrying capacity of local water resources, the competent water conservancy authorities have issued water use policies for photovoltaic sand control projects to dredge water channels such as ice flood water in the Yellow River, reclaimed water in urban parks, cooling water in thermal power plants and drainage water in mining areas. All League cities and banner counties (cities and districts) should take the initiative to assume territorial responsibilities, consolidate departmental responsibilities, conscientiously fulfill the responsibilities of examination and approval and follow-up supervision, and ensure the smooth landing of photovoltaic sand control projects.

(3) Strengthen supervision and management. To clarify the supervision responsibility of the competent energy department and the cooperation of relevant departments and units, to establish an evaluation mechanism for the construction and operation of photovoltaic sand control, to regularly dispatch the progress of the work, to carry out the evaluation of the construction and operation effect of photovoltaic sand control according to the annual evaluation plan, construction and grid-connected consumption, and to find out the typical problems and key problems to jointly study and solve them, so as to ensure the implementation of photovoltaic sand control according to the plan.

All can be viewed after purchase
Correlation

Prospective layout of next generation technologies such as perovskite batteries and crystalline silicon thin film tandem batteries.

2023-12-27 09:07:44

The notice will be implemented from January 1, 2024.

2023-12-26 11:32:16

At present, there are many problems, such as imperfect industrial policy, insufficient infrastructure, slow promotion of hydrogen vehicles and so on.

2023-12-22 09:25:45

Since 2023, Jilin's new energy projects have allocated energy storage according to 15% of the installed capacity in principle, charging time is more than 2 hours, and centralized sharing is encouraged. Among them, market-oriented grid-connected new energy projects, the capacity proportion and duration of new energy storage are moderately increased.

2023-12-08 11:25:42

Optimize the energy structure and accelerate the clean, low-carbon and efficient development of energy.

2023-12-08 10:01:01

Achieve business income of more than 60 billion yuan by 2025!

2023-12-07 09:17:16

It shall be submitted to the National Development and Reform Commission (Environment and Resources Department) before January 31, 2024.

2023-12-07 09:15:26

Subsidies can reach up to 20 million.

2023-12-04 09:20:30

Projects that have not been started beyond the validity period will automatically become invalid.

2023-12-01 09:44:07

By 2025, more than 10,000 fuel cell vehicles will be promoted in Guangdong Province, with an annual hydrogen supply capacity of more than 100,000 tons, and more than 200 hydrogenation stations will be built. By 2027, the scale of hydrogen energy industry will reach 300 billion yuan, and the whole industry chain of hydrogen "production, storage, transportation and utilization" will reach the advanced level in China.

2023-11-24 15:13:25

Inner Mongolia has standardized the general requirements, grid-connected requirements, application scenarios, layout requirements, investment conditions and support contents of independent new energy storage power station projects.

2023-11-21 09:45:56

The peak period is from 9:00 to 12:00 and from 17:00 to 22:00; the average period is from 7:00 to 9:00, from 12:00 to 17:00 and from 22:00 to 23:00; and the valley period is from 23:00 to 7:00 of the next day. The electricity price ratio is 1.5: 1: 0.5 during the peak period, the normal period and the valley period.

2023-11-17 10:07:03

A mid-term hearing was held on the 201 clause of the United States concerning China's photovoltaic imports.

2023-11-16 09:11:08

There are 302 projects with a total scale of about 1.4G W.

2023-11-10 19:24:58

By 2025, the annual hydrogen supply capacity will exceed 100,000 tons, and by 2027, the scale of the hydrogen energy industry will reach 300 billion yuan.

2023-11-09 11:56:27

It is required to take 2022 as the base year and strive to double the scale and quality of new energy, double the benefits driven by new energy, double the innovation ability of new energy science and technology, and double the manufacturing industry chain of wind and solar hydrogen storage equipment in 2025.

2023-11-08 09:51:17

By 2030, the installed capacity of photovoltaic sand control will be 89 million kilowatts, and the annual power generation will be 150 billion kilowatt-hours.

2023-11-07 18:23:27

The first batch of pilot construction of carbon peak was carried out in 15 provinces and regions.

2023-11-07 09:27:04

Encourage household photovoltaic "self-use, surplus electricity access to the grid" and industrial and commercial photovoltaic "all self-use" to achieve local consumption on the user side, improve the efficiency of distributed photovoltaic power generation, and reduce the pressure of public grid operation.

2023-11-06 14:54:44

Among them, detailed subsidies and application procedures are put forward to support the construction and operation of distributed photovoltaic projects, energy storage demonstration projects, green electricity hydrogen production, hydrogenation station construction, hydrogenation station operation energy storage demonstration project construction, energy storage project operation, etc.

2023-10-27 15:10:36

Since the second half of this year, many scenic projects have been abolished for various reasons.

2023-10-27 09:21:22

As of September 30, 2023, among the photovoltaic projects included in the competitive optimization scheme in 2021, 34 projects with installed capacity of 2.894 million kilowatts have not been started. According to the requirements, the construction scale of the above projects has been cancelled and the corresponding grid absorption space has been vacated.

2023-10-26 11:53:30

The project shall be completed and connected to the grid with full capacity by December 20, 2023, and the county government and the development enterprise shall issue a letter of commitment for grid connection on schedule. Time is tight and the task is heavy.

2023-10-24 14:39:42

The notice clarifies the scope of concurrent duties of relevant managers of renewable energy power generation projects, standardizes the license registration of renewable energy power generation projects, adjusts the license renewal policy of renewable energy power generation projects (units), and clarifies the responsibilities of power business license management of registered enterprises in different places.

2023-10-24 13:08:14

Focus on the rectification of mandatory requirements for supporting industries, mandatory requirements for investment landing.

2023-10-24 10:14:46

It will be implemented on December 1 and will be valid for 5 years!

2023-10-23 09:13:32

Shanghai plans to explore the construction of integrated hydrogen production, hydrogen storage and hydrogenation stations in Lingang New Area, and improve the regional hydrogen energy transmission network in Baowu Park and Shanghai Chemical Industry Zone.

2023-10-23 09:12:16

Yueyang County, Hunan Province, issued a notice to regulate the construction and management order of photovoltaic power generation projects, prohibit the fraudulent use of the name of unauthorized enterprises, and require that construction can be started only after obtaining the record certificate, otherwise the grid access procedures will not be handled. The notice will be implemented from May 8, 2023.

2023-10-20 19:20:26

The circular requests that by 2025, a number of demonstration projects with advanced technology, reasonable economic benefits and good prospects for popularization and application should be organized and implemented to promote the formation of a series of relatively mature and perfect supporting policies, technical standards and business models, so as to effectively promote the development of new technologies, new models and new formats of renewable energy.

2023-10-19 09:46:46

Since the third quarter, a total of 21 new subsidy policies involving photovoltaic and energy storage have been introduced in 9 provinces and municipalities.

2023-10-16 11:56:46

Hebei: Hydrogen stations to be included in local construction indicators

2023-10-13 09:12:49

The photovoltaic field is mainly related to photovoltaic power generation projects, offshore photovoltaic power generation, and ecological photovoltaic design in rocky desertification areas.

2023-10-12 10:51:04

Hydrogen energy is included in the key supporting industries in Karamay, and the maximum amount of support is not more than 5 million yuan.

2023-10-08 10:12:05

According to the document, many illegal acts, such as refusing or obstructing the signing of power purchase and sale contracts and grid-connected dispatching agreements with renewable energy power generation enterprises, failing to fairly open the power grid in accordance with regulations, violating the safety responsibility regulations of power construction units, contracting projects without qualification certificates, failing to organize completion acceptance, and unauthorized delivery and use, will be subject to administrative penalties.

2023-10-07 13:21:01

Since the third quarter, a total of 21 new subsidy policies involving photovoltaic and energy storage have been introduced in 9 provinces and municipalities.

2023-09-27 09:11:57

We will encourage the development of new energy sources such as photovoltaic and hydrogen energy, promote the development and utilization of new energy sources, optimize the energy structure, ensure energy security, promote carbon peak and carbon neutralization, and promote green development.

2023-09-25 10:16:44

Selection criteria: the main business income of Shanxi wind power equipment, photovoltaic, new energy storage industry chain "chain core" enterprises in the previous year, in principle, is not less than 50 million yuan; The annual product transaction volume between the core supporting "chain core" enterprises and the "chain owner" enterprises in the industrial chain exceeds 10 million yuan, and the annual product transaction volume between the potential chain owner "chain core" enterprises and more than 5 (including) other enterprises in the same chain exceeds 20 million yuan.

2023-09-25 09:48:54

According to the installed capacity, the subsidy is 0.40 yuan/watt (the subsidy standard is 1 yuan/watt for the project of building integrated photovoltaic application (photovoltaic modules as building components)), and the maximum subsidy for a single project is not more than 5 million yuan.

2023-09-22 11:46:47

The mainland has the conditions to transmit green power to Taiwan on a large scale, and is willing to strengthen cross-strait cooperation in the field of energy and jointly promote the green transformation and development of energy across the Straits.

2023-09-15 09:22:30

By 2025, the annual production capacity of 150 GW photovoltaic cells and components, 5G W wind turbines and components, 100 G Wh energy storage batteries and more than 5000 sets of hydrogen fuel cell equipment will be formed, and the output value of new energy manufacturing industry above the province's scale will reach 800 billion yuan. 

2023-09-13 10:05:29

Separately developed wind power, centralized photovoltaic and other new projects: (new energy projects approved or filed after the issuance of this implementation opinion), in principle, new energy storage shall be allocated according to not less than 10% of the installed capacity and more than 2 hours of energy storage time. Encourage new energy projects in stock to allocate new energy storage. The operation time of the new energy storage shall not be later than operation time of the new energy project.

2023-09-12 09:48:20

By 2025, the annual production capacity of 150 GW photovoltaic cells and components, 5G W wind turbines and components, 100 G Wh energy storage batteries and more than 5000 sets of hydrogen fuel cell equipment will be formed, and the output value of new energy manufacturing industry above the province's scale will reach 800 billion yuan.

2023-09-11 13:07:09