Recently, the People's Government of Yueyang County, Hunan Province, issued the " Notice on Further Standardizing the Construction and Management Order of Distributed Photovoltaic Power Generation Projects in Our County". According to
the notice, In the recent development and construction of local distributed photovoltaic power generation projects, there have been false publicity , transfer of risks , construction without preparation, The irregularities such as fake central enterprises , forged certificates and unauthorized changes have seriously infringed on the interests of the masses, damaged the image of the government and enterprises, and destroyed the normal development order of the industry.
To further standardize the construction and management order of distributed photovoltaic power generation projects, the circular proposes that it is forbidden to negotiate and carry out photovoltaic projects in the name of unauthorized enterprises or units. Distributed photovoltaic power generation projects that have not obtained the "Yueyang County Enterprise Investment Project Record Certificate " shall not start construction ;
At the same time, if there is no project record certificate for the construction that has already started, it must be stopped in time and the construction can be started only after the formalities have been perfected. For distributed photovoltaic power generation projects that have not obtained the "Yueyang County Enterprise Investment Project Record Certificate", the State Grid Yueyang Electric Power Company will not go through the formalities of grid access.
This Circular shall be implemented as of May 8, 2023.