On October 25, the Jiangxi Development and Reform Commission issued a "Notice of Jiangxi Energy Bureau on Overdue , indicating that as of September 30, 2023, the photovoltaic projects included in the competitive optimization scheme in 2021 will be included in the photovoltaic projects. There are 34 projects with installed capacity of 289.
In addition, for the remaining projects under construction, considering that the enterprise has completed a large investment, after the enterprise has made relevant commitments, it will be postponed to April 30, 2024, and the overdue projects will automatically withdraw from the grid to absorb resources. If the project is completed before December 31, 2023, the energy storage configuration requirements will still be implemented according to the original commitment; if the project is completed from January 1, 2024 to April 30, 2024, the energy storage will be configured according to 15% of its capacity and 2 hours. During the extension period, the power grid enterprises shall continue to handle the project grid connection according to the procedures.
In fact, Jiangxi is not the first province to withdraw photovoltaic projects. Since the second half of this year, many wind and solar projects have been abolished for various reasons, and digital new energy DataBM
has not been built. On July 22
last year, Shanxi Province issued a list of the first batch of wind and photovoltaic power generation projects to be abolished, in which 54 projects were abolished. The total scale is 1.388 million kilowatts, of which wind power projects 1.
The reason for the abolition of these projects is that they have occupied resources for a long time and have not been completed. In May
this year, Shanxi Province issued a list of the second batch of wind power and photovoltaic power generation projects to be abolished, with 19 projects totaling 1.
Liaoning Provincial Development and Reform Commission issued a public announcement on the proposed abolition of the grid-connected scale indicators (the first batch) for the 4.8 million kilowatt key wind and photovoltaic construction projects in the province that have not been completed on schedule.
The announcement said that the 4.8 million kilowatt wind power photovoltaic key construction projects in Liaoning Province had problems such as "nuclear but not built" and "construction lag" . After summarizing, it is proposed to abolish two photovoltaic power generation projects, namely, the 200 MW photovoltaic power generation project of Liaoneng Nanpiao and the 50 MW photovoltaic power generation project of Nanpiao Warm Pond, which have not been completed and connected to the grid on schedule, with a total scale index of 250 MW not connected to the grid. 927.3MW photovoltaic project to be abolished in Hubin District, Sanmenxia City,
Henan Province! 3MW, covering 690 MW centralized photovoltaic projects and distributed photovoltaic projects 237.
The announcement pointed out that the abolition of the above projects was a project that had not started construction or gone through any other formalities within two years after filing. It does not meet the construction conditions, is not included in the annual development plan of renewable energy in the province, occupies resources for a long time, and has not been completed for a long time.
It involves the ecological red line and policy changes. Take the initiative to withdraw
18 scenic projects in three places in Shaanxi and abolish them
SRC = "https://img7.ccement.com/richtext/img/zrc7smvwoy1698369815341.
Among them, Baoji City has abolished 7 wind power and photovoltaic projects, totaling 170,000 kilowatts.". Fugu County of Yulin City abolished 10 scenic projects, with a scale of 45. Yangxian County of Hanzhong City abolished 10 villages, totaling 0.
A total of 18 scenic projects in three places were abolished. The reasons for the abolition of
these projects are that the project approval documents have expired, the construction has not started within the validity period after filing, and the approval has not been approved within the prescribed time. It is also because it involves the ecological red line and the policy stop . Many projects
in Baoji City are no longer under construction because they involve concentrated areas of forest land in the second-level national public welfare forests. Adjustment of Photovoltaic Competitive Projects
in Anhui Province: Shrinking 2.
Due to the adjustment of water conservancy and land use policies, the construction scale of 36 projects has been adjusted, and the scale of 3.3GW has been reduced to 1.1GW, with a reduction of 2.