Sichuan Energy Storage New Policy: 10% * 2 hours for large-scale wind and solar projects, except for multi-energy complementation

2023-09-12 09:48:20

Separately developed wind power, centralized photovoltaic and other new projects: (new energy projects approved or filed after the issuance of this implementation opinion), in principle, new energy storage shall be allocated according to not less than 10% of the installed capacity and more than 2 hours of energy storage time. Encourage new energy projects in stock to allocate new energy storage. The operation time of the new energy storage shall not be later than operation time of the new energy project.

Recently, the Sichuan Development and Reform Commission, the Sichuan Energy Bureau, the Sichuan Economic and Information Department and the Sichuan Regulatory Office of the State Energy Administration jointly issued the "Opinions on Accelerating the Construction of New Energy Storage Demonstration Projects in Sichuan Province". It is proposed that the scale of new energy storage in the province will reach more than 2 million kilowatts by 2025. Specific provisions are as follows:

1. Requirements for distribution and storage of new energy projects:

wind power, centralized photovoltaic and other new projects developed separately: (new energy projects approved or filed after the issuance of this implementation opinion). In principle, the new type of energy storage should be configured according to not less than 10% of the installed capacity and more than 2 hours of energy storage time.

Encourage multi-energy complementary development of new energy projects to allocate new energy storage. For new energy projects incorporated into the integrated renewable energy development bases of water, scenery and light in the upper reaches of the Jinsha River, the lower reaches of the Jinsha River, the Yalong River Basin and the upper and middle reaches of the Dadu River, it is encouraged to allocate new energy storage in combination with the consumption situation.

New energy development enterprises can adopt independent construction, joint construction, market leasing (purchase) and other ways to implement the allocation of new energy storage capacity requirements to encourage new energy projects in stock to allocate new energy storage . The operation time of the new energy storage shall not be later than operation time of the new energy project.

2. Define three ways

to make profits for independent energy storage projects 1) Establish an independent new energy storage capacity sharing and leasing mechanism through leasing capacity profits

. The suggested reference range is 200-400 yuan/kilowatt year. New energy development enterprises are encouraged to sign long-term lease agreements with owners of new independent energy storage projects.

2) Before

entering the spot electricity market, the energy storage power station participates in the medium and long-term market transactions as an independent market entity. When charging, it can enjoy the time-of-use electricity price policy as a power market user; when discharging, it can participate in the market transaction of thermal power, and the price is formed by the market. If

an independent new energy storage power station transmits electricity to the power grid, its corresponding charging capacity shall not bear the transmission and distribution price, government funds and additional charges, and the charge for charging and discharging losses shall be borne by the independent new energy storage power station. After

entering the electricity spot market, the electricity price and on-grid price of the independent new energy storage power station are settled according to the spot market price and rules.

3) Profitable

power grid enterprises participating in the power ancillary service market shall sign a grid-connected dispatching agreement with the owners of independent new energy storage power stations, giving priority to dispatching under the same conditions. In principle, the number of times of full charge and discharge shall not be less than 250 times per year.

3. Requirements

for independent energy storage projects 1) Independent energy storage demonstration projects should be centralized, and the installed capacity of a single power station should not be less than 100,000 kilowatts in principle.

2) New energy storage projects with legal personality that meet the conditions and standards can be converted to independent new energy storage and participate in the electricity market as independent subjects. Encourage new energy storage projects in the form of allocation and construction, and choose to convert them into independent new energy storage projects. In principle, the energy storage of wind-solar-hydro-thermal storage multi-energy complementary integration project will not be converted to independent new energy storage for the time being.

The original text is as follows:

All can be viewed after purchase
Correlation

Prospective layout of next generation technologies such as perovskite batteries and crystalline silicon thin film tandem batteries.

2023-12-27 09:07:44

The notice will be implemented from January 1, 2024.

2023-12-26 11:32:16

At present, there are many problems, such as imperfect industrial policy, insufficient infrastructure, slow promotion of hydrogen vehicles and so on.

2023-12-22 09:25:45

Since 2023, Jilin's new energy projects have allocated energy storage according to 15% of the installed capacity in principle, charging time is more than 2 hours, and centralized sharing is encouraged. Among them, market-oriented grid-connected new energy projects, the capacity proportion and duration of new energy storage are moderately increased.

2023-12-08 11:25:42

Optimize the energy structure and accelerate the clean, low-carbon and efficient development of energy.

2023-12-08 10:01:01

Achieve business income of more than 60 billion yuan by 2025!

2023-12-07 09:17:16

It shall be submitted to the National Development and Reform Commission (Environment and Resources Department) before January 31, 2024.

2023-12-07 09:15:26

Subsidies can reach up to 20 million.

2023-12-04 09:20:30

Projects that have not been started beyond the validity period will automatically become invalid.

2023-12-01 09:44:07

By 2025, more than 10,000 fuel cell vehicles will be promoted in Guangdong Province, with an annual hydrogen supply capacity of more than 100,000 tons, and more than 200 hydrogenation stations will be built. By 2027, the scale of hydrogen energy industry will reach 300 billion yuan, and the whole industry chain of hydrogen "production, storage, transportation and utilization" will reach the advanced level in China.

2023-11-24 15:13:25

Inner Mongolia has standardized the general requirements, grid-connected requirements, application scenarios, layout requirements, investment conditions and support contents of independent new energy storage power station projects.

2023-11-21 09:45:56

The peak period is from 9:00 to 12:00 and from 17:00 to 22:00; the average period is from 7:00 to 9:00, from 12:00 to 17:00 and from 22:00 to 23:00; and the valley period is from 23:00 to 7:00 of the next day. The electricity price ratio is 1.5: 1: 0.5 during the peak period, the normal period and the valley period.

2023-11-17 10:07:03

A mid-term hearing was held on the 201 clause of the United States concerning China's photovoltaic imports.

2023-11-16 09:11:08

There are 302 projects with a total scale of about 1.4G W.

2023-11-10 19:24:58

By 2025, the annual hydrogen supply capacity will exceed 100,000 tons, and by 2027, the scale of the hydrogen energy industry will reach 300 billion yuan.

2023-11-09 11:56:27

It is required to take 2022 as the base year and strive to double the scale and quality of new energy, double the benefits driven by new energy, double the innovation ability of new energy science and technology, and double the manufacturing industry chain of wind and solar hydrogen storage equipment in 2025.

2023-11-08 09:51:17

By 2030, the installed capacity of photovoltaic sand control will be 89 million kilowatts, and the annual power generation will be 150 billion kilowatt-hours.

2023-11-07 18:23:27

The first batch of pilot construction of carbon peak was carried out in 15 provinces and regions.

2023-11-07 09:27:04

Encourage household photovoltaic "self-use, surplus electricity access to the grid" and industrial and commercial photovoltaic "all self-use" to achieve local consumption on the user side, improve the efficiency of distributed photovoltaic power generation, and reduce the pressure of public grid operation.

2023-11-06 14:54:44

Among them, detailed subsidies and application procedures are put forward to support the construction and operation of distributed photovoltaic projects, energy storage demonstration projects, green electricity hydrogen production, hydrogenation station construction, hydrogenation station operation energy storage demonstration project construction, energy storage project operation, etc.

2023-10-27 15:10:36

Since the second half of this year, many scenic projects have been abolished for various reasons.

2023-10-27 09:21:22

As of September 30, 2023, among the photovoltaic projects included in the competitive optimization scheme in 2021, 34 projects with installed capacity of 2.894 million kilowatts have not been started. According to the requirements, the construction scale of the above projects has been cancelled and the corresponding grid absorption space has been vacated.

2023-10-26 11:53:30

The project shall be completed and connected to the grid with full capacity by December 20, 2023, and the county government and the development enterprise shall issue a letter of commitment for grid connection on schedule. Time is tight and the task is heavy.

2023-10-24 14:39:42

The notice clarifies the scope of concurrent duties of relevant managers of renewable energy power generation projects, standardizes the license registration of renewable energy power generation projects, adjusts the license renewal policy of renewable energy power generation projects (units), and clarifies the responsibilities of power business license management of registered enterprises in different places.

2023-10-24 13:08:14

Focus on the rectification of mandatory requirements for supporting industries, mandatory requirements for investment landing.

2023-10-24 10:14:46

It will be implemented on December 1 and will be valid for 5 years!

2023-10-23 09:13:32

Shanghai plans to explore the construction of integrated hydrogen production, hydrogen storage and hydrogenation stations in Lingang New Area, and improve the regional hydrogen energy transmission network in Baowu Park and Shanghai Chemical Industry Zone.

2023-10-23 09:12:16

Yueyang County, Hunan Province, issued a notice to regulate the construction and management order of photovoltaic power generation projects, prohibit the fraudulent use of the name of unauthorized enterprises, and require that construction can be started only after obtaining the record certificate, otherwise the grid access procedures will not be handled. The notice will be implemented from May 8, 2023.

2023-10-20 19:20:26

The circular requests that by 2025, a number of demonstration projects with advanced technology, reasonable economic benefits and good prospects for popularization and application should be organized and implemented to promote the formation of a series of relatively mature and perfect supporting policies, technical standards and business models, so as to effectively promote the development of new technologies, new models and new formats of renewable energy.

2023-10-19 09:46:46

Since the third quarter, a total of 21 new subsidy policies involving photovoltaic and energy storage have been introduced in 9 provinces and municipalities.

2023-10-16 11:56:46

Hebei: Hydrogen stations to be included in local construction indicators

2023-10-13 09:12:49

The photovoltaic field is mainly related to photovoltaic power generation projects, offshore photovoltaic power generation, and ecological photovoltaic design in rocky desertification areas.

2023-10-12 10:51:04

Hydrogen energy is included in the key supporting industries in Karamay, and the maximum amount of support is not more than 5 million yuan.

2023-10-08 10:12:05

According to the document, many illegal acts, such as refusing or obstructing the signing of power purchase and sale contracts and grid-connected dispatching agreements with renewable energy power generation enterprises, failing to fairly open the power grid in accordance with regulations, violating the safety responsibility regulations of power construction units, contracting projects without qualification certificates, failing to organize completion acceptance, and unauthorized delivery and use, will be subject to administrative penalties.

2023-10-07 13:21:01

Since the third quarter, a total of 21 new subsidy policies involving photovoltaic and energy storage have been introduced in 9 provinces and municipalities.

2023-09-27 09:11:57

We will encourage the development of new energy sources such as photovoltaic and hydrogen energy, promote the development and utilization of new energy sources, optimize the energy structure, ensure energy security, promote carbon peak and carbon neutralization, and promote green development.

2023-09-25 10:16:44

Selection criteria: the main business income of Shanxi wind power equipment, photovoltaic, new energy storage industry chain "chain core" enterprises in the previous year, in principle, is not less than 50 million yuan; The annual product transaction volume between the core supporting "chain core" enterprises and the "chain owner" enterprises in the industrial chain exceeds 10 million yuan, and the annual product transaction volume between the potential chain owner "chain core" enterprises and more than 5 (including) other enterprises in the same chain exceeds 20 million yuan.

2023-09-25 09:48:54

According to the installed capacity, the subsidy is 0.40 yuan/watt (the subsidy standard is 1 yuan/watt for the project of building integrated photovoltaic application (photovoltaic modules as building components)), and the maximum subsidy for a single project is not more than 5 million yuan.

2023-09-22 11:46:47

The mainland has the conditions to transmit green power to Taiwan on a large scale, and is willing to strengthen cross-strait cooperation in the field of energy and jointly promote the green transformation and development of energy across the Straits.

2023-09-15 09:22:30

By 2025, the annual production capacity of 150 GW photovoltaic cells and components, 5G W wind turbines and components, 100 G Wh energy storage batteries and more than 5000 sets of hydrogen fuel cell equipment will be formed, and the output value of new energy manufacturing industry above the province's scale will reach 800 billion yuan. 

2023-09-13 10:05:29

Separately developed wind power, centralized photovoltaic and other new projects: (new energy projects approved or filed after the issuance of this implementation opinion), in principle, new energy storage shall be allocated according to not less than 10% of the installed capacity and more than 2 hours of energy storage time. Encourage new energy projects in stock to allocate new energy storage. The operation time of the new energy storage shall not be later than operation time of the new energy project.

2023-09-12 09:48:20

By 2025, the annual production capacity of 150 GW photovoltaic cells and components, 5G W wind turbines and components, 100 G Wh energy storage batteries and more than 5000 sets of hydrogen fuel cell equipment will be formed, and the output value of new energy manufacturing industry above the province's scale will reach 800 billion yuan.

2023-09-11 13:07:09