On September 21, the Bureau of Ecology and Environment of Puer City, Yunnan Province, issued a public announcement on the acceptance of environmental impact assessment documents for six construction projects, including the Tea-Light Complementary Power Generation Project in Daigla Village.
According to the announcement, the construction units of the six photovoltaic projects are all affiliated companies of CGN, with a total rated capacity of 415 MW (AC side). Installed capacity of 548. 1887 MWp, The

details are as follows:
Daigla Village Tea and Light Complementary Power Generation Project is located in Lisuo Lahu Township, Ximeng Wa Autonomous County, Pu'er City. The total investment is 160 million yuan , the land area is 80. The rated capacity of the project is 40 MW (AC side) , and the installed capacity is 53.71 MWp (DC side) . The system has a capacity ratio of 1.3422, and a total of 735 Wp monocrystalline silicon double-sided photovoltaic 73080 blocks are installed It is worth noting that. The initial site of the project is located in Xinchang Town, Ximeng Wa Autonomous County. Due to the limitation of relevant site selection factors, the final site is located in Lisuo Lahu Township. The total duration of the
project is 12 months, from December 2026 to December 2027. Located in Mangmao Village, Fuyan Town and Nanwai Village, Gongxin Township, Menglian Dai, Lahu and Wa Autonomous County, Pu'er City
, Mengma Tea-Light Complementary Power Generation Project has a total investment of 440 million yuan and a land area of 1,236,500 ㎡. The planned rated capacity of the project is 100MW (AC side) , and the installed capacity of DC side is 130.1068 MWp . A total of 177,016 735 W p monocrystalline silicon double-sided
project is 15 months, from October 2026 to December 2027.
Xinzhai Tea-Light Complementary Power Generation Project (Phase II) is located in Mohei Town and Mengxian Town, Ning'er Hani and Yi Autonomous County, Pu'er City, with a total investment of 546 million yuan . The total floor area is 271. The planned rated capacity of the project is 140MW , and the installed capacity of battery modules is 188.31 MWp . System capacity ratio 1. It is proposed to install 256,200 735 W p monocrystalline silicon N-type double-sided PV modules. The total construction period of this
project is 12 months, from December 2026 to December 2027.
The above three photovoltaic power generation project construction units are China-Guangzhou Nuclear New Energy (Pu'er Tea) Co., Ltd. and the remaining three project construction units are China-Guangzhou Nuclear New Energy (Menglian) Co., Ltd . The controlling shareholders of these two companies are CGN Yunnan New Energy Co., Ltd., which is a subsidiary of CGN Wind Power Holdings.
Mangxin Tea-Light Complementary Power Generation Project is located in Xingang Village, Fuyan Town, Menglian Dai, Lahu and Wa Autonomous County, Pu'er City, with a total investment of 88 million yuan. Total floor area 27. The planned rated capacity of the project is 20 MW (AC side), and the installed capacity of the DC side is 26.
The total construction period of the project is 15 months, from October 2026 to December 2027. Located in Fuyan Town, Menglian Dai, Lahu and Wa Autonomous County, Pu'er City, the Tea-Light Complementary Power Generation Project
of Banshun Tea Factory has a total investment of 220 million yuan . The total floor area is 66. The planned rated capacity of the project is 50 MW (AC side) and the installed capacity of the DC side is 65.
The total construction period of the project is 15 months, from October 2026 to December 2027.
Hong'an Photovoltaic Power Generation Project is located in Zhanglao and Nangen Dazhai, Nayun Town, Menglian County, Pu'er City, with a total investment of 286 million yuan and an area of 806500 ㎡. The planned rated capacity of the project is 65MW (AC side), and the installed capacity of the DC side is 84.
The total construction period of the project is 15 months, from October 2026 to December 2027.