of December 18, the entrance ceremony of the first batch of equipment for the 3GW photovoltaic module project of Huanyu Photovoltaic Technology (Changshu) Co., Ltd. (Hereinafter referred to as "Huanyu Photovoltaic") was solemnly held, marking that the project will soon be put into operation. From the official start of construction
on August 10 to the arrival of the first batch of equipment on December 18, Huanyu Photovoltaic has promoted this advanced photovoltaic module project with intensive technology and materials in an orderly manner. The first batch of equipment entering the site covers the main equipment such as automatic non-destructive scribing machine and automatic high-speed series welding machine, which is the core equipment in the production of N-type components.
The project took only 109 days to complete the formal construction to the top of the plant, followed by 21 days to complete the entry of the first batch of equipment. After the project is put into operation, it will further enhance the supply capacity of Huanyu photovoltaic N-type module products.
It is reported that Huanyu Photovoltaic Technology (Changshu) Co., Ltd. was established in January 2012 and is a technology company specializing in R & D, production and sales of solar photovoltaic modules.