5GW! 10 Photovoltaic Projects in Xinjiang Were Removed from the Grid-connected List

2025-07-01 08:44:43

According to incomplete statistics, as of June 30, 2025, the Xinjiang Construction Corps has publicized the list of 10 photovoltaic projects moving out of the Corps market-oriented grid-connected new energy projects, involving installed capacity of 5G W.

On June 27, the official website of the Development and Reform Commission of the Second Division, the Fourth Division, the Sixth Division and the Tenth Division of Xinjiang Construction Corps announced the list of nine photovoltaic projects moving out of the Corps'market-oriented grid-connected new energy power generation projects, involving a number of state-owned enterprises.

Among them, the official information of the Development and Reform Commission of the Second Division of Xinjiang Construction Corps shows that. China Energy Engineering Group Hunan Electric Power Design Institute Co., Ltd., China Nuclear Huineng Xinjiang Energy Development Co., Ltd., Guodian Investment Shanghai Electric Power Xinjiang Zhenyuan New Energy Co., Ltd. declared three projects to the department, involving 2 million kilowatts of installed capacity of photovoltaic projects. The photovoltaic project of the 200,000-kilowatt green energy park in the 73rd regiment of Kekedala City of

the 4th Division and the 100,000-kilowatt new load supporting photovoltaic project in the 61st regiment of Kekedala City of the 4th Division applied to move out of the list of market-oriented grid-connected new energy power generation projects of the Corps and cancel the development and construction. The owners of the project are China Nuclear Huineng Xinjiang Energy Development Co., Ltd. and Xinjiang North Energy Co., Ltd.

The Sixth Division Zhongxin Electric Power Group Co., Ltd. and the Sixth Agricultural Division Coal and Electricity Co., Ltd. have declared three projects with a total installed capacity of 900000 kilowatts. On June 10, the

Tenth Division China Nuclear Huineng Xinjiang Energy Development Co., Ltd. declared a total of one project with an installed capacity of 800000 kilowatts.

In addition, on 18 June, The Shihezi Municipal Development and Reform Commission of the Eighth Division of the Sinkiang Production and Construction Corps has also issued a report on the removal of the 1GW photovoltaic power generation project of the new power integration 4.6GW (Phase I 2.6GW) photovoltaic power generation project from the market-oriented grid-connected new energy project of the Corps. Publicity of the list.

According to incomplete statistics, as of June 30, 2025, the Xinjiang Construction Corps has publicized the list of 10 photovoltaic projects that have been moved out of the Corps'market-oriented grid-connected new energy projects. The PV installed capacity involved is 5G W .

All can be viewed after purchase
Correlation

According to the incomplete statistics of the digital new energy DataBM. Com, since the second half of 2024, Fujian, Shaanxi and Hebei have announced the abolition or adjustment of new energy projects that do not meet the construction conditions or are overdue for illegal construction, and the number of projects has exceeded 100, including 40 photovoltaic projects, involving nearly 4GW installed capacity.

2025-07-19 11:55:48

On July 16, Huaneng Henan Branch Qingneng Branch issued a pre-tender announcement for PC general contracting of 198 MW centralized photovoltaic project in Ningxia region, and the tenderer was Henan Clean Energy Branch of Huaneng International Power Co., Ltd. The announcement shows that the project is located in Yinchuan City, Ningxia Hui Autonomous Region, with a total capacity of 198 MW (AC side), a DC side capacity of 251 MW 14888, and a 59.4MW/158.4M Wh energy storage device. A 110kV booster station will be built for the project, which is planned to be connected to the substation of the State Grid through a 110kV line.

2025-07-17 16:46:52

On July 9, the Development and Reform Commission of Zhongwei City, Ningxia, issued the "Announcement on Cleaning up and Abolishing New Energy Projects without Construction Conditions in Zhongwei City", and four new energy projects without construction conditions were cleaned up and abolished.

2025-07-11 09:35:08

Golmud East Base in Qaidam Desert is an ultra-supercritical thermal power plant with the largest planned construction capacity, the largest total investment, the highest proportion of new energy and the highest altitude in China.

2025-07-02 10:32:49

According to incomplete statistics, as of June 30, 2025, the Xinjiang Construction Corps has publicized the list of 10 photovoltaic projects moving out of the Corps market-oriented grid-connected new energy projects, involving installed capacity of 5G W.

2025-07-01 08:44:43

On June 23, the Administrative Examination and Approval Service Bureau of Taiyuan City, Shanxi Province, issued a public announcement to make an approval decision on the environmental impact assessment document of the first phase of the 100MW photovoltaic project of Zhongdian Nongchuang (Qingxu) Energy Technology Co., Ltd. The Bureau basically agrees with the overall conclusion of the environmental impact assessment and various measures for ecological environment protection in the Report Form.

2025-06-24 10:21:42

Finally, it was successfully won by Tangxian Wenyuan Electric Power Technology Co., Ltd. at a price of 140 million yuan.

2025-06-19 18:36:38