On September 20, Xinlong Kaisheng Yecheng County 600000 kW Photovoltaic Sand Control Project (EPC) issued a notice of bid rejection.
The announcement shows that as of the date of publication of this announcement, after many written and oral reminders from the tenderer, the winning bidder has not concluded a written EPC general contract with the tenderer within the time limit stipulated in the tender documents without justified reasons , which is deemed to be his abandonment of the winning bid qualification, so the project is abandoned and the tender is rejected. Reorganize the bidding.

It is noteworthy that on June 5, The consortium formed by Southwest Engineering Co., Ltd. of China Railway 15th Bureau Group and Shandong Environmental Energy Design Institute Co., Ltd. with a total 182776 of RMB 5,400 , The unit price is 3.046 yuan/W (calculated by AC side), which wins the bid for EPC general contracting of the project.
It is understood that the tenderer of the project is Xinjiang Xinlong Kaisheng New Energy Co., Ltd., located in Kashgar, Xinjiang Uygur Autonomous Region, with a rated installed capacity of 600 MW . The installed capacity is 720MW, the energy storage is 60MW/120MWh, and the total capacity ratio is 1.2.
The bidding project is divided into one bid section, and the bidding scope includes survey, design, coordination of project formalities, geological survey, feasibility study report, construction and installation of 220kV booster station for supporting construction of photovoltaic power station, namely, all work contents from survey and design to completion acceptance and later quality assurance services.