On July 30, the successful candidate for EPC general contracting of Manmao Photovoltaic Power Generation Project of China Electric Power Construction was announced.
According to the announcement, there are two successful candidates. Among them , the consortium formed by Sinohydro Bureau 10 Co., Ltd. and Yunnan Nengtou Electric Power Design Co., Ltd. bid for 97.958 million yuan . The bid price of 1.399 yuan/W is listed as the first successful candidate.

It is understood that the owner of the project is Longchuan Juyuan New Energy Co., Ltd. The project is located in Chengzi Town, Longchuan County, Dehong Dai and Jingpo Autonomous Prefecture, Yunnan Province. It is planned to build 28 photovoltaic power generation sub-arrays with a rated capacity of 70 MW and an installed capacity of 87.27 MWp, which will be connected to the 35kV switchgear of the 220kV booster station of Qimuwo Guangyou Power Generation Project through three 35kV collector lines. The total construction period of the
project is planned to be 365 calendar days , starting on August 15, 2026, the first batch of photovoltaic array grid-connected power generation on May 15, 2027, and all photovoltaic array grid-connected power generation on July 15, 2027. The project will be completed and accepted on July 25, 2027, and the project will be handed over on August 15, 2027.
浙公网安备33010802003254号