On November 9, the announcement of the rejection of the EPC general contracting project of 100MW household distributed photovoltaic power generation in Etuoke Banner, Ordos City, Inner Mongolia Autonomous Region was issued.
The announcement shows that because the project contractor and the contractor negotiate to determine the termination of the construction contract, the project is abandoned.

The project issued a tender announcement on June 17. It is planned to focus on the areas where residents are concentrated and the conditions of courtyards and roofs are superior in Etuoke Banner. The installed capacity is 100MW (DC side), all of which are household photovoltaics , with a single household record capacity of 60-80 KW. It covers about 1250 households in Etuoke Banner of Ordos City.
On July 14, the announcement of the bidding results of the project showed that Shanxi Qijian Group Co., Ltd. (The leader) and Zhonghuan Urban and Rural Planning and Design Group Co., Ltd. won the project at a bidding price of 200.5 million yuan, with a unit price of 2 yuan/W.
It is noteworthy that on July 25, the official public number of the Energy Bureau of Etuoke Banner, Inner Mongolia, issued a statement that the information of the tender announcement for the EPC general contracting project of 100MW household distributed photovoltaic power generation in Etuoke Banner, Ordos City, was significantly inconsistent with the content of the Bureau's record. Information distortion, suspected of exaggerating the scale of the project, misleading the intention of cooperative enterprises, was ordered to revoke. (For details, please click: Outrageous! Small filing leverages big bidding?
At the same time, on November 9, the EPC general contracting project of 100MW household distributed photovoltaic power generation in Damao Banner, Baotou City, Inner Mongolia Autonomous Region, also issued a notice of bid rejection. The reason is that there are less than three valid bidders.
It is noteworthy that on the day of termination, the second tender announcement was issued for the 100MW household distributed photovoltaic power generation EPC general contracting project in Damao Banner.

On October 29, Damao Banner issued a tender announcement for the EPC general contracting project of 100MW household distributed photovoltaic power generation. The project plans to carry out household photovoltaic construction throughout Damao Banner, focusing on areas where residents are concentrated and courtyards and roofs have superior conditions, with an installed capacity of 100MW (DC side). The registered capacity of a single household is 60-80KW, covering about 1250 households in Damao Banner, with an investment of about 200 million yuan.
Digital New Energy DataBM. Com noted that the bidders of the two abandoned projects were Inner Mongolia Duorui Energy Technology Co., Ltd .