The Digital New Energy DataBM. Com was informed that on October 25, the Jiangxi Development and Reform Commission issued the Notice on Cleaning up Overdue Photovoltaic Projects . Thirty-four projects with a total installed capacity of 2.894 GW were cancelled because they did not start construction.
The original text is as follows:
Notice
of Jiangxi Energy Bureau on the Clearance of Overdue Photovoltaic Projects The Development and Reform Commission (Energy Bureau) of all districts and municipalities, the State Grid Jiangxi Electric Power Co., Ltd., and the Jiangxi Renewable Energy Information Center. Relevant enterprises:
In order to realize the effective allocation of grid access and consumption resources, according to the Notice of Jiangxi Provincial Energy Bureau on the Investigation and Clearance of Stock Wind Power and Photovoltaic Projects (Gan Neng Xin Neng Zi [2023] No.6), the Provincial Energy Bureau organized and carried out the investigation of stock project construction. The requirements for the clean-up work are hereby notified as follows.
As of September 30, 2023, among the photovoltaic projects included in the competitive optimization scheme in 2021, 34 projects with installed capacity of 2.894 million kilowatts have not been started (see Annex 1 for details). According to the requirements, the construction scale of the above projects has been cancelled and the corresponding grid consumption space has been vacated.
For the remaining projects under construction, considering that the enterprise has completed a large investment, after the enterprise has made relevant commitments, it will be postponed to April 30, 2024, and the overdue project will automatically withdraw from the grid to absorb resources. Among them, those completed before December 31, 2023 will implement the energy storage configuration requirements according to the original commitment; those completed between January 1, 2024 and April 30, 2024 will be configured with energy storage according to 15% of its capacity and 2 hours. During the extension period, the power grid enterprises shall continue to handle the project grid connection according to the procedures.