24, Yuneng Science and Technology announced that the company's holding subsidiary, Lingchu Yuneng, had recently signed a purchase contract with Xi'an Xidian New Energy Co., Ltd. for the first bid section of the 200 MW/400 MWh shared energy storage demonstration project on the grid side of Ningxia Taiyangshan Quanyan 330 substation, with a purchase volume of 50 MW/100 M Wh. The products involved in the contract include 200kW/372kWh energy storage integrated cabinet, SCB11-37/3450 box transformer, etc.
The contract amount is about 91.5806 million yuan (including tax).
Yuneng Technologies said that if the contract is fulfilled smoothly, it is expected to have a positive impact on the development and operating performance of the company's energy storage business, which is conducive to enhancing the company's sustained profitability and core competitiveness.