Ignition of a 5 500 t/d clinker production line overseas

2025-05-26 14:32:38

The successful ignition of the rotary kiln not only marks a significant stage achievement in the cooperation between the two sides, but also will have a positive impact on the development of the cement industry in Iraq after putting into operation, effectively improving the local cement production capacity, meeting the market demand and contributing to the infrastructure construction in Iraq.

Recently, the successful ignition of the EP rotary kiln of Lucky Samawah 5500TPD clinker production line in Iraq, which was constructed by Tianjin Cement Institute, marked a phased victory of the project. It has successfully entered the trial production stage.

The clinker line EP project contract was signed in May 2023, which is a clinker line project with a daily output of 5500 tons. The scope of the contract includes design, equipment supply and technical services from raw material crushing to clinker storage. The project site is located in Samawah, southern Iraq, about 350 kilometers from the capital Baghdad. The successful ignition of the

rotary kiln not only marks a major stage achievement in the cooperation between the two sides, but also will have a positive impact on the development of the cement industry in Iraq after putting into operation, effectively improving the local cement production capacity, meeting the market demand and contributing to the infrastructure construction in Iraq.

All can be viewed after purchase
Correlation

The plant, built at a cost of about US $200 million (equivalent to about RMB 1.384 billion), has a planned capacity of 3,500 tons of clinker cement per day, and the first phase of the project is expected to be put into operation in 2027.

2025-06-05 09:56:34

The construction of the production line started in October 2024 and is now progressing smoothly. The construction of supporting facilities such as offices, laboratories and water pump houses has been completed. The civil engineering of the power generation system has been fully completed, and 70% of the equipment installation has been completed. The rest of the infrastructure and equipment installation are progressing in an orderly manner according to the construction plan. It is expected to be completed and put into operation in October this year.

2025-06-03 15:55:21

Anhui Zongyang Conch Cement Co., Ltd. intends to withdraw from two 2500 tons/day cement clinker production lines (1 # kiln and 2 # kiln) in the plant area, and adjust and replace the production capacity to one 5000 tons/day (3 # kiln), one 10000 tons/day (4 # kiln) and two 4500 tons/day (5 # kiln and 6 # kiln) cement clinker production lines in the same plant area.

2025-06-03 10:20:18

The successful ignition of the rotary kiln not only marks a significant stage achievement in the cooperation between the two sides, but also will have a positive impact on the development of the cement industry in Iraq after putting into operation, effectively improving the local cement production capacity, meeting the market demand and contributing to the infrastructure construction in Iraq.

2025-05-26 14:32:38

The announcement shows that Handan Jinyu Taihang Cement plans to build a demonstration project of 9000 t/d low-carbon intelligent environmental protection cement clinker production line, and the withdrawal capacity comes from one 2000 t/d, one 2500 t/d and one 4500 t/d of the same company, with a replacement ratio of 1:1.

2025-05-22 09:32:06

The company can produce 2.5 million tons of high-quality cement and 1.8 million tons of clinker annually. In the first quarter of 2025, the output value reached 9.679 million yuan, an increase of 20% over the same period last year.

2025-05-19 16:44:19

The project plans to invest about 120 million US dollars to build a cement clinker production line with a daily output of 2800 tons and a cement grinding production line with an annual output of 1.2 million tons. However, since its launch in 2015, the construction progress has lagged behind due to various factors and has not yet been put into operation.

2025-05-14 10:40:55

It is understood that the project is the first district, city and county level state-owned capital investment cooperation project in Nyingchi City, which is jointly invested by four state-owned enterprises, namely, Xizang Gaozheng Building Materials Co., Ltd., Xizang Zangjian Cement Co., Ltd., Nyingchi City City Investment Company and Langxian City Investment Company, and will build a modern cement production line in Langxian County.

2025-05-14 10:30:27

Due to market expectations and policy changes, the project has not started construction. According to the Implementation Measures for Capacity Replacement of Cement and Glass Industry (2024 edition), after the application of Huainan Shunyue Cement Co., Ltd. and the report of Huainan Bureau of Industry and Information Technology after review and publicity, the production line relocation plan of the above project is now cancelled.

2025-05-13 10:16:12

The replacement plan shows that the 5000t/d clinker production line project of Yunhan Cement in Yingjiang County, a subsidiary of Conch Cement, supplements 1000t/d production capacity, with a replacement ratio of 1.5: 1. The withdrawn 1500t/d production capacity comes from the 2500t/d clinker production line of Kunming Conch Cement.

2025-05-08 09:30:43

Previously, according to the website of Chongqing Economic and Information Commission, Chongqing Tongliang Southwest Cement Co., Ltd. will withdraw a 2500t/d and a 4800t/d clinker production line for the relocation of a 7300t/d cement clinker production line.

2025-04-28 10:48:33

Municipal key projects in 2025 include "four batches" of projects started, under construction, completed and reserved. Among them, there are 1252 projects under construction, under construction and completed, with a total investment of about 3.2 trillion yuan and an annual planned investment of 480 billion yuan, and 316 reserve projects, with a total investment of about 1.2 trillion yuan.

2025-04-27 14:09:18

The existing new dry process cement clinker production line with a daily output of 2500 tons (Φ4.0 * 60m) will be merged into a new dry process cement clinker production line with a daily output of 4000 tons (Φ4.8 * 72m) (i.e. 2 # clinker line). The total capacity will remain unchanged after the merger.

2025-04-24 10:42:22

Xizang Langxian Gaozheng Building Materials Co., Ltd. intends to build a 4000t/d cement clinker production line project (hereinafter referred to as "Langxian Project") in Nyingchi City Langxian County by means of capacity replacement within the autonomous region.

2025-04-24 09:43:00

Huaxin has been optimistic about Mozambique's economic development for a long time and has continued to increase investment. The 3000t/d clinker production line of Huaxin Mozambique Cement Co., Ltd.'s Nacala Plant was ignited and put into operation on November 29, 2024, and the operation is in good condition.

2025-04-16 11:12:20

According to the statistics of China Cement Network Cement Big Data Research Institute, the current clinker production line under construction has a capacity of 22.712 million tons, of which 8 production lines are expected to be put into operation in 2025, with a capacity of nearly 12 million tons. In addition to the 4500t/d line of Shaanxi Shengwei Building Materials Group, 7 clinker production lines are expected to be put into operation this year.

2025-04-14 13:31:36

The replacement plan shows that Line 3 of Zhejiang Hongshi Cement Co., Ltd. needs to supplement the replacement capacity of 1250t/d, and the production capacity of the production line increases from 4000t/d before the supplement to 5250t/d after the supplement.

2025-04-14 09:59:53

It is understood that in November 2023, the Jiangxi Office of Industry and Information Technology issued the announcement on the production capacity of Fenyi Conch Cement Co., Ltd. with a daily output of 4500 tons of cement clinker, saying that Fenyi Conch Cement Co., Ltd. intends to implement the overall relocation and technical renovation project of cement clinker production line from the city to the park, and will build a 4500t/d clinker production line, which will be built in the city. Withdraw from the company's original 2500t/d and 2000t/d clinker production lines.

2025-04-14 09:53:23

In March 2023, the former Department of Economy and Information Technology of Anhui Province (now the Department of Industry and Information Technology of Anhui Province) announced the relocation plan of the cement clinker production line with a daily output of 4500 tons of Huainan Shunyue Cement Co., Ltd. (Wan Jing Xin Announcement [2023] No.8). Later, due to market expectations and policy changes, the project did not start construction.

2025-04-08 10:34:23

The replacement plan shows that the two 4 500 t/d clinker production lines of Tapai Cement in Huizhou each have a replacement and supplementary capacity of 833 t/d, and the capacity of the two production lines after the replacement is 5 333 t/d.

2025-04-07 10:05:29

According to statistics, since this year, in addition to the above production lines, nine cement clinker production line construction projects have not been promoted, with a total annual production capacity of 13.95 million tons (calculated in 310 days).

2025-04-03 09:44:25

The cooperation between Sinoma International (Nanjing) and Longshan Group began in 2015, and Sinoma International (Nanjing) has undertaken four 6000TPD clinker cement production lines, one grinding station and four transfer station projects, with a cooperation amount of more than 500 million US dollars.

2025-03-24 20:43:15

In July 2024, the promotion meeting of Shandong Lianhe Wangqi Cement 4000t/d cement clinker new dry process production line project was held.

2025-03-19 09:50:21

The production line of Longgou Wannianqing Company in Chongyi County, which is built by Jiangxi Building Materials Group, with an annual output of 800000 cubic meters of concrete, is being vigorously promoted.

2025-03-06 16:25:34

According to the tracking of China Cement Network Cement Big Data Research Institute, there are currently 15 production lines under construction in China, with a total capacity of about 23 million tons.

2025-02-27 09:21:49

Among them, the industrial projects include the 9 MW pure low-temperature waste heat power generation project of Longxiang Building Material's new dry cement production line with a daily output of 5000 tons of clinker.

2025-02-24 17:32:50

Show according to platform of relevant property right trade, many cement asset depreciate recently continue to make over.

2025-02-20 09:36:14

Due to the change of market environment and the adjustment of enterprise strategy, three clinker production lines have been announced to be no longer constructed in 2025, with a total capacity of 4.34 million tons per year (calculated by 310 days).

2025-02-18 09:39:57

This project will not increase the production capacity. After the implementation of the technical transformation, the comprehensive coal consumption per ton of clinker will be reduced by 5.5kgce/t compared with that before the technical transformation, the annual 28644 of raw coal will be saved by tons, the electricity will be saved by 1.86 million degrees, and the annual cost will be saved by about 32.5 million yuan. At the same time, the emission of CO2 and other pollutants will be effectively reduced, which will have good social and ecological benefits.

2025-02-17 09:27:25

To sum up, the responsibility for the feedback of the ecological environment warning film in the Yangtze River Economic Zone in 2023 has not been traced clearly, not to mention that it can play a warning role, and the rectification task has not taken into account the requirement of the unification of the record capacity and the actual capacity. Therefore, the sales number appears to be very hasty and reluctant!

2025-02-15 12:12:57

The successful capping of the kiln tail frame marks that the project has formally entered the installation stage. The project department will carry forward the company's iron army spirit of "being able to bear hardships, fight and dedicate", constantly strengthen safety, quality and progress control, complete various construction tasks with high quality, and ensure that the project is ignited on schedule.

2025-02-08 10:16:27

Under the background of the current market downturn, cement enterprises are facing heavy pressure. The decline of market demand leads to the decrease of cement production and sales, which has a serious impact on the profits and operation of enterprises. In this case, for cement enterprises, new clinker projects should be carefully considered!

2025-01-16 16:59:38

Continued projects include: Handan BBMG Taihang 2 × 4500t/d Cement Kiln Co-processing Solid Waste Production Line Relocation Project (Fengfeng Mining Area).

2025-01-07 11:22:09

In accordance with the requirements of the Ministry of Industry and Information Technology's "Measures for the Implementation of Capacity Replacement in Cement and Glass Industry (2024 edition)" (Ministry of Industry and Information Technology's original [2024] 206) document, after organizing experts'on-site verification and acceptance, the daily production capacity of 800 tons and 1000 tons of clinker production line of Wangqing North Cement Co., Ltd. has been transferred out, the production line has been dismantled, the site has been leveled, and the production line has been completed. It does not have the ability to resume clinker production, which is now announced and the public is welcome to supervise.

2024-12-30 11:15:39

Fujian Moucheng Cement Development Co., Ltd. has shut down and dismantled two Φ4.0 * 60 m cement clinker production lines used for the capacity replacement scheme of the construction project of the cement clinker production line with a daily output of 5000 tons (announced on December 17, 2020).

2024-12-25 14:12:59

The announcement shows that Jiangxi Yudu Southern Wannianqing Cement Co., Ltd. has upgraded the existing 4800 t/d new dry cement clinker production line in the existing plant area, merged the 2000 t/d new dry cement clinker production line of Jiangxi Ganzhou Southern Wannianqing Cement Co., Ltd., located in Luoao Town, Yudu County, and implemented the two-in-one technology by equivalent replacement. The production capacity of cement clinker is increased from 4800 t/d to 6800 t/d.

2024-12-25 13:53:06

According to the announcement, Huaibei Xiangshan Cement Co., Ltd. has withdrawn from cement clinker production due to the construction needs of Huai-Su-Bengbu Intercity Railway, and intends to adjust the capacity of 2000t/d cement clinker production line to 4500t/d and 5000t/d cement clinker production line of Huaibei Zhongcheng Cement Co., Ltd., a wholly-owned subsidiary.

2024-12-10 10:26:20

According to the statistics of China Cement Network, together with Huawo (Shandong) cement production line, 11 clinker production lines have been ignited and put into operation this year, with a capacity of 14.632 million tons (calculated in 310 days).

2024-12-09 11:22:22

The publicized projects are Yunnan Jianfeng Dazhan Cement Co., Ltd.'s 4,000t/d clinker construction project and Maitreya Hongshi Cement Co., Ltd.'s 4,628t/d new dry process cement clinker production line (with 9 MW pure low-temperature waste heat power generation) project.

2024-12-09 09:58:00

It is understood that Huawo (Shandong) Cement Co., Ltd. will build a 4000t/d cement clinker production line with a replacement ratio of 1.25: 1 for two 2500t/d cement clinker production lines.

2024-12-06 11:00:54

According to the tracking of China Cement Network Cement Big Data Research Institute, some production lines will be put into operation until 2025, and no new lines will be put into operation in the fourth quarter. The overall supply pressure is controllable, but the contradiction between supply and demand is highlighted in the downward period of demand, and it is expected that the contradiction between excess capacity will continue to intensify.

2024-11-21 09:54:41

Through field inspection and acceptance, Meizhou Real Madrid Cement Co., Ltd. has shut down and dismantled a cement clinker production line with a capacity of 2500t/d located in Beifang Village, Xinpu Town, Jiaoling County, Meizhou City, Guangdong Province; Yingde Yingma Cement Co., Ltd. has shut down and dismantled a cement clinker production line with a capacity of 600t/d located in Fuyang 2nd Road, Yingcheng Town, Yingde City, Qingyuan City, Guangdong Province. The above two production lines are no longer qualified for production.

2024-10-17 09:57:28

According to the announcement, Guangdong Qingyuan Guangying Cement Co., Ltd. will merge the existing cement clinker production line with a daily output of 2500 tons (Φ4.0 * 60 meters) with the cement clinker production line with a daily output of 4000 tons (Φ4.8 * 72 meters) in the same plant to build a 6500t/d clinker production line, and the total capacity will remain unchanged after the merger.

2024-10-17 09:36:31

The announcement shows that the technical renovation and upgrading project of the cement clinker production line with a daily output of 6000 tons relies on the integration and upgrading of the original site of the 1 # clinker production line with a daily output of 4000 tons and the 2 # clinker production line with a daily output of 3000 tons of Shuicheng Conch Panjiang Cement Co., Ltd. The 2 # clinker production line with a daily output of 3000 tons of Shuicheng Conch Panjiang Cement Co., Ltd. is transferred by reduction and replacement according to the ratio of 1.5: 1.

2024-10-15 10:41:40

The second phase plans to invest 1.4 billion yuan to build the first cement clinker production line with a daily output of 5000 tons, and the third phase plans to invest 1.7 billion yuan to build the second cement clinker production line with a daily output of 5000 tons, a lime production line with a daily output of 1200 tons, a light calcium carbonate production line with an annual output of 100000 tons and an ALC plate production line with an annual output of 500000 cubic meters.

2024-10-14 10:29:55

Line A 5000t/d is used as per 1:1. 2500t/d of Line B is converted to 1666t/d by 1.5: 1, which is combined with the capacity of Line A to 6666t/d. The design capacity of Line A is 4500t/d on the list. How can replacement plan become 5000t/d, which is consistent with the actual capacity calculated by kiln diameter? The actual capacity of Line B is 2833t/d on the list. How can replacement plan be 2500t/d, which is consistent with the design capacity?

2024-09-25 10:01:01

Maitreya Red Lion Cement Co., Ltd. won the mining right of Baituqiang Limestone Mine for Cement in Xunjiansi Town, Maitreya City, Yunnan Province for 68.82 million yuan. It is understood that Red Lion Cement also has a clinker production line project in the local area. The project information is as follows: Maitreya Hongshi Cement Co., Ltd. 4628t/d new dry process cement clinker production line (with 9MW pure low-temperature waste heat power generation) project has been listed as the provincial major project of Yunnan Province in 2024.

2024-09-24 11:26:57

Recently, the Natural Resources and Planning Bureau of Zaozhuang City, Shandong Province, issued the "Shandong United Wangqi Cement Co., Ltd. 4000t/d New Dry Process Cement Clinker Production Line and Waste Heat Power Generation Project Planning Approval Announcement". It is understood that the total investment in the technical renovation of the 4000t/d cement clinker new dry process production line project of Shandong United Wangqi Cement Co., Ltd. is 1 billion yuan. On the basis of the daily production of 2500t/d, the technical renovation of equipment has been upgraded to the 4000t/d new dry process cement clinker production line and the supporting construction of 6MWh waste heat power generation system. To realize the intellectualization, digitalization, energy saving and environmental deepening of production process and equipment level.

2024-09-02 09:58:33

It is reported that the project demolishes a Ф4.2 × 60m 2500t/d new dry clinker production line of Ningxia Yinghai Building Materials Group Co., Ltd. and a Ф4.3 × 64m 2500t/d new dry clinker production line of Ningxia Yinghai Tianyan Building Materials Co., Ltd. A 5000 t/d second-generation new dry process cement clinker production line will be built locally with equivalent replacement, and a 9 MW pure low-temperature waste heat power generation system will be built.

2024-08-27 10:03:38

Since the beginning of this year, the operating pressure of the cement industry has been unprecedented, the overall profit of the industry has suffered a historic loss, and the survival and development of small and medium-sized enterprises have been severely challenged. In view of the current industry situation, it is expected that the release progress of new production capacity will be less than expected.

2024-08-08 09:42:42

The crisis in Bolivia's construction industry is becoming increasingly severe, mainly due to the sharp rise in the price of construction materials. This greatly increases the cost of construction and is detrimental to construction workers. Prices of important building materials have been rising in the past few months, with some tripling. The underlying reasons are closely related to the rising black market price of the US dollar and the shortage of fuel.