On May 21, Hebei Provincial Office of Industry and Information Technology issued the Announcement on the Change of Cement Clinker Production Capacity Relocation Plan of Handan Jinyu Taihang Cement Co., Ltd.
The announcement shows that Handan Jinyu Taihang Cement plans to build a demonstration project of 9000 t/d low-carbon intelligent environmental protection cement clinker production line, and the withdrawal capacity comes from one 2000 t/d, one 2500 t/d and one 4500 t/d of the same company, with a replacement ratio of 1:1. The
planned construction time is January 1, 2026, and the planned ignition and commissioning time is June 30, 2027.
According to the previous release of Hebei Industry and Information Technology Office, the project was originally planned to build a 2 * 4500t/d clinker production line project.