21 July, Jiangsu Provincial Public Service Platform for Tendering and Bidding issued a public announcement that Jiangsu Sheyang Huasheng Company Sheyang Port Zero Carbon Park 150 MW Phase II Fishing-photovoltaic Complementary Power Generation (Section III) project does not adopt the bidding method .
The announcement shows that five public tenders have been conducted in the three bidding sections of the project, because less than three bidders have submitted bidding documents in each public tender. All bids failed . As this project is not a construction project that must be examined and approved, the tenderer Sheyang Huasheng Energy Technology Co., Ltd. has decided not to invite tenders for this project.
The following is the specific bidding round of the third bid section:
According to the data, Sheyang Huasheng Company Sheyang Port Zero Carbon Park 150 MW Phase II Fishing-photovoltaic Complementary Power Generation Project is located in Sheyang Port Economic Development Zone, Sheyang County, Yancheng City, Jiangsu Province. It is divided into three bid sections. About 77,592 pieces of N-type monocrystalline silicon double-sided double-glass 630Wp photovoltaic modules are installed in
one bid section . The AC side capacity is about 42.45 MW, and the DC side capacity is about 48.88 MW; the second bid section is equipped with about 87,192 N-type monocrystalline silicon double-sided double-glass 630Wp PV modules, the AC side capacity is 47.75 MW, and the DC side capacity is about 54.93 MW; The third bid section is for the construction of a 110KV photovoltaic booster station (including related electrical equipment) and related living facilities, about 73.5KM of 35KV collector lines, and about 48 tower foundations.
The Digital New Energy DataBM. Com was informed that the winning bid for the first tender section of the project was announced on July 22, and the winning bidder was China Nuclear Huatai Construction Co., Ltd . The winning bid amount is 91.39995709 million yuan, and the enterprise is a subsidiary of China Nuclear Group.
The second tender section has issued a re-tender announcement on June 27, 2025, but because there are less than three valid bidders, the second tender section re-tender announcement was issued on July 21. On the same day, the second bid section was re-tendered-the second tender announcement was issued.
It is understood that the environmental impact assessment of the Tangmian photovoltaic power generation area (excluding switching stations and supporting transmission lines) of the project has been approved by Yancheng Ecological Environment Bureau on April 17, 2025.