Over 2.3GW! Announcement of 14 Photovoltaic Projects Including Huadian, Huaneng and CGN

2026-08-31 17:38:32

Digital new energy DataBM. Com found that in the past half month, there were 14 photovoltaic projects in Jiangsu, Hebei, Yunnan and other places, with a total scale of 2347 MW and a total investment of nearly 5 billion yuan.

Digital new energy DataBM.

Among them , the largest capacity of a single photovoltaic project is Huaneng Guanyun 500 MW offshore photovoltaic project and Ganzi Daofu Yari Phase II photovoltaic power generation project with a total installed capacity of 500 MW.

From the perspective of project construction units, it includes central enterprises such as Huadian, Huaneng, CGN and China Electric Power Construction .

Details are as follows:

Huadian 200 MW Photovoltaic Project Environmental Impact Assessment Acceptance

On August 26, the Ecological Environment Bureau of Qianxinan Prefecture issued a public announcement on the acceptance of the environmental impact report form of Shuangfeng Photovoltaic Power Station in Zhenfeng County.

超2.3GW!ccement.com/news/2608/richtext/img/6a954a22e4e8f6415715.jpg

The project is newly built, located in Lurong Township and Baiceng Town, Zhenfeng County, Qianxinan Prefecture, Guizhou Province. The total investment is about 7.

The project adopts BC type 650Wp monocrystalline silicon double-sided double-glass battery module 373520 block (182 cells). The total installed capacity of AC side is 200 MW, consisting of 74 photovoltaic power generation units. Including 22 units of 3.3MW, 25 units of 3.0MW, 6 units of 2.7MW, 8 units of 2.1MW, and 13 units of 1. The project also plans to install 667 units of 300 kW " The total construction period of the project is 12 months. It is planned to start construction in December 2026 and complete in December 2027.

Expansion!

The project is an expansion project, located in Dongli Village, Sidu Town, Zhaoan County, with a total investment of 2. The installed capacity of the AC side of the project is 50 MW. The installed capacity of DC side is 67.

The construction period of the project is 16 months. ( " It is reported that the construction of the project has been started in July 2025. As of January 2026, the installation of photovoltaic array brackets is being carried out in Block 4 of the original EIA approval, and no construction has been started in other areas. In the process of land acquisition, due to land circulation, it is necessary to reduce the scope of the original EIA red line and relocate outside the scope of the original EIA red line, and the construction of the relocated land has not started. After the

adjustment, the AC side installed capacity of the project is 200MW , 620 Wp monocrystalline silicon component 416832 blocks are installed, 62.67 hm2 of land that cannot be implemented within the scope of the original EIA land acquisition is cancelled, and 150.72 hm2 of the original EIA land area is used. The new photovoltaic area covers an area of 150.

The construction period is 8 months. (Related reading " According to the announcement, the project is located in Fengshan Town, Fengqing County, Lincang, Yunnan Province, with a total investment of 400 million yuan . Fengqing Juyuan New Energy Technology Co., Ltd., a subsidiary of China Electric Power Construction , is responsible for the construction. The PV power station installed on the

DC side of the project has a capacity of 110.MWp 19456 and a rated AC capacity of 100MW , consisting of 30 PV arrays. Including 10 X 4.16 MW, 10 X 3.84 MW, 10 X 2.

over 2.3GW!

The construction period of the project is 12 months , and the construction is expected to start in August 2026. It will be completed and connected to the grid in August 2027.

Shanxi 200 MW Photovoltaic Power Station Project was approved

on August 22. Yuci Branch of Jinzhong Ecological Environment Bureau of Shanxi Province issued a notice to approve the EIA report form of Yuci Zhizhen System-friendly New Energy Power Station Project.

Over 2.3GW!

The construction period of the project is 12 months.

On August 21, Jiangsu Nantong Rudong County Data Bureau issued an announcement on the approval decision of the environmental impact assessment document of the 30 MW fishing-photovoltaic complementary photovoltaic power generation project in Rudong County.

The project is located in Ginkgo Village, Yeyingjiao Village, Dingzi'an Village and Zhoudian Village, Juegang Town, Rudong County, Nantong City, Jiangsu Province, and is constructed by Power Investment Zheyuan (Nantong) Intelligent Energy Co., Ltd. The total investment of

the project is 90 million yuan , and the AC side installed capacity is planned to be 30 MW. The construction content includes the use of 51072 block monocrystalline silicon 710 Wp photovoltaic modules, and the proposed "full access to the grid" mode.

Huaneng Guangdong 45MW Distributed Photovoltaic Project has been put on record through the

online approval and supervision platform of investment projects in Guangdong Province. On August 20, Huaneng Shantou Chenghai District Longdu Town Rural Public Infrastructure Distributed Photovoltaic Project was put on record.

The record information shows that the construction unit of the project is Huaneng (Guangdong) Energy Development Co., Ltd. Shantou Power Plant, with a total planned investment of 1. The project mainly includes monocrystalline silicon photovoltaic modules, inverters, brackets, cables, power distribution devices, etc.The

project filing and declaration date is August 19, 2026, and the starting and ending period is March 1, 2027. The construction period of the project is 12 months, and the annual power generation is estimated to be about 49.5 million kWh after completion.

Over 2.3GW!

The project is a new one, located in the hillside area near Beize Village Committee, Yinyuan Town, yuanjiang County, Yuxi City, and is constructed by CGN Yuxi yuanjiang Wind Power Co., Ltd. The total investment is about 1.

超2.3GW!ccement.com/news/2608/richtext/img/6a954a22e039a626497.jpg

The total installed capacity of the project is 30.08 MW on the AC side , and 10 photovoltaic sub-arrays are constructed. 2 PV sub-arrays of 3.52 MW, 4 PV sub-arrays of 3.20 MW, 1 PV sub-array of 2.88 MW, 2 PV sub-arrays of 2.56 MW and 1 PV sub-array of 2.The

project construction period is 6 months . Announcement

of CGN 170 MW Photovoltaic Project On August 19, the Ecological Environment Bureau of Lincang City, Yunnan Province, issued an announcement on the proposed approval of the EIA documents of Heimatang Photovoltaic Power Generation Project. Located in Aihua Town, Yunxian County, Lincang City, Yunnan Province, the project is constructed by CGN New Energy (Yunxian County) Co., Ltd. with a planned rated capacity of 170MW . The main construction contents of

the project include photovoltaic array, tower base of collector line, box transformer, booster station, living area, operation and maintenance center and supporting transportation, communication and power supply facilities.

It is noteworthy that on August 27, 2025, the Heimatang Photovoltaic Power Generation Project held a commencement ceremony in Toudaoshui Village, Aihua Town, Yunxian County, Lincang City, Yunnan Province. Estimated Total Investment of the Project 6. (Related Reading : Announcement of GNPC 170 MW Photovoltaic Project! 9); ">  over 2.3GW! Ccement. Com/news/2608/richtext/IMG/6a954a230665f6400333. </span></p><p style= The total investment is about 3.

The main construction of the project is 122. (

It is understood that the project site relies on the existing sea area of Huaneng Guanyun offshore wind power, with a planned installed capacity of 500 MW and a planned sea area of about 700 hectares.

Over 2.3GW! of 1200MW in Lianyungang area.

Sichuan 500MW Photovoltaic Project Announcement

On August 17, the Bureau of Ecology and Environment of Ganzi Prefecture, Sichuan Province, issued a public announcement of the approval opinions on the environmental impact assessment document of Ganzi Daofuyari Phase II Photovoltaic Power Generation Project.

The project is located in Seka Township, Daofu County, Ganzi Prefecture. It is planned to build a 500MW photovoltaic power station and a supporting 220kV booster station. The station is equipped with a 125MW/250MWh energy storage area and a total of 730Wp monocrystalline silicon double-sided battery modules for 751856. The construction period of the project is 18 months. The construction unit of the

project is Daofu Shudao Clean Energy Co., Ltd., which is indirectly owned by Shudao Investment Group Co., Ltd. and Sichuan Road and Bridge Construction Group Co., Ltd. ( " According to the previously issued pre-announcement of land acquisition for the project, Hebei Provincial Department of Natural Resources approved the conversion and expropriation of collective agricultural land 0.

over 2.3GW!

Total investment 5. Construction period is 12 months. Announcement

of

Yunnan 50MW Photovoltaic Project On August 17, the Bureau of Ecology and Environment of Lincang City, Yunnan Province, issued a public announcement on the proposed approval of the EIA of Geely Linguang Complementary Photovoltaic Power Generation Project (Phase II).

The project is located in Zhongchang Village, Junsai Township, Zhenkang County, Lincang City, Yunnan Province, with a total investment of about 1.

It is mainly composed of PV array, inverter, box-type transformer, 35kV collector line and one 220kV booster station. The project is divided into 16 projects. 3

. The construction period of the project is 6 months.