On July 7, the Bureau of Ecology and Environment of Anshun City, Guizhou Province, issued a public announcement on the acceptance of environmental impact assessment of three photovoltaic power station projects.
The projects are Xingnong Photovoltaic Power Station in Baiyan Town , Puding County, Harmonious Photovoltaic Power Station in Maodong Township, Puding County, and Shiban Photovoltaic Power Station in Pingshang Town, Puding County.
The EIA content shows that the three projects are all new projects , which are constructed in the mode of complementary agriculture and light. It is constructed by Puding Lianxin Energy Development Co., Ltd . Details are as follows:
According to the environmental impact assessment data of Xingnong Photovoltaic Power Station
in Baiyan Town, Puding County, the construction site of the project is located in Huachu Town, Machang Town and Chuandong Street, Puding County, Anshun City, Guizhou Province, with a planned land area of 2,430.72 mu and a total investment of 380 million yuan.
The Project plans to install 178,386 solar cell modules of 730Wp in the sloping fields of the tea garden, which are divided into 11 sub-arrays of 1.0MW, 14 sub-arrays of 1.6MW, 5 sub-arrays of 2.0MW and 18 sub-arrays of 3.2MW, and the actual installed capacity at the DC side is 130.MWp 22178. Rated installed capacity of AC side is 100M W. According to the environmental impact assessment data of Harmony Photovoltaic Power Station
in Maodong Township
, Puding County, the construction site of the project is located in Chuandong Street, Yuxiu Street and Huachu Town, Puding County, Anshun City, Guizhou Province, with a planned land area of 2,298.18 mu and a total investment of 380 million yuan.
In this project, it is planned to install 178,386 730Wp solar cell modules on the sloping land of the tea garden, which are divided into four 1.0MW sub-arrays, four 1.6MW sub-arrays, seven 2.0MW sub-arrays and 124 3.2MW sub-arrays, and the actual installed capacity at the DC side is 130.MWp 22178. Rated installed capacity of AC side is 100M W. According to the environmental impact assessment data of Shiban Photovoltaic Power Station
in Pingshang Town
, Puding County, the construction site of the project is located in Chuandong Street, Yuxiu Street and Huachu Town, Puding County, Anshun City, Guizhou Province, with a planned land area of 3,076.61 mu and a total investment of 380 million yuan.
The Project plans to install 178,386 solar cell modules of 730Wp in the sloping fields of the tea garden, which are divided into 6 sub-arrays of 1.0MW, 3 sub-arrays of 1.6MW, 7 sub-arrays of 2.0MW and 24 sub-arrays of 3.2MW, and the actual installed capacity at the DC side is 130.MWp 22178. Rated installed capacity of AC side is 100M W.