On December 24, Jingao Science and Technology Qujing Base in Yunnan Province solemnly held the commissioning ceremony of 10g W high-efficiency battery and 5G W high-efficiency component projects. After the project is put into operation, it means that Jingao will take the lead in completing the whole industrial chain layout of silicon rod-silicon wafer-battery-component in Qujing.
It is reported that Jingao Qujing Phase III project was signed in March 2022, construction started in July, battery production equipment began to be installed in June 2023, and the first battery was offline on July 16.
As the first batch of photovoltaic enterprises stationed in Qujing, Yunnan, Jingao has implemented three consecutive projects since 2017, with a cumulative investment of more than 12 billion yuan, and Qujing has become one of the largest photovoltaic industry chain production bases in the world.