The Digital New Energy DataBM. Com was informed that on August 3, The People's Government of Jiangyin City, Jiangsu Province issued a public announcement on the environmental impact report form of the fishing-photovoltaic complementary power generation project (re-submitted for approval) of the State Power Investment Jiangyin Huangtuli Port of Wuxi Xinggang New Energy Co., Ltd .
According to the announcement, the project is a new one, located in Huangtu Town (Huinan Village, Changzeqiao Village), Ligang Street (Xishiqiao Community, Houmei Community, Jiangshi Village, Cangshan Village, Weichang Village), Lingang Economic Development Zone, Jiangyin City, Wuxi City, Jiangsu Province. The total investment is 490 million yuan , which is constructed by Wuxi Xinggang New Energy Co., Ltd. with a total land area of about 2935.6 mu. The installed capacity of

the project is 153.1152 MWp on the DC side and 130 MW on the AC side. The scheme of block power generation and centralized grid connection is adopted. Considering the convenience of system installation and maintenance, the grid-connected power generation system is divided into 52 photovoltaic subsystems. Monocrystalline silicon double-sided components with power of 720Wp are used. Each subsystem is connected to the inverter in series through 2 * 14 and 2 * 28 groups. After the DC is converted into AC, it is connected to the box-type transformer to form the wiring of the box-type transformer unit of the subsystem.
It is worth noting that the project has obtained the administrative approval of Jiangsu Jiangyin Lingang Economic Development Zone Management Committee on July 14, 2025, and started construction in November 2025. At present, the construction has not been completed, and this is a major change for re-approval .
The EIA document shows that the main reason for this change is that during the construction and implementation of the project, the location of some areas in the photovoltaic area has changed due to the problem of land lease. The details are as follows:

The project is scheduled to be completed in December 2026, with a total construction period of 12 months .