On October 16, the Bureau of Ecology and Environment of Ganzi Prefecture, Sichuan Province, issued an announcement on the acceptance of the ecological environmental impact assessment documents for the construction projects of Daofu Gehapu Phase I 500MW Photovoltaic Project and Daofu Gonglu Phase II 1.3 MW Photovoltaic Project. Located in Taining Town, Daofu County, Ganzi Prefecture, Sichuan Province, Daofu Shudao Clean Energy Co., Ltd. is responsible for the construction of
the 500MW photovoltaic power generation system; A new 220kV booster station (including 150MW/300 MWh energy storage area) will be built. The total installed capacity of the AC side of the

project is 500MW , and 557.4348 MWp is installed on the DC side, including 91 units with a nominal capacity of 5.52 MW (the installed capacity of the DC side is 6.0372 MWp, and the installed capacity of the AC side is affected by the capacity reduction. 5.38 MW ~ 5.52 MW) and two arrays with nominal capacity of 3.68 MW (DC side installed capacity of 4.0248 MWp and AC side installed capacity of 3.592 MW due to capacity reduction).
This project plans to use 864240 block N-type 645 Wp monocrystalline silicon double-sided double-glass photovoltaic modules . The preliminary arrangement of the
project is from April 2027 to June 2028 with power generation conditions , and the total construction period of the project is 15 months .
Daofu Gonglu Phase II 1.3 million kilowatt photovoltaic project is located in Bamei Town, Seka Township, Longdeng Township and Muru Township, Daofu County, Ganzi Xizangan Autonomous Prefecture, Sichuan Province, and is constructed by Daofu Shudao Clean Energy Co., Ltd. The construction includes the construction of a new 1300 MW photovoltaic power generation system; Three 220kV booster stations are newly built (1 # booster station contains 270MW/540MWh energy storage area, 2 # booster station contains 120MW/240MWh energy storage area, and 3 # booster station contains 51MW/102MWh energy storage area). The rated capacity of the

project is 1300MW , and the project is divided into 244 PV arrays; each PV array is provided with 1 box-type transformer, totaling 244 sets; Each fixed subarray is connected in parallel with 195 ~ 376 kebabs photovoltaic strings, which are connected with 26 645 Wp monocrystalline silicon double-sided modules kebabs, and each photovoltaic array is connected with 7 ~ 13 460 kW string inverters . 2081716 block N type 645 Wp monocrystalline silicon double-sided battery module is proposed to be used
in this project. The preliminary arrangement of the
project is from April 2027 to December 2028 with power generation conditions , and the total construction period of the project is 21 months .