On October 16, Chongqing Tongnan District Ecological Environment Bureau issued a public announcement on the acceptance of the EIA documents of "Chongqing Huadian Tongnan Mixin Composite Photovoltaic Power Generation Project" and "Chongqing Huadian Tongnan Yuxi Composite Photovoltaic Power Generation Project".
According to the announcement, Chongqing Huadian Tongnan Mixin Composite Photovoltaic Power Generation Project , with a total investment of 132.09 million yuan , is located in Mixin Town and Yuxi Town, Tongnan District, Chongqing, and is a new project. It is constructed by Chongqing Tongnan Huadian Xinneng Energy Co., Ltd. and adopts "photovoltaic + agricultural planting". The

installed capacity of the project is 80 MW, and the installed capacity of the DC side is 104.31792MWp. It is planned to use 655 Wp single-crystal double-sided components , with a total of 159264 blocks. Every 28 PV modules form a PV string, with a total of 5688 strings.
The project is divided into 42 PV arrays, each 1.25/1.6/2/2.5MW PV array is equipped with one 1.25/1.6/2/2.5MVA step-up transformer. There are 3 1.25MW PV arrays, 11 1.6MW PV arrays, 15 2MW PV arrays and 13 2.5MW PV arrays. The construction period of the
project is 12 months.
Chongqing Huadian Tongnan Yuxi Composite Photovoltaic Power Generation Project , with a total investment of 357 million yuan , is located in Yuxi Town and Qunli Town, Tongnan District, Chongqing. It is a new project, which is constructed by Chongqing Tongnan Huadian Xinneng Energy Co., Ltd. It adopts "photovoltaic + agricultural planting". The
installed capacity of the project is 79.99 MW , and the installed capacity of the DC side is 106.5M Wp. It is planned to use 655 Wp single- crystal double-sided components , totaling 162596 blocks. There are 5175 groups arranged on 2 × 14 brackets and 1264 groups arranged on 2 × 7 brackets.
The project is divided into 40 photovoltaic arrays. Including 3 photovoltaic arrays of 0.8 MW, 2 photovoltaic arrays of 1.0 MW, 2 photovoltaic arrays of 1.25 MW, 8 photovoltaic arrays of 1.6 MW, 9 photovoltaic arrays of 2 MW, 12 photovoltaic arrays of 2.5 MW and 5 photovoltaic arrays of 3.0 MW. The construction period of the
project is 12 months.