, 2026, the Development and Reform Commission of Hebei Province issued the Announcement on the Proposed Adjustment of Wind Power and Photovoltaic Projects Due to Participate in the Centralized Grid-connected Action in 2025.
According to the announcement, there are 31 wind and solar projects involved, with a total capacity of 3.3885 million kilowatts. Among them, there are five photovoltaic projects with a scale of 633000 kilowatts .
Digital New Energy DataBM. Com noted that 30 of the 31 wind and solar projects to be adjusted were delayed in grid-connected time limit and one photovoltaic project was reduced in scale. Of the five photovoltaic projects
to be adjusted, two projects have been extended to September 30 , 2026, and two projects have been extended to December 31 , 2026. In addition , the construction scale of the State Power Investment Jingxing 200 MW photovoltaic power generation project was reduced to 127,200 kilowatts.
From the point of view of project owners, five photovoltaic projects involve enterprises such as State Power Investment Corporation , Datang Group and China Electric Power Construction Corporation.
The original text is as follows:

In order to do a good job in the management of wind power and photovoltaic power generation projects during the alternation period of new and old policies, upon the application of each city, the proposed adjustment of wind power and photovoltaic power generation projects due to participate in the centralized grid-connected action in 2025 will be publicized. The list of specific projects and adjustment opinions are shown in the annex.
In accordance with the requirements of the Measures for the Development and Construction of Wind Power and Photovoltaic Power Generation Projects in Hebei Province (Trial Implementation), the municipalities are requested to further strengthen the management of wind power and photovoltaic power generation projects, and to promote the completion of follow-up projects in strict accordance with the time limit for grid-connected projects, except for objective factors such as force majeure, which cause the projects to fail to put into operation at full capacity on schedule. All projects that are not connected to the grid will be cancelled and the scale of projects that are not connected to the grid will be reduced.
The publicity time is from January 12 to January 16, 2026. During this period, if there is any objection, please report it to the New Energy Division of the Provincial Development and Reform Commission (Energy Bureau).
Contact number: 0311 — 88600512 (fax)
E-mail: nyjxnyc@hbdrc.gov.cn
Attachment: Statistical Table
of Proposed Adjustment of Expired Wind Power and Photovoltaic Projects Hebei Development and Reform Commission Annex of January 12