On July 28, the EPC general contracting project of Shuan 200MW photovoltaic project in Shucheng County, Anhui Province and the EPC general contracting project of Ji'an 200MW photovoltaic project in Yeji District, Anhui Province announced the successful candidates respectively.
Among them, in the Shuan 200 MW photovoltaic project in Shucheng County, China Energy Construction Group Co., Ltd. ranked the first candidate with a 16991 of 10.59 million yuan .

The project is located in Nangang Town, Baishenmiao Town and Ganchahe Town, Shucheng County, Lu'an City, Anhui Province, with a total area of about 4050 mu. The current land use is mainly tea gardens, pits and ponds, and the terrain is hills and plains. The designed rated capacity of AC side of the
project is 200MW , the installed capacity of DC side is 255.5M Wp, and the capacity ratio is 1.2775. The power station adopts the scheme of block power generation and centralized grid connection. The system is divided into 26 3.2M W photovoltaic power generation units, 21 2.6MW photovoltaic power generation units, 5 2.0MW photovoltaic power generation units, 19 1.6MW photovoltaic power generation units and 26 1.0MW photovoltaic power generation units.
The bidding contents include but not limited to: survey and design involved in the project; procurement, transportation, acceptance and storage of materials and equipment; construction preparation and construction, equipment installation and commissioning of all works of the project; all inspection, test and acceptance work involved in the project; trial operation work after project acceptance; Handover of production, completion acceptance and service work within the warranty period.
The project is planned to start on July 30, 2026 in the photovoltaic field area, complete the power collection line and electrify the photovoltaic field area before December 20, 2026, and complete the full-capacity grid-connected power generation before May 30, 2027. In the 200MW photovoltaic project of Ji'an
in Yeji District, Anhui Mingdu Energy Construction Group Co., Ltd. ranked the first candidate with a 20747 of 66.79 million yuan.

The project is located in Sanyuan Town, Silin Village, Wangdian Village and Longyuan Village, Yeji District, Shucheng County, Anhui Province, with a total area of about 4050 mu, and the current land use is mainly pits and ponds. Bidding content and scope
of the project: EPC general contracting of the project includes photovoltaic area and power collection line, including but not limited to: survey and design involved in the project; procurement, transportation, acceptance and storage of materials and equipment; construction preparation and construction, equipment installation and commissioning of all works of the project; All inspection, test and acceptance work involved in this project; commissioning work after project acceptance; handover of production, completion acceptance and service work within the warranty period, etc.
The project is planned to start on July 30, 2026 in the photovoltaic field area, complete the power collection line and electrify the photovoltaic field area before December 20, 2026, and complete the full-capacity grid-connected power generation before May 30, 2027.