EPC Bidding for Huadian Inner Mongolia 1G W Photovoltaic Sand Control Project

2026-11-25 10:23:56

On November 20, Inner Mongolia Huadian Luanjingtan 1.5 million kilowatt photovoltaic sand control project photovoltaic EPC general contracting section I issued a tender announcement, the tenderer is Inner Mongolia Huadian Luanjingtan Green Energy Co., Ltd. The planned photovoltaic capacity of the project is 1.5 million kilowatts, the supporting ecological treatment is 60,000 mu, the capacity ratio is 1:1, two 220KV booster stations are planned to be built, and the total construction period is 365 days. This tender corresponds to a number of tasks within the scope of the 1 million kilowatt photovoltaic project, and defines the corresponding performance requirements for independent bidding and consortium bidding. Some key equipment is purchased by the tenderer.

On November 20 , Inner Mongolia Huadian Luanjingtan Green Energy Co., Ltd. issued a tender announcement for the EPC general contracting section of Inner Mongolia Huadian Luanjingtan 1.5 million kilowatt photovoltaic sand control project.

The announcement shows that the project has a planned photovoltaic capacity of 1.5 million kilowatts and a supporting ecological control area of 60000 mu (including land for photovoltaic projects). The total AC side capacity is 1500. The 09000 is MW, the total DC side capacity is 1500. The 12604 is MWp, and the capacity ratio is 1:1. It is proposed to build two 220KV booster stations in the north and south. The two 220KV booster stations are connected to Tengger 500KV substation through one 220kV line respectively. The transmission distance is about 47.2km. The transmission line is proposed to be invested and constructed by the power grid company (the final scheme is subject to the approval of the access system). The total duration of the

华电内蒙古1GW光伏治沙项目EPC总包招标1

project is 365 days.

The bidding project is divided into one bidding section. Photovoltaic power station EPC general contracting – Photovoltaic EPC general contracting bid section 1 1 million kilowatt photovoltaic power generation project and supporting 35 kV collector line, maintenance road, photovoltaic field fence (including gate), Pavement hardening (about 5km) of the access road (from the level crossing to the gate of the attended booster station), survey and design of two 220kKV booster stations (each with a capacity of 750,000 kilowatts), building installation and construction, equipment and material procurement ( inverter , box transformer, 220kV GIS, Reactive power compensation system equipment and prefabricated cabin, 35kV switch cabinet and prefabricated cabin, grounding transformer and small resistance complete equipment, 35kV station transformer and 400V power distribution equipment, diesel generator, electrical secondary equipment and prefabricated cabin, remote viewing technology defense system and other equipment are excluded; Photovoltaic modules , brackets and main transformers are purchased by the tenderee. Included in the form of provisional estimate), transportation, storage, secondary reshipment, commissioning, test, acceptance, full coverage of 5G network in the equipment area of booster station, quality warranty period service, creation of high-quality projects, environmental protection, land reclamation, vegetation restoration, compliance formalities, etc., and cooperate and coordinate the relevant work within the scope of responsibility of the tenderee. In terms of

performance requirements, independent bidders are required to bid from January 1, 2021 to the deadline for bidding (subject to the time of operation). It shall have at least two commissioning performances of PV construction (or EPC, PC) general contracting projects with a single project capacity of 200 MW and above and at least one commissioning performance of gathering station (or substation) construction (or EPC, PC) general contracting projects with a voltage level of 220KV and above. The bidder of

consortium bidding shall meet the following requirements: from January 1, 2021 to the deadline of bidding (subject to the time of commissioning). It shall have at least two commissioning performances of photovoltaic construction (or EPC, PC) general contracting projects with a single project capacity of 200 MW and above and at least one commissioning performance of gathering station (or substation) construction (or EPC, PC) general contracting projects with a voltage level of 220 kV and above. From January 1, 2021 to the deadline for bidding (subject to the time of signing the contract), the members of the consortium shall have at least one contract performance of photovoltaic construction (or EPC, PC) general contracting project.

All can be viewed after purchase
Correlation

On November 20, Inner Mongolia Huadian Luanjingtan 1.5 million kilowatt photovoltaic sand control project photovoltaic EPC general contracting section I issued a tender announcement, the tenderer is Inner Mongolia Huadian Luanjingtan Green Energy Co., Ltd. The planned photovoltaic capacity of the project is 1.5 million kilowatts, the supporting ecological treatment is 60,000 mu, the capacity ratio is 1:1, two 220KV booster stations are planned to be built, and the total construction period is 365 days. This tender corresponds to a number of tasks within the scope of the 1 million kilowatt photovoltaic project, and defines the corresponding performance requirements for independent bidding and consortium bidding. Some key equipment is purchased by the tenderer.

2026-11-25 10:23:56

Digital New Energy DataBM. Com learned that on March 10, the announcement of the fourth and fifth bidding sections of EPC competitive consultation for 420 MW roof photovoltaic power generation project in Qixingguan Industrial Park, Bijie City, Guizhou Province was issued.

2026-03-11 17:47:11

On July 1, Gansu Provincial Public Resources Trading Center issued a tender announcement for the 200 million photovoltaic power station project in Yuzhong County. The tender unit is Yuzhong Mingwei Bioenergy Technology Co., Ltd. The announcement shows that the project is located in Wujiayao Village, Weiying Township, Yuzhong, Lanzhou City, Gansu Province, with a total investment of 639.21 million yuan, a construction scale of 200MW and a DC side installed capacity of 238.508 MWp.

2025-07-07 09:45:20

Sired Harden continues to provide global customers with solid waste recycling pretreatment solutions, helping to transform domestic waste into alternative fuels, and supporting the optimization of energy structure and the synergistic utilization of solid waste in the cement industry.