China Resources Power 340 MW Photovoltaic Project General Contracting Project Bidding!

2025-06-05 09:57:20

Digital New Energy DataBM. Com learned that on June 3-4, China Resources Group issued two tender announcements for general contracting of photovoltaic projects with a total capacity of 340 MW.

Digital New Energy DataBM. Com learned that on June 3-4, China Resources Group issued two tender announcements for general contracting of photovoltaic projects with a total capacity of 340 MW.

Guangdong Yunfu Yunan Runhe 300 MW Composite Photovoltaic Project (Zone III) Photovoltaic Field Area I Bid Section PC General Contracting Project Tender Announcement

On June 3, China Resources Group issued a tender announcement for Guangdong Yunfu Yunan Runhe 300 MW Composite Photovoltaic Project (Zone III) Photovoltaic Field Area I Bid Section PC General Contracting Project. The tenderer is China Resources New Energy (Yunfu Yunan) Co., Ltd., the project site is Yunan County, Yunfu City, Guangdong Province, and the project scale is 300 MW.

The announcement shows that the project is contracted by PC general contracting mode, the installed capacity of DC side is 94. 12592 MWp, and the total installed capacity of AC side inverter is 76 MW. The content of this

tender is mainly divided into equipment procurement and construction work related to the construction and installation of the photovoltaic field area, as shown in the following figure:

The project will start on July 1 this year, and the foundation of the photovoltaic field will start on July 20. The installation of PV modules will be started on August 10 , and the time for full capacity grid-connected power generation will be December 10, 2025; the completion acceptance will be conducted on March 10, 2026.

It should be noted that the above time nodes are tentative, subject to the written notice of the tenderee. The relative construction period and the total construction period remain unchanged during the contract performance period, and the total construction period from commencement to completion acceptance is 253 calendar days. Due to natural disasters and force majeure, the construction period shall be postponed accordingly.

The project requires the tenderer to have three or more qualifications for general contracting of power engineering construction, and to have two or more new photovoltaic projects (single project capacity not less than 50 MWp) from January 1, 2020 to the deadline for bidding. However, the EPC general contracting of the new project in the photovoltaic field area is undertaken by the design unit alone, except that the PC part is subcontracted to the construction general contractor. Consortium bidding is not allowed

in this tender. Bid

closing/opening time: 2025/06/25 09:30:00 (Beijing time)

Peixian Rundian New Energy Co., Ltd. China Resources Power Peixian Smart Energy 500MW Photovoltaic Base Phase II (First Batch)

40MW Project Photovoltaic Field EPC General Contracting Project Tender Announcement

On June 4, China Resources Group issued a tender announcement for EPC general contracting project of photovoltaic field area of Peixian Intelligent Energy 500MW Photovoltaic Base Phase II (the first batch) 40MW project of China Resources Power Peixian Rundian New Energy Co., Ltd. The tenderer is Peixian Rundian New Energy Co., Ltd. The

contents of the tender are the survey and design of the project's photovoltaic field (including collector lines), the procurement of equipment and materials (except photovoltaic modules), transportation and storage, supervision, installation (including the installation of photovoltaic modules and brackets supplied by Party A), and construction. Relevant civil coordination, test and inspection test, system commissioning, trial operation, defect elimination, training, acceptance, final delivery and production, quality assurance, etc. during the project process, including all materials, spare parts, special tools, consumables and relevant technical data, etc.; project insurance during the construction period; Project acceptance (including quality supervision, grid connection and other special acceptance and completion acceptance), handover and services within the warranty period.

The announcement shows that the tender delivery period/construction period is July 21, the construction time of photovoltaic field foundation is August 15, the installation time of photovoltaic modules is October 25, the full capacity grid-connected time is December 20, and the completion acceptance is March 20, 2026. The bidding for the

project requires the bidder to have at least one main engineering design performance of the photovoltaic field of the fishing-photovoltaic complementary photovoltaic power generation project of 40 MW or more from January 1, 2021 (inclusive) to the deadline for bidding. It has the performance of the completed EPC or PC general contracting project of the main project of the photovoltaic field of a 40 MW and above fishing-photovoltaic complementary power generation project.

The project allows consortium bidding, but the number of members does not exceed 2. Bid

closing/opening time: 2025/06/25 09:30:00 (Beijing time).

All can be viewed after purchase
Correlation

The tender announcement shows that the project is a turnkey project of EPC general contracting, regardless of whether it is mentioned in the tender document or not. Involving the design, construction, procurement (excluding PV modules), completion and commissioning, project inspection, file acceptance, completion settlement, cooperation with power quality supervision acceptance, quality supervision acceptance of local functional departments, acceptance of other projects, overall completion acceptance, cooperation with grid connection formalities in this bid section, Work contents such as network test and related costs (including the part to be borne by the Tenderee) are within the scope of work of the Tenderer.

2025-08-11 18:02:47

On July 29, Anhui Xuancheng Public Resources Trading Supervision and Administration Bureau issued a tender announcement for the 15.8 MW distributed photovoltaic power generation project of Ningguo Cement Plant of Anhui Conch Cement Co., Ltd. The tenderer is Ningguo Conch New Energy Co., Ltd.

2025-08-06 17:44:31

This tender requires the bidder to have good operation, business reputation and corresponding qualifications. In terms of performance, the bidder is required to have at least one domestic single 100MW or above photovoltaic project performance from January 1, 2022 to the deadline for bidding.

2025-08-05 09:05:41

On August 1, two tender announcements were issued for EPC general contracting of 150 MW photovoltaic power generation project in Sanhe Village, Guangde City, and EPC general contracting of 150 MW photovoltaic power generation project in Shanbei Village, Guangde City. The planned AC side installed capacity of the two projects in this tender is 150 MW, and the tentative DC side installed capacity is 180.0036 MWp. The construction unit is Guangde Huichen New Energy Co., Ltd., which is a subsidiary of CNNC.

2025-08-04 17:14:00

On July 29, the bidding results of PC general contracting project procurement (re-bidding) of CGN New Energy Shanxi Lingchuan 33MW Distributed Photovoltaic Project were announced.

2025-07-30 10:17:47

The project is located in Shouguang City, Weifang City, Shandong Province. It is a beach salt field photovoltaic project. The total installed capacity of AC side is 220 MW, and the installed capacity of DC side is 243.412 MWp. It is planned to select 620Wp and above N-type monocrystalline silicon double-sided modules.

2025-07-25 16:43:09

The tender announcement shows that the project is to build a photovoltaic power station on the slope between the original 1 # and 2 # crushing stations and 3 # and 4 # crushing stations in the first mining area of Heidaigou Open-pit Coal Mine, and the actual installed capacity of the DC side of the photovoltaic power station is 16. 20736 MWp.

2025-07-23 16:20:22

According to the announcement, there are three shortlisted candidates, all of whom are consortia. The total bidding price is between 22.9053 million yuan and 22.9988 million yuan, and the bidding unit price is between 3.11 and 3.13 yuan/watt.

2025-07-22 10:10:01

On July 18, the tender announcement for EPC general contracting of energy storage project of Inner Mongolia Huadian Tengger 1 million kilowatt photovoltaic power generation phase II project was issued. The tenderer is Bayanhot Photovoltaic Branch of Inner Mongolia Huadian Tengger Green Energy Co., Ltd.

2025-07-21 09:40:32

On July 17, CGN New Energy Yunnan Yaoanbala 60MW Photovoltaic Project announced the successful candidates for the PC general contracting project (re-bidding) of photovoltaic field area, collector line and 110kV booster station.

2025-07-18 09:55:31

Announcement on Winning the Bid for EPC (Including Key Equipment) of 10 x6 MW Distributed Photovoltaic Project of CGN New Energy in Yunyang County, Chongqing

2025-07-16 17:37:46

On July 14, China Huadian Corporation released the announcement of successful candidates for Shandong Huadian 400MW household distributed photovoltaic project Ludong (200 MW) and Luxi (200 MW) EPC + 5-year operation and maintenance general contracting bidding project.

2025-07-15 17:36:15

The tender announcement shows that the project is located in Wuhe County, Bengbu City, Anhui Province, with a DC side capacity of 84.012 MW and an AC side capacity of 60 MW. The duration of the bidding and procurement project is 150 days from the date of signing the contract.

2025-07-14 10:06:52

The winning unit price is 2.596 yuan/watt.

2025-07-11 18:39:59

The announcement shows that the planned total capacity of the project is 500MW, supporting the construction of a 220KV offshore booster station and an onshore centralized control center, which are connected to the onshore centralized control center through 220KV composite submarine cables and connected to the grid system station through outgoing lines.

2025-07-08 17:30:22

On July 1, Gansu Provincial Public Resources Trading Center issued a tender announcement for the 200 million photovoltaic power station project in Yuzhong County. The tender unit is Yuzhong Mingwei Bioenergy Technology Co., Ltd. The announcement shows that the project is located in Wujiayao Village, Weiying Township, Yuzhong, Lanzhou City, Gansu Province, with a total investment of 639.21 million yuan, a construction scale of 200MW and a DC side installed capacity of 238.508 MWp.

2025-07-07 09:45:20

Digital New Energy DataBM. Com learned that from June 30 to July 1, Jiangsu and Yunnan issued three public announcements of EIA acceptance for photovoltaic power generation projects, with a total installed capacity of 260.76 MW and an installed capacity of 311.45 MW.

2025-07-02 16:05:55

On July 1, the announcement of the procurement project of Xidian Intelligent Energy Linyou County Photovoltaic Phase II EPC Procurement Project was issued. The announcement shows that the project uses the roofs of farmers in Linyou County, Baoji City, Shaanxi Province to build photovoltaic power stations with a total capacity of 4.12 MW and 635 W photovoltaic modules and inverters.

2025-07-02 11:21:57

Project overview: Taiyanggou Pumped Storage Power Station is located in Wulatehou Banner, Bayannur City, Inner Mongolia. The lower reservoir dam site is 12 km away from Wulatehou Banner and about 60 km away from Bayannur City. The upper reservoir is located in the upstream of Taiyanggou in Bayinbaolige Town near the gully head. The reservoir area is mainly composed of two gullies in the east and west, and the dam is built at the intersection of the two gullies to form the reservoir. The dam site of the lower reservoir is located in the downstream of the dam ditch in the front of the middle section of Langshan Mountain in Yinshan Mountains, and the reservoir is formed by blocking the river with a few bends. The installed capacity of the power station is 1200MW, and four vertical-shaft single-stage single-speed mixed-flow reversible pump-turbines with a single unit capacity of 300MW are installed.

2025-06-30 11:30:39

On June 26, Sichuan Public Resources Trading Platform announced the announcement of the successful candidate for EPC general contracting of Griping Photovoltaic Power Generation Project in Panzhihua West District. There are 5 shortlisted enterprises, namely, Guiyang Survey, Design and Research Institute Co., Ltd. of China Power Construction Group, Sichuan Architectural Design and Research Institute Co., Ltd., Shandong Electric Power Engineering Consulting Institute Co., Ltd., Chengdu Survey, Design and Research Institute Co., Ltd. of China Power Construction Group, and Kunming Survey, Design and Research Institute Co., Ltd. of China Power Construction Group. The winning unit price is between 3.4 yuan/W and 3.64 yuan/W.

2025-06-30 09:13:09

There are three candidates for the bid, namely, Southwest Engineering Co., Ltd. of China Railway 15th Bureau Group, China Construction Third Engineering Bureau Group Co., Ltd. and First Engineering Co., Ltd. of China Railway 22nd Bureau Group, with a unit price of 3.73-3.79 yuan/watt.

2025-06-26 09:18:32

From June 23 to 24, Kunming City, Lijiang City and Chuxiong Prefecture of Yunnan Province released the EIA announcements of four photovoltaic power generation projects, with a total installed capacity of 660 MW and a total investment of 2.97 billion yuan.

2025-06-25 17:30:43

On June 17, Shengtai New Energy Technology Co., Ltd., Wuchuan County, Hohhot City, Inner Mongolia, issued an announcement on the termination of the EPC of the 500 MW photovoltaic composite (agricultural-photovoltaic complementary) project. According to the announcement, the content of the tender is changed.

2025-06-18 09:14:46

On June 13, Shengtai New Energy Technology Co., Ltd., Wuchuan County, Hohhot City, Inner Mongolia, issued an EPC tender announcement for the 500 MW photovoltaic composite (agricultural-photovoltaic complementary) project.

2025-06-16 18:11:48

Weekly Report on Statistics of National Major Construction Projects Winning Bids (6.2-6.8)

2025-06-09 15:58:29

On June 5, China Energy Construction Group issued a tender announcement for the procurement of 650 MW photovoltaic EPC general contracting project in Zhengdou, Ganzi Township, Sichuan Province. The tenderer is China Energy Investment (Xiangcheng) New Energy Power Generation Co., Ltd.

2025-06-09 09:09:40

Digital New Energy DataBM. Com learned that on June 3-4, China Resources Group issued two tender announcements for general contracting of photovoltaic projects with a total capacity of 340 MW.

2025-06-05 09:57:20

On May 28, China Huadian Corporation issued a tender announcement for Shandong Huadian 400MW household distributed photovoltaic project Ludong (200 MW) and Luxi (200 MW) EPC + 5-year operation and maintenance general contracting project.

2025-06-04 17:50:16

On May 28, the construction of Gasidu Phase II 300MW Photovoltaic Power Station Project in Jinchuan County, Aba Prefecture, Sichuan Province was officially started, with a total investment of 1.4 billion yuan, and is expected to be put into operation in December 2025.

2025-06-03 09:32:39

On August 11, Conch Cement announced that Li Qunfeng resigned as general manager of the company and continued to serve as executive director of the company and director of some subsidiaries of the company. At the same time, the Board unanimously agreed to appoint Mr. Yu Shui as the general manager of the Company.