19 September, Huadian Jinsha River Upstream Hydropower Development Co., Ltd. Huadian Jinshang Xizang Weak County Guarantee Project -Gongjue 14 MW , such as 33 MW, Bangor 20 MW, Shuanghu 10 MW " According to the tender announcement, Located in Gongjue County, Changdu City, the EPC Project of Gongjue 14 MW Photovoltaic Power Generation Project covers an area of 400 mu, with installed capacity of 14 MWp on the DC side and 14 MW on the AC side. Equipped with 14 MWh (3.5MW * 4h) grid-type energy storage , the bidding scope is as follows
: For example, the EPC general contracting project of 33 MW photovoltaic power generation project is located in Ruxian County, Naqu City, covering an area of about 621 mu. The installed capacity of DC side is 33 MWp, the installed capacity of AC side is 33 MW, and 33 MW (8.25 MW * 4 H) grid-type energy storage is configured; The bidding scope is as follows:
The EPC general contracting project of Bangor 20MW photovoltaic power generation project is located in Bangor County, Naqu City, covering an area of about 850 mu. The installed capacity of DC side is 20 MWp, the installed capacity of AC side is 20 MW, and 20 MW (5MW * 4 H) grid-type energy storage is configured; The EPC Project
of Shuanghu 10MW Photovoltaic Power Generation Project is located in Shuanghu County, Naqu City, covering an area of about 250 mu, with an installed capacity of 10 MWp on the DC side and 10 MW on the AC side. Configuration 10 MW (2.
Bangor 20 MW Shuanghu 10 MW PV Power Generation Project EPC general contracting bidding scope is as follows:
connected to the grid with full capacity on December 31, 2025." The remaining three projects are planned to be connected to the grid at full capacity on January 31, 2026.In addition to requiring bidders to have good business conditions, business reputation and corresponding qualifications,
the bidder's performance is from January 1, 2020 to the deadline for bidding ( subject to the time of operation ). It shall have the EPC general contracting performance of at least two photovoltaic (including energy storage) projects that have been put into operation at an altitude of more than 3000 m and a capacity of not less than 20 MW; When a
consortium is used for bidding, the leading party in the consortium shall meet the above performance requirements, and the members of the consortium shall have the performance of photovoltaic power generation projects from January 1, 2020 to the deadline for bidding.
It is worth noting that the bidder shall not provide design or consulting services for the preliminary work of the bidding project, shall not be the supervisor, agent or bidding agency of the bidding project, and shall not be the same legal representative as the aforementioned subject or have a holding/equity participation relationship.