On September 17, Huarun Guangzhou Zengcheng Xiancun Steel Trade City (Qianhe, Ouhui, Chuangli, Yelian) issued a tender announcement for EPC general contracting of four distributed photovoltaic projects , and the tenderer was Huarun Integrated Energy (Yunfu) Co., Ltd.
The tender announcement shows that the project plans to build four distributed photovoltaic projects on the roof of the factory building of No.13 Lixinjiu Road, Southwest Village, Xiancun Town, Zengcheng District, Guangzhou City, Guangdong Province. The DC sides of the four projects are 6.54762MWp, 6.49224MWp, 7.01196MWp and 6.65483MWp respectively .
The project is an EPC turnkey project, no matter whether it is mentioned in this technical document or not. The work contents and relevant costs related to the design, construction, house reinforcement, fixed steel inclined ladder, procurement, completion and production, project inspection, file acceptance, completion settlement, project acceptance, overall completion acceptance and other project acceptance of the project are within the scope of work of the bidder. The total planned construction period of the
project is 346 days, which is tentatively scheduled from October 20, 2025 to September 30, 2026: mobilization before October 20, 2025, commencement before November 20, 2025, and completion acceptance before September 30, 2026. In addition to requiring bidders to have good business reputation and corresponding qualifications,
the bidder's performance is from January 1, 2022 to the deadline for bidding (subject to the time of signing the contract). There must be at least one single distributed photovoltaic EPC contract performance of 20 MWp or above .
It is worth noting that if the equipment design scheme is patented, the bidder must hold the relevant valid patent certificate and its creative patent evaluation report, or the relevant patent authorization.
The project allows consortium bidding, and the number of members does not exceed 2. Bid
closing/opening time: 2025-10-13 09:30 (Beijing time)