On December 23, the Hebei Development and Reform Commission announced the proposed adjustment of wind power and photovoltaic power generation projects in Hebei Province in 2025. After conducting a comprehensive survey of the wind power and photovoltaic projects included in the annual development and construction plans (construction plans) over the years, the wind power and photovoltaic projects required to be completed before December 31, 2025 , and the wind power and photovoltaic projects included in the provincial reserve, the adjustment opinions of the relevant expired projects and all the reserve projects to be retained will be publicized.
The adjustment catalogue shows that the number of photovoltaic and wind power projects to be adjusted in Hebei Province is 103 , with a total scale of 14.89199 million kilowatts , of which 5.71449 million kilowatts are photovoltaic. 9.1775 million kilowatts of wind power.
Among them, 1.22299 million kilowatt scale projects were cancelled and 12.8 million kilowatt scale projects were postponed. Including the cancellation of 458,990 kilowatt photovoltaic project indicators and the postponement of 4,665,500 kilowatt photovoltaic project construction. The indicators of
six wind and solar projects have shrunk, with the construction capacity reduced from 869000 kilowatts to 391600 kilowatts, and the indicators reduced by 477400 kilowatts .
In addition, the publicity information also disclosed the reserve projects to be retained, with a total number of 321 projects and a total scale of 38.769.19 million kilowatts . Among them, there are 173 photovoltaic projects with a scale of 20.79094 million kilowatts and 151 wind power projects with a scale of 17.97825 million kilowatts.