On August 18, the tender announcement of 28.8 MW roof distributed photovoltaic power generation project of Anhui Maanshan and County Jingkai Energy Technology Co., Ltd. was issued.
The tender announcement shows that the estimated investment of the project is about 115.4346 million yuan, mainly using the roof of the existing plant in the park of Hexian Jingkai District to build a distributed photovoltaic power station , with an available roof construction area of about 244500 square meters. The installed capacity of DC side is 28.8 MW , which is divided into 8 grid-connected points and connected to the grid with 380V voltage level. The roof photovoltaic system of this project adopts the grid-connected mode of " self-generation and self-use, surplus electricity access to the grid ". The specific bidding scope is as follows:
It is worth noting that the highest bidding price of the project is 81.0144 million yuan , and the highest bidding price per watt is 2.81 yuan/watt (DC side installed capacity). After the signing of the
bidding plan contract, the construction drawing design and grid-connected access scheme will be completed within 30 days, and the total construction period will be 365 days after receiving the notice from the tenderee according to the actual situation of the site. Within 180 days after the commencement of a single sub-project, the installation and commissioning shall be completed and accepted. (The drawing review period is not within the above service period)
This tender accepts consortium bidding, but the number of consortium members (including the consortium leader) shall not exceed 2 .
Bid closing time/bid opening time: 9:00, September 8, 2025.