On November 18, Datang issued a tender announcement for EPC general contracting of four photovoltaic projects , with a total tender capacity of 350 MW . Details are as follows:
(Shaanxi Company) Datang Pingli County 100MW Photovoltaic Project EPC General Contracting Project Bidding
The tenderer of the project is Datang Fuping Thermal Power Co., Ltd., the construction site is Pingli County, Ankang City, Shaanxi Province, the construction scale is 100MW, and the planned construction period is 365 days. The scope of this
tender: construction drawing design and as-built drawing preparation of the 100MW photovoltaic project booster station, photovoltaic field and collector line (excluding the outgoing line) in Pingli County, Datang, procurement of equipment and materials (except for the equipment supplied by Party A), unloading, secondary transportation and storage, all construction and installation, commissioning, trial operation and defect elimination. Grid-connected formalities, relevant special acceptance, coordination and other work.
This tender requires bidders to have good financial status, business reputation and corresponding qualifications. In terms of performance, there must be 2 or more 50 MW (or EPC general contracting performance of completed photovoltaic power station in plain desert/mountainous area (MWp) and above .
(Shaanxi Company) Datang Baqiao Thermal Power Lintong 50 MW Photovoltaic Power Generation Project EPC General Contracting Bidding
The tenderer of the project is Baqiao Thermal Power Plant of Datang Shaanxi Power Generation Co., Ltd. and the construction site is Lintong District, Xi'an City, Shaanxi Province. The construction scale is 50 MW and the planning company is 275 days from April 1, 2026 to December 31, 2026.
This tender includes the construction drawing design, completion drawing preparation, equipment and material procurement (except for equipment supplied by Party A), unloading, secondary transportation and storage, construction, installation, commissioning, trial operation, defect elimination, and grid connection formalities of Lintong 50 MW photovoltaic power generation project switch station, photovoltaic field area and collector line (excluding outgoing line). Relevant special acceptance, coordination and other work.
This tender requires bidders to have good financial status, business reputation and corresponding qualifications. In terms of performance, two or more 50 MW (or MWp) and above (mountain/agricultural/forest-photovoltaic complementary) photovoltaic power plants must have been completed EPC general contracting performance in the past five years .

(Shaanxi Company) Datang Fengxiang District 100MW Photovoltaic Project EPC General Contracting Bidding
The tenderer of the project is Tang Shaanxi Power Generation Baoji Fengxiang New Energy Co., Ltd. and the construction site is Liulin Town, Fengxiang District, Baoji City, Shaanxi Province. The construction scale is 100MW and the planned construction period is 306 days, from March 1, 2026 to December 31, 2026. The scope of this
tender is the construction drawing design, completion drawing compilation, procurement of equipment and materials (except for the equipment supplied by Party a), unloading, secondary and multiple transportation and storage of the 100000 kilowatt photovoltaic project booster station, photovoltaic field area and collector line (excluding the outgoing line) in Fengxiang District of Datang. Test and inspection of equipment and materials (including materials supplied by Party A), construction engineering, installation engineering, communication connection, equipment and system commissioning, trial operation, defect elimination, power grid acceptance, maintenance within the warranty period, grid connection formalities handling, coordination and other relevant special acceptance.
This tender requires bidders to have good financial status, business reputation and corresponding qualifications. In terms of performance, two or more 100MW (or 100MWp) and above (plain desert/mountain/agricultural photovoltaic (including forest photovoltaic) complementary) photovoltaic power stations have been completed EPC general contracting performance in the past five years .
(Shaanxi Company) Datang Fugu 100MW Photovoltaic Power Generation Project EPC General Contracting
Datang Shaanxi Fugu Coal and Electricity Co., Ltd., the tenderer of the project, is located in Huangfu Town and Qingshui Town, Fugu County, Yulin City, Shaanxi Province. The construction scale is 100MW , and the planned construction period is tentatively from December 30, 2025 to December 30, 2026.
The bidding scope is EPC general contracting of Tangfugu 100MW photovoltaic power generation project, including construction drawing design and as-built drawing preparation of 110kV booster station, photovoltaic field area and collector line (excluding transmission line). Procurement of equipment and materials (excluding equipment supplied by Party A), test and inspection of equipment and materials, transportation and management, unloading, secondary transportation and storage, installation, commissioning, trial operation and defect elimination of all buildings. Communication connection, equipment and system commissioning, power grid acceptance, maintenance within the warranty period, grid connection formalities, obtaining power generation business license (full capacity) and corresponding special acceptance, coordination and other work until the completion acceptance is completed.
This tender requires bidders to have good financial status, business reputation and corresponding qualifications. In terms of performance, two or more 100MW (or 100MWp) and above (plain desert/mountain/agricultural photovoltaic (including forest photovoltaic) complementary) photovoltaic power stations have been completed EPC general contracting performance in the past five years . Consortium bidding is accepted for
the above tenders, and the deadline for bidding is 9:00 on December 9, 2025.
浙公网安备33010802003254号