On November 12, the successful candidate for the EPC general contracting project (bid section I) of the 600,000-kilowatt photovoltaic sand control project in Xinlong Kaisheng Yecheng County was announced.
The announcement shows that there are two successful candidates, namely,
the first successful candidate: the Second Construction Engineering Co., Ltd. of China Construction Third Engineering Bureau and Hubei Zhicheng Construction Co., Ltd. The bid price is CNY 1,320,800,000 and the unit price is CNY 3.302/watt ; The second successful candidate: Baijing Construction Group Co., Ltd., with a bid price of 1,439.2 million yuan and a unit price of 3.598 yuan/watt . (Note of the author: the unit price here is calculated according to 400MW, and "all construction and installation works of 400MW photovoltaic field and power plant" is mentioned in the bidding scope of Bid Section I in the bidding documents.)

Previously, on September 30, the project issued a tender announcement, and the tenderer was Zhongan Power Investment (Henan) Energy Co., Ltd.
Xinlong Kaisheng Yecheng County 600MW Photovoltaic Sand Control Project is located in Yecheng County, Kashgar Prefecture, Xinjiang, with a rated installed capacity of 600MW . 60MW/120MWh energy storage , supporting construction of photovoltaic support , support foundation and component installation, maintenance road, box transformer foundation, etc. The project is divided into two bid sections.
The bidding scope of Bid Section I includes survey, design, coordination of project formalities, geological survey, feasibility study report, all construction and installation works of 400 MW photovoltaic area and power plant, etc.


Earlier, on October 20, the project issued a postponement announcement, due to the adjustment of the project tenderer's plan. The deadline for submission of bidding documents and the time for opening bids were postponed from 9:00 on October 21, 2025 to 9:00 on November 6, 2025.