14 July, China Huadian Corporation released EPC + for Shandong Huadian's 400MW household distributed PV projects in Ludong (200 MW) and Luxi (200 MW) Announcement of successful candidates for 5-year operation and maintenance general contracting bidding project.
The results showed that there were two candidates for the Ludong 200MW bid section, namely, Zheng Taian Energy Digital Energy (Zhejiang) Co., Ltd. , with a bid price of 474.0012 million yuan. The bidding unit price is 2.37 yuan/watt ; The bidding price of Rizhao Guoxin Electric Power Technology Co., Ltd. is 469.6816 million yuan, and the bidding unit price is 2.348 yuan/watt . There is only one successful candidate of Zhengtai Anneng Digital Energy (Zhejiang) Co., Ltd. for the project
of Luxi 200MW bid section, whose bidding price and unit price are the same as those of Ludong bid section.
Earlier, on May 28, the project issued a tender announcement. The specific bidding scope of the two bidding projects is shown in the following figure:
the two bidding projects require the EPC project to complete 100% of the total capacity (AC side) grid connection before December 31, 2025. At the same time, the operation and maintenance service of each set of photovoltaic power station is valid for 5 years from the first day of the next month when each set of photovoltaic power station is connected to the grid and the handover confirmation form is obtained.