On October 24, the bidding results of the EPC general contracting project of the 50,000-kilowatt photovoltaic sand control pilot project in Xigaze City in 2025 were announced.
The announcement shows that the winning bidder is China Water Conservancy and Hydropower Eighth Engineering Bureau Co., Ltd. with a bid price of 78,241,128 yuan . The bidding unit price is 1.565 yuan/watt .

Earlier, on September 25, the project issued a tender announcement.
The announcement shows that the project is located at the boundary between Jiangdang Township and Nianmu Township in Xigaze, Xizang Autonomous, with a planned total installed capacity of 51. 56125 MWp on the DC side and 50 MW on the AC side. The total planned construction period is 6 months . It is expected to start work on November 1, 2025, the first batch of photovoltaic arrays will be connected to the grid on January 31, 2026, and all photovoltaic arrays will be connected to the grid on April 30, 2026.