Green New Quanxing with 4000 Tons of Fine Products — — On-the-spot Report of Quanxing Cement Production Line Project with a Daily Output of 4000 Tons of Cement Clinker

2023-11-26 12:54:36

The completion and trial operation of 4000t/d clinker production line has become an important milestone in the development history of Quanxing Cement Company, marking that Quanxing Group has opened a new page on the road of green and low-carbon development.

In the golden autumn season, the emerald is golden. On September 28, Shandong Quanxing Cement Co., Ltd. (Hereinafter referred to as "Quanxing Cement Company"), located in Taierzhuang, the "Canal Ancient City", was full of joy and colorful flags. With an investment of 1.02 billion yuan, the cement

is 0.4000t/d. The completion and trial operation of the clinker production line has become an important milestone in the development history of Quanxing Cement Company. It marks that Quanxing Group has opened a new page on the road of green and low-carbon development. Looking back on the construction process, Quanxing people have written a new miracle of production line construction in today's cement industry with hard work and responsibility; looking forward to the future, Quanxing people will not waver in anchoring the goal of green and low carbon, and strive to write a new chapter of high-quality development.

High starting point, establish target positioning. Around the project construction, the project goal of "Building Jiangbei Benchmarking Project" has been defined, and the project construction orientation of "Safety as the day, environmental protection as the first, quality as the basis, progress as the surface, standardization as the frame, incorruptness as the basis, performance as the responsibility, cooperation as the force, indicators as the reality, benchmarking as the pride" has been put forward. To ensure the realization of economic benefits, social benefits, environmental benefits, clean benefits, standardized management of the "five benefit objectives" of high standards. Set up a construction team with

high specifications. The company has set up a project construction leading group headed by Liu Heming, deputy general manager of the group and general manager of the company. All members of the Party Committee of the company are also members of the project leading group to improve project management specifications. The group consists of 10 professional groups, including work coordination, civil construction, mechanical and electrical equipment, process technology, safety and environmental protection, business compliance, supervision and assessment. Within the group, six professional managers and technical specialist were selected to set up special working classes, which were responsible for the construction of the new line project, and a steel division capable of fighting hard battles and being good at fighting hard battles entered the scene.

High standards, promote the establishment of clear responsibilities. In order to ensure the coordinated progress of the work during the construction of the project, more than 20 work systems, such as regular work meetings, information bulletins, work logs, assessment and supervision, have been established, and work logs have been filed regularly every day, a regular project meeting has been held every day, and a weekly "project construction report" has been formed every week to clarify the construction period, quality, safety and acceptance. The whole process is strictly assessed. At the same time, from progress to quality, from civil construction to equipment arrival and installation, from safe and civilized construction to honesty and self-discipline, the overall division of labor is clear and the responsibility is assigned to people. Party A, the general contractor and the supervisor also specify the person in charge, divide the responsibility area and compact the division of responsibilities. Around the self-pressure of the project objectives, all the relevant personnel signed the military warrant of the project.

Pay close attention to fine management to ensure safety. Adhere to the concept of "safety is the greatest benefit" and measure the safety ruler to the end. One is to sign responsibility certificates layer by layer. The company signs safety and environmental protection agreements with construction, supervision and auditing units respectively, and the project department signs safety and environmental protection responsibility letters with each professional group to implement the responsibility to each link, each unit, each team and each person. All construction teams must be trained and qualified by the company before they can take up their posts, strictly implement the operation requirements of "one project, one scheme", and ensure that every equipment, every link and every work on the site has a responsible person. Second, keep a close eye on key areas. In view of the safety management of weak points such as high-altitude operation, cross-operation, power consumption operation and vehicle traffic, the supervision of wearing labor protection supplies, working with tickets, working with certificates, construction power consumption and foundation pit enclosure has been strengthened in an all-round way, and special personnel have been arranged to carry out on-site supervision, so as to resolutely eliminate illegal operation and illegal operation, thus creating a grid safety management mode of horizontal to side and vertical to the end. Third, strengthen supervision and inspection. Adhere to the working idea of focusing on hidden danger investigation and special renovation, and carry out pull-net safety risk provention and control, hidden danger investigation and management and closed management for the normalization of new line construction. Since the construction of the new line, 60 comprehensive inspections have been organized, 1500 problems have been found, the problem closure and rectification rate is 100%, and the project safety has been realized. "Quanxing Cement Company's safety efforts are the most stringent in all our projects, which can be described as" harsh ", but this is the only magic weapon to ensure the safety of the project," said Niu Yanlin, chairman of Sinoma International, the contractor of the project.

Strict and careful supervision to catch up with the progress. The company establishes the consciousness of "the beginning is the decisive battle, the beginning is the sprint", unifies the thinking and understanding, and strengthens the confidence to win. Firstly, we should refine the overall objectives, reverse the schedule, constantly optimize the project construction plan, strictly implement the system of "daily dispatch, weekly assessment and monthly notification", implement the management of wall chart operations and "red, yellow and blue" signs of project progress, and refine the assessment of project progress nodes. The second is to strictly control the quality, joint supervision, auditing and other participating units, do a good job of quality supervision in the construction process, designate special personnel to follow up 24 hours, keep photos and image data for all concealed works, and only after acceptance can next link of construction be carried out. When there are contradictions and conflicts between progress and quality, progress must be subordinated to quality. Strengthen quality supervision, inspection and spot check. Unqualified materials are strictly prohibited from entering the factory for use. Unqualified construction will be reworked. Since the construction of the new line, more than 20 parts have been reworked, dismantled and re-constructed.

Strict discipline and strong style of work. The company firmly establishes the sense of ownership of "I am Quanxing", clarifies that "everyone is responsible for the project construction", and strengthens the style construction. One is to strengthen coordination and cooperation. All departments, especially the members of the project team, are required to base themselves on their own duties, cooperate with each other, and spare no effort to provide work coordination, services and necessary assistance to the construction units, supervision units and audit units. The second is to strengthen information sharing. Insist on relying on services, timely help solve problems in construction projects, timely convey, share and share information in all aspects, so as to achieve interconnection and interoperability. Adhere to efficient, pragmatic, honest and clean work style, improve work efficiency, form work force, and create a good internal and external environment for project construction. Third, strengthen assessment and supervision. In strict accordance with the scope, standards and deadlines stipulated in the contract, in strict accordance with the group's project construction management methods and assessment methods, strict work discipline, integrity discipline, dare to be more genuine, dare to be tough, for those who fail to do so, accountability, punishment and punishment should be carried out to ensure that the project is completed with high standards.

Party members and cadres "take the lead". The Party Committee of the company always plays a role of checking and directing, and studies and deploys the project construction plan one after another with a high sense of political responsibility. Liu Heming, deputy general manager of the group and general manager of the company, set an example by staring at the scene at least four hours a day, checking hidden dangers, grasping rectification and long-term high-intensity work, which made him change a pair of shoes every two months on average, and also caused serious damage to his knees. Comrade Li Xiuqi, the project leader, checked the drawings, made the information and made the plan. He worked late into the night every day and had almost no rest throughout the year. The long outdoor work not only made him lose 20 kilograms of weight successfully, but also left two light-colored marks on his tanned face protected by the helmet belt. It is the leading role of Party members and cadres that drives all the construction personnel to work together and strive forward.

Fight against the "most beautiful retrograde" of novel coronavirus. The construction of the project spans four seasons and has experienced several rounds of COVID-19 epidemic, resulting in blocked transportation, trapped personnel and limited traffic, which are always testing the project builders. They look for all available time to seize the construction period, especially during the most violent round of epidemic in winter, construction personnel and materials are seriously affected, resulting in the problem of delayed construction period. The personnel of the project team are not reliable, take the factory as their home, try their best to find ways, use personnel, machines and tools, work overtime, catch up with the construction period, speed up the progress, ensure the quality, and stick to the front line day and night, wind and snow.One group of people were infected with the novel coronavirus, another group of people were immediately on top, and some people were thrown into the scene as soon as the fever subsided. Every employee of the company's project department will carry out the "three-no spirit" of "no time, no pay, never say no in work" throughout the project construction, which provides a guarantee for the completion of the project construction with high quality.

Fighting against heaven and earth, "cold comes and summer goes". In winter, the weather is freezing, windy and snowy, but it is a critical period for key links. In December last year, during the construction of the sub-project of the central control building, in order to ensure the progress of the project, the construction workers tied the steel bars in a cold winter rain. Even if the clothes were wet by the cold rain and the hands were numb with pain, they only entered the working state again after a short adjustment. In summer, the weather is hot and rainy, but it is the peak period of equipment installation. In July 2023, the construction of the new line entered a critical stage, with the highest temperature on site reaching 39 degrees Celsius and more than 700 construction workers on site. In order to ensure the safety, quality and progress of the project construction, the company arranges special personnel to conduct spot checks on the pre-shift meeting of each construction team, check the status of personnel, implement heatstroke prevention and cooling measures, strengthen the supervision and inspection frequency of site safety and "three violations" by arranging personnel according to the construction time and area, and resolutely "catch up with the progress without sacrificing safety and quality" to ensure the steady progress of project safety.

Speed up and "set a new record". With the joint efforts of all the staff, they have overcome many difficulties and set new records one by one, creating a "spring speed" for the construction of production lines in the cement industry. The concrete structure construction of the kiln tail sub-project started on December 3, 2022, which took 39 days to complete the capping and pouring, 26 days ahead of the project schedule of 65 days for concrete structure construction, setting a benchmark in the industry; the central control building was successfully capped on December 28, and the pouring was completed before the year, shortening the construction period by half a month; On May 28, 2023, the project began to hoist the rotary kiln, and the original workload of 7 days was successfully completed in only 78 hours, which greatly shortened the construction time of the project; On August 4, 2023, the first-line demolition work was completed, five days ahead of schedule.. Over the past year, Quanxing people have gathered a strong fighting capacity of "one team, one goal, one pace, one mind" around the established goals, attacking cities and villages all the way, overcoming a series of complex problems, creating a number of achievements, and creating a classic project.

"We have the ability to design and construct the 4000 line project well, and also have the ability to operate and develop the project well. We are more capable, confident and determined to build the 4000 line project into a strong grasp and hard core support for the Group to achieve the goal of industrial doubling." Zhang Zonghui, Secretary of the Party Committee and Chairman of the Group, has high expectations for the operation of the project.

tree" green and low carbon "benchmark. Focus on the national "double carbon" strategy, increase investment in environmental protection and governance, promote energy-saving technological transformation of Line 3 , eliminate high energy-consuming motors in batches to achieve energy saving and consumption reduction; relying on the industrial advantages of Green Energy Group, use raw material greenhouses, mine slopes, etc., to build photovoltaic power generation projects; promote the establishment of green factories, and strive to create a national green factory in 2025.

Set up the benchmark of "digital intelligence". Focus on the construction of "digital brain", make full use of computing network technology, online analysis and detection technology, intelligent sensing technology, automatic control technology, information technology and artificial intelligence technology, maximize labor productivity, safe operation ability, emergency response ability, risk prevention ability and scientific decision-making ability, and realize fully intelligent cement plant.

Set up the benchmark of "coordinated development". Focus on "solid chain and strong chain", relying on advanced decomposition furnace calcination process, promote kiln co-disposal of contaminated soil projects, to achieve comprehensive utilization of resources and cost reduction. We will vigorously tackle the key problems of alternative fuels such as waste spinning, reduce pollutant emissions and carbon emissions from the source, achieve synergistic effects of pollution reduction and carbon reduction, and help the Group transform into a high-quality development.

Looking forward to the future, Quanxing Cement Company will continue to carry forward the practical spirit of "opening roads in every mountain and building bridges in every river", and make new and greater contributions to the Group's goal of industrial doubling and high-quality development.

All can be viewed after purchase
Correlation

It is reported that the Maitreya Red Lion Cement Project covers an area of 679.95 mu, with a total investment of about 1.62 billion yuan. It adopts a new dry decomposition production process to build a cement clinker production line with a daily output of 4628 tons, supporting 9 MW pure low-temperature waste heat power generation project, 200000 tons/year solid (dangerous) waste project and 5 million tons/year aggregate mine project. Supporting construction of public auxiliary facilities such as raw material storage yard, limestone homogenization warehouse, packaging, bulk, water, electricity and office area.

2026-09-14 16:15:03

In Dashui Industrial Park, Jinzhong Town, Kaiyang County, Guiyang City, Guizhou Kailin Group Co., Ltd. intends to use dihydrate phosphogypsum as the main raw material, through dehydration, decomposition, calcination and other processes of phosphogypsum, to build a new set of annual treatment of 1.7 million tons of phosphogypsum (dry basis), to produce 800000 tons/year sulfuric acid and co-produce 720000 tons/year cementitious materials recycling plant, so as to realize the recycling of sulfur resources. The total investment of the project is 2.025 billion yuan.

2026-09-14 09:50:44

During the talks with Mr. Pirmakhanov Saken, General Manager of Samruk-Kazena National Fund Investment Company in Kazakhstan, the two sides conducted in-depth communication on infrastructure construction, new energy, building materials, comprehensive utilization of mineral solid waste, data center, logistics and other fields in Kazakhstan. Preliminary consensus was reached on potential areas of cooperation, localized plant construction, resource coordination and follow-up docking mechanism.

2026-09-14 09:38:16

A total of 36 projects have been introduced, focusing on four key areas, namely, transportation, logistics, water conservancy and energy, with an estimated total investment of 61.4 billion yuan and a planned private capital of 15.6 billion yuan, covering railway, warehousing, wind power, energy storage, charging facilities and water diversion projects. Private capital can participate in many ways, such as sole proprietorship, holding and equity participation in project companies.

2026-09-11 09:20:14

Schedule the construction progress of 109 major projects, accelerate the implementation of projects under construction, promote a number of new projects to start construction as soon as possible, further strengthen the guarantee of factors, consolidate the responsibility of project quality and safety management, form a joint force to jointly promote the construction of major projects, and provide strong support for the realization of a good start of the 15th Five-Year Plan.

2026-09-07 13:49:58

The project is the first cement project of China Building Materials Group in Central Asia, with a total investment of about 180 million US dollars. After completion, it will become the first modern cement plant in Aktobe Prefecture, effectively alleviating the supply gap of high-end cement in the region.

2026-09-07 09:50:31

What needs to be more vigilant is that from the publicity rhythm, there will be more similar projects queuing for landing in the future.

2026-09-03 15:29:16

Hubei Economic and Credit Office issued three announcements of capacity replacement schemes for phosphogypsum acid production projects, all of which came from cement enterprises in the province.

2026-09-02 09:19:26

On July 27, the first truck of commercial concrete of Lingshan Guanfeng Commercial Concrete, the entrusted processing project of Xingye Conch Commercial Concrete, was successfully delivered. On August 28, Shuangfeng Conch and Xiangtan Xiyuan Commercial Concrete Processing Project were put into operation smoothly.

2026-09-01 11:47:17

This project has completed the filing of investment projects. Relying on its own industrial foundation, the enterprise has built a production line with an annual output of 2 million tons (800,000 cubic meters) of sand and gravel aggregate, which can make up for the shortage of high-quality mechanism sand and gravel supply in the region, extend the industrial chain of the enterprise, meet the needs of local engineering construction materials, promote the green and standardized upgrading of the sand and gravel industry, and boost local economic development.

2026-08-31 11:52:46

It is understood that due to ecological protection requirements and other reasons, the original supporting mines can not meet the production needs, Yongan Jinniu Cement Co., Ltd. intends to relocate its second 4500t/d cement clinker production line from Yongan City, Sanming City to Hucun Town, Ninghua County, Sanming City, and promote the construction by Ninghua Jinniu Cement as the main body of project implementation.

2026-08-31 10:00:04

The reconstruction of the cement production line does not change the mining scale, mining technology and transportation mode of the company's limestone mine.

2026-08-28 14:19:13

Promote the establishment and improvement of investment and financing mechanisms suitable for different types of projects in different fields, and provide strong support for accelerating the construction of major projects.

2026-08-26 13:31:43

The successful capping of the preheater tower at the kiln inlet was strongly supported by the owner, the general contractor and other construction parties, which created conditions for the subsequent equipment installation and production line commissioning, and also tested the engineering organization and performance ability of Sinoma Tian'an in the complex overseas environment.

2026-08-21 11:46:42

The linkage test lasted for 4 hours, covering the whole process of crushing, screening, sand making and conveying. The equipment of each system ran smoothly, and the technical parameters met the design requirements.

2026-08-20 10:31:46

Recently, Saudi YAMAMA Cement Company officially issued a PTO certificate to Sinoma Overseas, marking the success of the world's first 10,000-ton line relocation and upgrading project undertaken by Sinoma Overseas.

2026-08-20 10:06:31

The withdrawal of each production line is the result of the optimal allocation of the market under the guidance of the capacity replacement policy. For enterprises, this is not only a self-slimming to eliminate inefficient production capacity and reduce overall production capacity, but also an opportunity to integrate resources and optimize regional market layout.

2026-08-20 09:34:32

After all, phosphogypsum needs to be absorbed, and the cement industry also needs to live. These two things should not be a zero-sum game.

2026-08-18 16:37:03

In the second half of the year, nine clinker lines with capacity exceeding 10 million tons are planned to be put into operation. Considering that the pressure of industry operation in the second half of the year is still high, it is expected that the release progress of new production capacity may not be as planned.

2026-08-18 10:09:22

The total investment of this technical transformation project is 57.24 million yuan, including 9 million yuan for environmental protection, accounting for 15.7% of the total investment.

2026-08-17 13:30:34

In recent years, with excellent product quality and perfect after-sales service system, Huaxin Building Materials brand has won the trust of local prefabricated parts factories, mixing stations and other industrial and civil customers.

2026-08-17 11:19:23

After the project is put into full operation, it is estimated that the annual output of cement clinker will be 1.8 million tons, the annual average sales revenue will be 447 million yuan, the tax revenue will be 80 million yuan, and nearly 100 new jobs will be created, which will effectively make up for the shortcomings of the regional building materials industry and optimize the local industrial structure.

2026-08-13 09:58:53

Fusui Xinning Conch New Building Materials Project (Phase II), EPC contracted by Guangxi Building Materials Institute, is setting off a construction boom, and an aggregate production line with an annual output of 5 million tons is gradually changing from design drawings to realistic outlines.

2026-08-10 15:33:26

Recently, the intelligent commercial concrete station project of Hebei Jinyu Dingxin Cement Co., Ltd. was officially completed and put into operation. The total investment of the project is 50 million yuan, with a planned annual capacity of 1.2 million cubic meters.

2026-08-10 15:05:12

Project overview: After the completion of the project, the annual output of cement will be 1 million tons. Buildings and structures such as clinker warehouse, auxiliary material warehouse, power distribution room and control room are mainly newly built with an area of 3371.1m ², and the original clinker warehouse, cement finished product warehouse, auxiliary material warehouse and other buildings with an area of 4155.52m ² are utilized.

2026-08-10 09:50:51

Sapalbek Tuyakbayev, founder of Primus Capital, said the company was working with Sinoma Cement to build a high-tech production facility that would meet leading international standards for energy efficiency and environmental safety.

2026-08-07 09:30:12

The project is located in Yaojiagang Chemical Industry Park, Zhijiang, Yichang City, Hubei Province. A set of acid production line with an annual treatment capacity of 2 million tons of phosphogypsum will be built to co-produce 750,000 tons of cement clinker per year and 600,000 tons of sulfuric acid.

2026-08-06 10:03:50

Guizhou Qianxi Southwest Cement Co., Ltd. plans to expand the existing cement clinker production line from 2000 t/d to 3000 t/d, replace the raw material and fuel by co-processing the general solid waste with the cement kiln, and upgrade the denitrification system.

2026-08-03 10:36:29

The breakthrough of the installation node has created favorable conditions for the subsequent equipment installation and process promotion. During the construction period, the owner, Taiwenlong Cement, gave full trust and collaborative support, and the two sides cooperated closely to overcome the difficulties.

2026-08-03 09:33:58

The two replacement schemes failed to be organized and implemented for some reasons, and the application for cancellation was submitted after the consensus of Gezhouba (Zhongxiang) Cement, Gezhouba (Jiayu) Cement and Gezhouba (Xingshan) Cement.

2026-07-24 09:47:24

With a high gross profit margin of 40.13%, the aggregate business has become an important profit pillar of the company, forming an efficient synergy with the main cement industry.

2026-07-22 10:30:05

It is understood that the total investment of Mudanjiang North Far East Cement New Dry Intelligent Cement Clinker Production Line Project with a daily output of 5000 tons is 1.05 billion yuan, including mining system, raw material preparation system, clinker firing system, product storage and transportation system and 9 MW waste heat power generation system.

2026-07-13 11:05:05

Xinzhou Shanshui Environmental Protection Technology Materials Co., Ltd. (A wholly-owned subsidiary of Shanxi Shanshui Cement Co., Ltd.) will build a 4500t/d clinker production line with a replacement ratio of 1:1.

2026-07-13 09:30:30

A 4000t/d new dry process cement clinker production line has been built, and the annual output of clinker production line is 691700 tons.

2026-07-02 15:54:00

At the same time, Pingba Branch Bureau of Ecological Environment Bureau of Anshun City, Guizhou Province issued the Announcement of the Draft of Environmental Impact Assessment of Taiwan Cement (Anshun) Cement Co., Ltd. on Transferring the Capacity of a Clinker Production Line with a Daily Output of 4000t/d, Retaining the Capacity of a Clinker Production Line with a Daily Output of 5000t/d and Annual Output of 4 Million Tons of Cement Grinding System and Related Facilities and Equipment.

2026-07-01 09:53:37

Construction scale and content: Capacity replacement (non-new project) shall be carried out in accordance with the requirements of the Implementation Measures for Capacity Replacement of Cement and Glass Industry (2024 version) (Ministry of Industry and Information Technology original (2024) No.206).

2026-06-29 10:01:13

China Smelter recently won the bid for nearly 5.5 billion yuan of engineering projects, demonstrating its strong market competitiveness and order acquisition ability in the field of metallurgical construction and infrastructure.

2026-06-23 16:13:47

The total investment of the project is 107.03 million yuan, the total floor area is 10819 m2, and the construction content includes two sets of fully enclosed 140m3/H concrete mixing production lines, one set of 205t/H aggregate production line and related auxiliary building facilities in the plant area. The two production lines are planned to produce 170,000 m3 of commercial concrete (including 70,000 m3 of precast concrete components) and 700,000 tons of sand and gravel annually.

2026-06-23 11:32:49

The three contracts signed this time include: Tororo Steel Plant Construction Project with an annual output of 600,000 tons in Uganda, Kabale Iron Ore Mining Project with an annual stripping capacity of 2.4 million tons in Uganda, and Lithium, Tantalum-Niobium and Tin Mining Project in Rwanda.

2026-06-23 10:23:10

According to local official media reports earlier this year, the production line is expected to enter the trial production stage in July 2026.

2026-06-23 09:56:28

After the completion of the project, the annual production capacity of 800000 cubic meters of concrete and 200000 tons of cement prefabricated parts will be formed.

2026-06-22 15:31:30

As the highest single building of the project and an important part of the core process system of the cement production line, the successful capping of the preheater tower marks an important stage achievement of the project construction and creates favorable conditions for the subsequent equipment installation and system commissioning.

2026-06-22 10:30:21

It is reported that the project is a key construction project of the 14th Five-Year Plan in Hebei Province and a key control project of Beijing-Tianjin-Hebei transportation integration. The route is about 46 kilometers long, starting from the G95 high-speed Gu'an East Interchange and ending at the west bridge head of the overpass bridge across the Beijing-Guangzhou Railway.

2026-06-18 13:49:37

According to previous media reports, some people reported that the project of "Beidou High Precision Major New Infrastructure Intelligent Monitoring System" along the Jiwei Expressway in Shandong Province had serious quality problems in the construction process.

2026-06-18 11:55:32

In May 2025, Jixiang Cement Co., Ltd. and ASEAN Energy Technology Co., Ltd. formally signed the overall lease agreement of the whole project, relying on the strong industry accumulation and mature market resources of the partners to focus on the resumption of production, firmly hold the bottom line of value preservation and appreciation of state-owned assets, and open up a new path of long-term sustainable development of the project!

2026-06-09 10:50:05

It is reported that Yunnan Jianfeng Dazhan Cement Co., Ltd. plans to invest 997 million yuan to build a new dry cement production line with a daily output of 4000 tons of clinker. The kiln tail is equipped with double-series six-stage low-pressure loss cyclone preheater and TDF calciner, and supporting construction of pure low-temperature waste heat power generation system, desulfurization and denitrification system, etc.

2026-06-09 10:30:33

After the completion of the project, the annual output of cement grinding will be expanded from 1.45 million tons to 1.8 million tons, and the cement bulk capacity will be increased by 350,000 tons per year. The land nature of the construction project is industrial land, which conforms to the industrial policy.

2026-06-08 10:51:16

This project plans to build standardized factory buildings, warehouses, comprehensive office buildings and other production supporting buildings, and build two new environment-friendly concrete mixing production lines and one cement prefabricated part production line, forming an annual production capacity of 800000 cubic meters of concrete and 200000 tons of cement prefabricated parts.

2026-06-04 11:11:48

The announcement shows that the top three successful candidates are Tianjin Cement Industry Design and Research Institute Co., Ltd., Chengdu Building Material Industry Design and Research Institute Co., Ltd., China Railway 19th Bureau Group First Engineering Co., Ltd., and Anhui Conch Building Material Design and Research Institute Co., Ltd.

2026-06-03 14:16:21

On the whole, the clinker manufacturing process of the phosphogypsum acid co-production clinker project is very close to the ordinary new dry clinker production process, and many of the equipment used are general equipment in the cement industry.

2026-06-02 14:01:57