On March 25, the Environmental Protection Bureau of Yangchun City, Guangdong Province, issued a public notice on the review of the environmental impact assessment documents of Yangchun 80 MW Agricultural Hybrid Photovoltaic Power Generation Project of Yangchun Nuclear Run New Energy Co., Ltd.
According to the announcement, the project is located in Gaocheng Village, Nanyong Village, Guigang Village, Shangli Village, Naqi Village and Dalang Village, Guigang Town, Yangchun City, Yangjiang City, Guangdong Province, and is constructed by Yangchun Kerun New Energy Co., Ltd . The total investment of

the project is 502.2 million yuan , and the total installed capacity is 80 MW. It is planned to select 575 Wp (N type) single-sided monocrystalline silicon modules . Each set of brackets is equipped with 26 modules, and the vertical double-row arrangement is adopted; It is divided into 25 power generation units, each of which has an installed capacity of about 3.125 MWp.
The project adopts the integrated wiring mode of 10 sets of 320kW series inverters and 1 set of 3150 kVA step-up transformer, 6 ~ 7 step-up transformers are T connected to one incoming line, and a total of 4 collector circuits are led to the 35 kV collector cabinet. The voltage is boosted by the main transformer and then sent out by a 110kV overhead line. The content of the
booster station was previously approved by Yangjiang Ecological Environment Bureau on August 28, 2023. The construction period of the
project is 6 months .