On July 14, Shanxi Lu'an Solar Energy Technology Co., Ltd. Photovoltaic holding subsidiary of Jinneng Holding Power Group Co., Ltd .
The announcement shows that the bidding project is located in Luzhou District, Changzhi City, Shanxi Province, and is divided into nine bidding sections.
Among them, bid section 1 is the bidding of module supplier frame; bid section 2 is the bidding of photovoltaic junction box frame; bid section 3 is the bidding of photovoltaic glass frame; Bid Section 4 is the bidding of module cell frame; Bid Section 5 is the bidding of photovoltaic silica gel frame; Bid Section 6 is the bidding of module packaging material frame; Bid Section 7 is the bidding of module aluminum frame; Bid Section 8 is the bidding of module welding strip and bus bar frame; Lot 9 is a component " The requirements for bidders in this tender are as follows:
Except for Lot 4, bidders in other lots are required to be manufacturers of the corresponding tender products. Agents are not allowed to bid .
In addition, The bidder's performance requirements for each lot from June 1, 2023 to the deadline for bidding (the contract signing date is during this period) are as follows:
Lot 1 requires the bidder to provide one item within the specified time. The accumulative supply performance of PV modules shall not be less than 500 MW , and at least one contract shall not be less than 50 MW ; The bidder of
Bid Section 2 must have a cumulative supply performance of not less than 1.1 million sets of photovoltaic junction boxes within the specified time; The bidder of
Lot 3 must have a cumulative supply performance of not less than 2 million pieces of photovoltaic glass within the above time range; The bidder of
Lot 4 must be a manufacturer or distributor with the production capacity of photovoltaic cells, and no authorization is required. In terms of performance, within the above-mentioned time limit, there must be a cumulative supply performance of not less than 50 million pieces of component batteries (distributors participating in the bidding). The self-owned performance of the distributor or the performance of the manufacturer submitted by the distributor shall be deemed as valid performance; the manufacturer corresponding to the self-owned performance provided by the distributor shall be consistent with the manufacturer of the bidding products of this project.);
the bidder of bid section 5 must have a cumulative supply performance of not less than 300,000 kg of photovoltaic sealant within the specified time; The bidder of
Bid Section 6 must have a cumulative supply performance of not less than 10,000 sets of component packaging materials within the specified time; The bidder of
Bid Section 7 shall have a supply performance of providing aluminum frames of components with a total of no less than 1.1 million sets or 440 Ten thousand/piece ; The bidder of
bid section 8 must have one supply performance of providing component welding strip and bus bar within the specified time. The total amount of the two is not less than 300 tons ; The bidder of
Bid Section 9 must have a cumulative supply performance of not less than 7.5 million square meters of component film within the specified time. Consortium bidding is not allowed for
the above bid sections.The bid opening time of each
bid section is as follows:
Bid Section 1 : 09:00, August 3, 2026;
Bid Sections 2 and 3 : 09:00, August 4, 2026;
Lot 4 and 5 : 09:00, August 5, 2026;
Lot 6 and 7 : 09:00, August 6, 2026;
Bid section 8 and 9 : 09:00, August 7, 2026.