Recently, Huadian Group issued a tender announcement for EPC general contracting of three photovoltaic projects, involving Guizhou and Sichuan, with a total capacity of 2010 MW. Details are as follows:
Guizhou 200 MW Photovoltaic Project EPC Tender
On November 10, Zhenfeng Huaxin New Energy Co., Ltd. Zhenfeng County Shuangfeng Photovoltaic Power Station Project EPC General Contracting Tender Announcement was issued, and the tenderer was Guizhou Huadian New Energy Development Co., Ltd.
The project is located in Naweng Village, Lurong Township, Zhenfeng County, Qianxinan Prefecture, Guizhou Province. The proposed installed capacity is 200 MW (DC side capacity 242.
This tender requires the bidder to have the qualification of general contracting of power engineering construction at or above the first level issued by the competent national construction department and to have an effective safety production license; Or have the qualification of Grade B or above of engineering design power industry (new energy power generation) issued by the competent national construction department. Consortium bidding is not accepted for
this project .
Submission deadline/bid opening time: 9:00 on December 1, 2026. EPC Bidding
for
Sichuan 1810MW Photovoltaic Project on November 6, Sichuan Huadian Liangshan Jinyang Yongfeng Photovoltaic Power Generation Project EPC General Contracting and Sichuan Huadian Aba Hongyuan Anqu Phase II 750000 kW Photovoltaic Project EPC General Contracting Tender Announcement was issued.
Liangshan Jinyang Yongfeng Photovoltaic Power Generation Project is located in Jinyang County, Sichuan Province, with a total installed capacity of 1,060MW and a project performance period of 685 days. The project is divided into two bid sections, the details are as follows:
among them, the capacity of bid section I is 750MW , which is planned to enter the site on December 15 this year, and the main body will be started on March 1, 2027. Full-capacity grid connection on October 31, 2028 (all
, The bidding scope includes but is not limited to: the main works of the photovoltaic power station in the bid section,
Among them, the bid section II shall be ensured to have the operation conditions of 200MW before December 20, 2027.". The performance requirements for bidders of bid sections
I, II and III are as follows: ▪ Independent bidders: from January 1, 2021 to the deadline for bidding (subject to the time of commissioning). It shall have at least one single project of 200MW and above centralized high-altitude (3000m and above) photovoltaic main project construction (or EPC or PC) general contracting and operation performance. ▪ The bidder of consortium bidding: the leading party of the consortium from January 1, 2021 to the deadline for bidding (subject to the time of commissioning). It should have at least one single project of 200MW and above centralized high-altitude (3000m and above) photovoltaic main project construction (or EPC or PC) general contracting and commissioning performance. The members of the consortium shall have the performance of the general contract for the construction of the main centralized photovoltaic project (or EPC or PC) from January 1, 2021 to the deadline for bidding (subject to the time of signing the contract).
It is worth noting that Bid Section III requires independent bidders and consortium leaders to meet the above performance requirements. It is also necessary to have at least one general contracting and commissioning performance of 220kV and above voltage level booster station project construction (or EPC or PC) within the above time range.
Liangshan Jinyang Yongfeng Photovoltaic Power Generation Project and Aba Hongyuan Anqu Phase II 750,000 kW Photovoltaic Power Generation Project are all subject to consortium bidding. The number of members of the consortium shall not exceed 2 .
Submission deadline/bid opening time: 10:00, November 27, 2026.