of November 13, Jingwei issued the Announcement on Major Litigation Matters of Wholly-owned Subsidiaries, and Hangzhou Hongsheng Electric Power Design Consulting Co., Ltd. (Hereinafter referred to as "Hongsheng Electric Power"), a wholly-owned subsidiary of the company, received the Notice of Response from the People's Court of Changxing County, Huzhou City, Zhejiang Province. Three companies including Hongsheng Power were sued due to the dispute over the EPC general contract of the "Peaceful Co-storage" Integrated Smart Energy Phase I Project, with a total claim amount of 103.0843 million yuan .
It is reported that the plaintiff Power Investment Zhejiang Storage (Changxing) Intelligent Energy Co., Ltd. (Formerly known as State Power Investment Group Changxing Energy Storage Co., Ltd.) The defendant Hongsheng Electric Power, Zhejiang Taihu Nenggu Technology Co., Ltd. and Zhejiang Changxing Electric Engineering Co., Ltd. were sued. Request that the three defendants be ordered to jointly compensate the plaintiff for the loss of discharge capacity caused by battery quality problems, the interest during the period of capital occupation, the loss of battery replacement, the lawyer's fee paid for this case, the case acceptance fee, the litigation preservation fee and the preservation insurance fee, totaling 103.0843 million yuan.
At present, the case has been filed and has not yet been heard.

From the contract dispute
four years ago, in November 2022, the EPC general contracting project of the "peaceful co-storage" integrated smart energy project started bidding.
Bidding information shows that the project is located in Wushan Industrial Park, Heping Town, Changxing County, Huzhou City, Zhejiang Province, with a total of 100.8 MW/1061.683 MWh of "Peace Co-storage" comprehensive intelligent energy project, and 45.36 MW/477.757 MWh of energy storage power station in the first phase of the project. It includes the design, construction and equipment supply of the power station, including lead-carbon battery , battery management system and energy storage power station access system engineering.
In December of the same year, a consortium composed of Changxing Taihu Energy Valley Technology Co., Ltd., Hongsheng Power and Zhejiang Changxing Electric Engineering Co., Ltd. finally won the EPC contract for the first phase of the project with an amount of 1,008,598,850 yuan (equivalent to about 2.11 yuan/Wh).
It is noteworthy that the information shows that during the construction of the project, Hongsheng Electric Power is responsible for the design of the project, and Taihu Energy Valley undertakes the operation and maintenance tasks of the whole life cycle of the project. Tian Eye Check information shows that Zhejiang Changxing Electrical Engineering Co., Ltd. is mainly engaged in construction and installation business.
According to the Economic Daily and other media reports, about 3 million lead-carbon batteries in the "Peaceful Co-storage" project are provided by Tianneng, with more than 1.6 million in the first phase.
In addition, the Digital New Energy DataBM. Com noted that this is not the first time that Jingwei shares have been listed as defendants for such EPC projects. On January 16
this year, the company disclosed a major litigation announcement. In one case, Zhejiang Electric Power Investment Energy Valley Energy Development Co., Ltd. sued Taihu Energy Valley, China Construction Third Engineering Bureau First Construction Engineering Co., Ltd. and Hongsheng Electric Power . The amount involved is about 100.2 million yuan , and the cause of the case is the dispute over the construction contract of the construction project.
The announcement shows that in August 2023, the three defendants formed a consortium to win the bid for the EPC service provider framework procurement project of the plaintiff's energy storage project in 2023-2024. Hongsheng Electric Power is also responsible for the design of the project as a participant in the consortium.
The plaintiff, Zhejiang Power Investment Energy Valley Energy Development Co., Ltd. , demanded that the three defendants bear the liability for breach of contract and compensate for the loss on the grounds that the construction period of the project involved exceeded the contract agreement and the quality problems of the batteries caused losses to the plaintiff. The three defendants, as parties to the consortium, are required to bear joint and several liabilities for the performance of the contract.
On November 13, Jingwei shares disclosed in the announcement that as of the date of this announcement, the company and its subsidiaries Hongsheng Electric Power and Zhejiang Hongneng Electric Power Co., Ltd. Since January 17, 2026, the total amount involved in litigation, arbitration and other matters is about 113.0227 million yuan , which exceeds 10% of the latest audited net assets of the company. Among them, the amount involved by the Company and its subsidiaries as the plaintiff was RMB5,126,600, and the amount involved by the Company and its subsidiaries as the defendant in 6 cases was RMB107,896,100 (including the amount of this major litigation). The third quarterly report

of 2026 shows that in the first three quarters, the company achieved a total operating income of 198 million yuan, a decrease of 42.44% compared with the same period last year; the net profit loss attributable to the parent company was 38.2116 million yuan, compared with 15.6872 million yuan in the same period last year; the net profit loss deducted from non-profits was 41.4022 million yuan, compared with 13.4286 million yuan in the same period last year. The net cash flow generated from operating activities was-155 million yuan, compared with 16 million 131 thousand and 100 yuan in the same period last year.