Up to 0.754 yuan/W! Huadian Gansu 800MW PV Module Procurement Successful Candidate Announcement!

2026-02-28 11:32:02

On February 27, Huadian Group issued a notice of successful candidates for the 800000 kilowatt high-efficiency photovoltaic module procurement bidding project in Hexi New Energy Base, Tengger Desert, Gansu Province.

On February 27, Huadian Group issued a notice of successful candidates for the 800000 kilowatt high-efficiency photovoltaic module procurement bidding project in Hexi New Energy Base, Tengger Desert, Gansu Province.

According to the announcement, there are two successful candidates. They are Longji Leye Photovoltaic Technology Co., Ltd. and Zhejiang Aixu Solar Energy Technology Co., Ltd . The winning unit price is 0.754 yuan/W and 0.704 yuan/W respectively. On November 24,

2025, Huadian Group released the PV module procurement project with a capacity of 800MW. Among them, Gansu Tengger Desert Hexi New Energy Base Jiudun Beach 3 million kilowatt photovoltaic project in Liangzhou District, Wuwei City, plans to purchase 632000 kilowatt high-efficiency photovoltaic modules . Hongshagang 800000 kilowatt photovoltaic project in Minqin County plans to purchase 168000 kilowatt high-efficiency photovoltaic modules .

This procurement requires that the maximum power of the module is not less than 650 W, the front photoelectric conversion efficiency is not less than 23.8%, and the peak power of the back is not less than 70% of the front. (For details, please click: Huadian Gansu 800MW PV Module Procurement Bidding!

All can be viewed after purchase
Correlation

On March 27, China Railway 11th Bureau Group Co., Ltd. issued a tender announcement for photovoltaic framework procurement in 2026-2027.

2026-04-01 09:01:33

On March 27, the change announcement of EPC general contracting project of 100MWp household distributed photovoltaic power generation in Hulunbuir City, Inner Mongolia was issued. The announcement shows that the installed capacity (DC side) in the original tender content will be changed from 200 MW to 100 MW, and other contents will remain unchanged.

2026-03-31 11:43:07

On March 27, Jinzhong Heshun 200 MW/800 MWh Shared Network Energy Storage Power Station EPC General Contracting Tender Announcement was issued. The tenderer is Jinzhong Xinruineng Technology Co., Ltd. The total investment of the project is 750 million yuan, equivalent to a unit price of 0.94 yuan/Wh.

2026-03-31 10:59:44

Digital New Energy DataBM. Com was informed that on March 27, the successful candidate for EPC general contracting project of Phase II 100000 kW photovoltaic project in Qinshui County, Jincheng City, Shanxi Province was announced.

2026-03-30 17:33:07

As a native of Baoshan Xinjie and a salesman of Baoshan Conch, in my childhood memory, catching up with the big market is the most common daily life of the villagers, but it also hides many inconveniences. In the scattered markets a few kilometers away, due to geographical and transportation constraints, vendors have few types of goods, and the freshness of fruits and vegetables is also a problem. When it rains, it is even more muddy and difficult to walk. "When will there be a decent farmer's market in Xin Street?" The villagers have been talking about this for many years, and it is also the expectation I hid in my heart when I was young. Now, this expectation has finally come true.

2026-03-30 11:56:13

The total investment of this project is about 6 billion yuan, the land area is about 500 mu (subject to the actual land acquisition by bidding, auction and listing), and the construction of 60 G Wh energy storage (power) battery production base project.

2026-03-30 10:20:01

The report shows that in 2026, the company plans to sell about 67 million tons of cement and clinker, 190 million tons of aggregate and 30 million cubic meters of concrete globally, with total revenue expected to exceed 40 billion yuan.

2026-03-30 10:12:16

On March 24, the tender announcement for EPC general contracting of Chongqing Huadian Fuling Dishui 60.48 MW Photovoltaic Power Generation Project, a related project of Chongqing Branch of China Huadian Corporation, was issued.

2026-03-30 09:06:38

On March 25, China Railway Tunnel Bureau Group Construction Co., Ltd. Bobai County Government Assets Roof Distributed Photovoltaic Power Generation Project (South Area) EPC General Contracting Project Photovoltaic Module Procurement Tender Announcement was issued.

2026-03-30 09:06:28

On March 25, the successful candidate for EPC general contracting of 100m W fishing-photovoltaic complementary photovoltaic power generation project in Wangji Town, Siyang County, Jingneng was announced.

2026-03-30 09:02:10

On March 26, the tender announcement for the general contracting (EPC) of the 1 million kilowatt "grass-light complementary" photovoltaic project of Shima Bingdi Integration of the Eighth Division was issued.

2026-03-27 17:58:58

First-line manufacturers generally take action to reduce production, compared with the high production schedule in March, the production schedule of components was reduced by 5-30% in April.

2026-03-27 17:58:19

On March 25, the successful candidate of Jingxu Yaodu 200 MW Photovoltaic Power Station EPC Project was announced.

2026-03-26 17:49:51

On March 25, the bidding results of the energy storage system framework procurement project of CGN New Energy in 2026 were officially announced. The procurement scale of the project reached 7.2 GWh, and the tenderer was CGN Wind Power Co., Ltd.

2026-03-26 16:55:39

The new Wuhan hub through line project is drawn from Yunmeng East Station of Hanshi high-speed rail, with Xiaogan South Station and Hanyang Station, crossing the Yangtze River along the Third Ring Road of Wuhan City, with Baishazhou Highway and Railway Yangtze River Bridge, and connecting Wuhuang Intercity after crossing the river. The newly-built main line is 72.193 km long (the length from the junction point of Yunmeng East to the dividing point at the north end of the same line with Wuyi is 40.149 km; the length from Zoumaling Line Station (excluded) to Huangjiahu Line is 32.044 km long), and the connecting line is 8.605 km long. Among them, the main bridge of the newly-built Baishazhou Rail-cum-Road Yangtze River Bridge is 2623 meters long, and the first-and second-line railways, upper highways and synchronous construction of the rail-cum-road joint construction section on both sides of the river

2026-03-26 16:46:22

Including 492 super charging stations and related supporting construction, scheme design within the scope of land use, deepening optimization and approval, material and equipment procurement, supporting equipment procurement and installation, and all construction contents within the scope of construction (construction general contracting until completion acceptance, defect repair within the quality defect liability period, maintenance within the warranty period and other related work).

2026-03-25 13:57:10

Land use scale: the total land area is 47331. 32 square meters (subject to the scope designated by the planning and natural resources department)

2026-03-25 13:55:35

The total construction area is about 300000 square meters, including R & D building, ultra-supercritical production workshop, supercritical production workshop, enzyme preparation workshop, warehouse, pilot production workshop, preparation workshop, extraction workshop, comprehensive preparation workshop and supporting facilities.

2026-03-25 13:55:23

Digital New Energy DataBM. Com was informed that on March 24, the successful candidate of Matai 250MWp Photovoltaic Project Design and Construction (EPC) in Linxiang District, Lincang City, Yunnan Province was announced.

2026-03-25 11:38:58

In 2025, the company's operating income was 0 yuan, net profit was 334 million yuan, total assets were 586 million yuan, total liabilities were 797 million yuan, and owner's equity was-211 million yuan.

2026-03-25 10:06:04

Digital New Energy DataBM. Com was informed that on March 20, the invitation announcement for EPC general contracting of 100MWp distributed photovoltaic project in Zhangzhou City, Fujian Province was issued, and the tenderer was Fujian Xingchu New Energy Technology Co., Ltd.

2026-03-24 18:17:49

On March 20, Shanxi Province issued two tender announcements for energy storage projects, covering EPC and energy storage equipment, with a total scale of 460 MW/1.4 GWh.

2026-03-24 16:09:22

Recently, Xinjiang Changji Guotou issued an announcement on the termination of the procurement of energy storage system equipment for four shared energy storage projects, with a total scale of 800 MW/3.2 GWh, all due to the adjustment of the bidding plan.

2026-03-24 11:06:31

According to the incomplete statistics of the Digital New Energy DataBM. Com, the capacity of the announced photovoltaic module bidding and shortlisted projects increased significantly to 39.05 GW in two weeks (3.6-3.20), and the total number of photovoltaic module bidding projects increased to 4.27 GW at the same time.

2026-03-21 12:40:06

On March 17, CGN Jiangsu Jianhu County Fishing and Photovoltaic Complementary Phase II 200 MW Photovoltaic Power Generation Project EPC General Contracting Project Component Equipment Tender Announcement was issued, and the tenderer was China Energy Construction Group Jiangsu Electric Power Design Institute Co., Ltd.

2026-03-20 17:25:15

This week, the photovoltaic module market is like a "roller coaster" type of fluctuations, the head manufacturers have not yet improved in price reduction transactions, followed by rumors of price increases.

2026-03-20 14:53:07

EPC General Contracting of Supporting Wharf Works of Zhangjiagang Haijinjiang LNG Terminal Project (Suzhou LNG Reserve Center) in Dongsha Operation Area of Zhangjiagang Port Area of Suzhou Port

2026-03-20 09:35:40

LCBDa Hydropower Station is located in CY County, XZCD City. The dam site is located in the upstream reach of LCJ at the entrance of Serugou, br Township, CY County. It is the fourth stage of the one-reservoir eight-stage development scheme in the hydropower planning of the upstream of LCJ (the reach in XZ). The dam type development is adopted. The power station is about 125 km away from cy County, about 226 km away from CD City, and about 175 km away from MK County. The installed capacity is 1500 MW, and the project scale is a first-class large (1) project. The layout of the project is RCC gravity dam + flood discharge system of the dam body + diversion system of the dam body on the left bank + underground powerhouse on the left bank. The dam consists of non-overflow dam section, ecological flood discharge hole dam section,

2026-03-20 09:25:53

Shanghai Construction Engineering has successfully won two major projects with a total amount of more than 1.4 billion yuan, demonstrating its strong competitiveness and market advantages in the field of large-scale engineering construction.

2026-03-20 09:20:28

According to the Ministry of New and Renewable Energy of India, the government has extended the application of the Approved Model and Manufacturer List (ALMM) framework to solar silicon ingots and wafers to strengthen the development of the country's photovoltaic manufacturing industry.

2026-03-19 16:42:57

Shanshui Group invites public bidding for the + 80m slope treatment, platform ecological restoration and green mine upgrading project of Hutishan Mine in Zaozhuang, and adopts the pre-qualification system, requiring bidders to have corresponding qualifications, performance and good credit.

2026-03-19 16:09:24

The project is located in Mabian Yi Autonomous County, Leshan City, Sichuan Province. The full name of the project is Mabian Yi Autonomous County Oil Rock Building Stone Limestone, Building Basalt Mine Development Project Design and Construction General Contracting. At present, the project has been approved by the relevant approval, approval or filing authorities, and has met the bidding conditions. This time, the construction unit is selected by means of public bidding. The source of funds for the project is self-raised funds, with a total amount of 98,500 yuan 77777. The tenderers are Mabian Zhengye Science and Technology Development Co., Ltd. and Zhongying Zhengye Construction and Development (Sichuan) Co., Ltd.

2026-03-19 11:19:14

The total building area of T3 terminal is 452,500 square meters, with 6 floors above ground and 2 floors underground, and the building height is 46.80 meters. The main body is of reinforced concrete frame structure and the roof is of steel structure.

2026-03-19 11:19:07

China Huaxin Cement is interested in bidding for the cement business of Brazilian steel giant CSN.

2026-03-19 11:01:28

The overall bidding unit price is 0.735-0.780 yuan/W, and the average unit price is 0.743 yuan/W.

2026-03-19 10:10:28

On March 18, Huarun yuantong Longhua 80MW Photovoltaic Power Generation Project Photovoltaic Field PC Project Tender Announcement was issued, and the tenderer was Huarun yuantong (Longhua) New Energy Co., Ltd.

2026-03-19 09:52:54

On March 16, the successful candidate of EPC general contracting project of Xiaxiong 50 MW photovoltaic project in Ganzi County, Ganzi Prefecture, Sichuan Province, was announced.

2026-03-18 16:49:14

On March 13, Chongqing Fengdu 80MW "Camellia oleifera + photovoltaic" industrial project EPC project general contracting tender announcement was issued, the tenderer was Fengdu Sanneng New Energy Co., Ltd., and the source of project funds was self-financing 34789 71000 yuan.

2026-03-18 16:09:01

On March 17, Beijing Energy Group Co., Ltd. issued a tender announcement for the procurement project of photovoltaic module framework in 2026. Purchase 2GW of N-type TOPCon modules and 2GW of N-type BC modules respectively.

2026-03-18 15:26:07

On March 13, Fujian Company Fuzhou Power Plant Fuqing Baige Mountain 350 MW Fishery Complementary Photovoltaic Power Station Project (Section A) EPC Project Public Bidding Announcement was issued, and the tenderer was Guoneng (Fuzhou) Thermal Power Co., Ltd.

2026-03-18 13:28:42

On March 17, Beijing Energy Group Co., Ltd. issued a tender announcement for the procurement project of photovoltaic module framework in 2026.

2026-03-18 13:20:44

On March 17, (Sichuan Company) Ganzi Daocheng Gatong Phase I Photovoltaic Power Generation Project announced the successful candidate for EPC general contracting.

2026-03-18 13:10:19

The construction scale is 120MW, installing 14 sets of wind turbine generator units with a single unit capacity of 5.0MW and 8 sets of wind turbine generator units with a single unit capacity of 6.25MW (the final model and single unit capacity shall be determined through equipment bidding), and jointly building a 110kV booster station with the company's proposed Panzhou Dashan Wind Farm and Panzhou Xiangshui Town Dalongtan Phase I Agricultural Photovoltaic Power Station.

2026-03-18 11:26:38

The first phase of Xuzhou Urban Rail Transit Line 4 starts from Qiaoshang Village Station at the intersection of Zhujiang Road and Daxue Road, runs northward along Daxue Road-South Third Ring Road through Zhaishan District to Daguozhuang Airport District, then along Hanyuan Avenue-Chang'an Avenue-Yangshan Road-Pantaoshan Road, and ends at Tuolanshan Road Station at the intersection of Tuolanshan Road and Jingong Road.

2026-03-18 11:26:33

The project starts from the east of Linyu Bridge in the west, connects with the existing Science and Technology Avenue (Linan Section), and ends at the 6 # shield well in the north of Nanhu embankment in the east, with a total length of about 5 kilometers. The project is divided into two parts: the expressway system and the ground auxiliary road system. The expressway system is heavy. The underground expressway is about 1.77 km long, the ground expressway is about 3.25 km long, and the ground auxiliary road is about 3.76 km long. The main construction contents include road engineering, tunnel engineering, bridge engineering, pipeline engineering, tunnel electromechanical engineering and ancillary engineering.

2026-03-18 11:26:28

On March 16, the successful candidate for EPC general contracting project of Dalongtan Phase I Agricultural Photovoltaic Power Station in Xiangshui Town, Panzhou City, Liupanshui City, Guizhou Province was announced.

2026-03-17 16:22:13

According to the report of the International Energy Agency, at present, the cake of the energy storage industry is big enough-the entry of the giants will only magnify the growth potential!

2026-03-17 16:16:57

On the ninth day of the first lunar month, I traveled to Australia and New Zealand together. This trip was successful and comfortable. What we see is not only the scenery, but also the local social civilization, living in peace, leisure and dignity. After returning, the information, insights and introductions will be compiled, leaving a little trace of the journey, as well as the videos and photos taken by the group members for self-appreciation and sharing with friends and colleagues. Limited to ignorance, the views in the article may be one-sided or even fallacious, if there is any enlightenment, it is a great honor.

2026-03-17 10:56:12