On November 18, Ningguoyun Silicon Base Lingwu Phase II 1G W Photovoltaic Project Equity Investment + EPC General Contracting Tender Announcement was issued, and the tenderer was Ningguoyun Ruiyuan New Energy (Lingwu City) Co., Ltd.

The project is divided into one bid section, which is mainly divided into three parts: (1) survey and design of the whole stage of the bid section; (2) Equipment procurement and construction of 1000MW PV (rated capacity of AC side: 1000MW, scale of DC side: 1182MWp, capacity ratio: 1.182) area; (3) Equipment procurement and construction of 330kV booster station and power transmission and transformation line. The
tender announcement shows that the project is located in Lingwu City, Ningxia, covering an area of 24000 mu, and the installed capacity of the photovoltaic project is 1000 MW . DC side scale 1182 MWp . The project plans to build a 330 kV substation connected to Ningxia power grid, and the final access scheme shall be subject to the access system report. The scope of this
tender is equity investment + EPC general contracting of the project. In terms of
EPC general contracting, the bidder's work includes but is not limited to: project survey, preliminary design, construction drawing design, as-built drawing, equipment and materials and spare parts purchase. Procurement and installation of equipment, electrical and control systems, installation and construction of building engineering, equipment commissioning, system access, joint trial operation, technical training, training and acceptance of operators, etc.
The bidder shall provide the preliminary design scheme of the project in the bidding documents. The design scheme shall achieve the best design, the latest technology, the lowest cost, and adopt the grid-friendly design.
It is worth noting that the winning bidder of this tender (if it is the winning bidder of the consortium, it refers to the equity investor in the consortium) must provide the commitment documents (if it belongs to the group company). The commitment document must be issued by the group company) explicitly agreed to undertake to transfer 49% of Ningguoyun Ruiyuan New Energy (Lingwu City) Co., Ltd. held by Ningxia State-owned Capital Operation Group Co., Ltd. for not less than RMB 303 million. Equity interest in.

The project is planned to commence on December 25, 2025 (the specific commencement time is subject to the notice of the tenderee), and the construction period shall not exceed 187 calendar days.
This bidding requires bidders not only to have good business reputation and corresponding qualifications, but also to have specific requirements for finance and performance. In terms of
finance, the working capital used by the bidder to apply for the bid section (including cash resources with appropriate vouchers, letter of intent for bank loans, credit line, bank credit contract, etc. Or the amount of current assets-current liabilities in the financial audit report of 2024 shall not be less than 60 million yuan ; It has the corresponding self-owned capital strength and investment and financing capacity, and the deposit balance of its own capital in financial institutions is not less than RMB 80 million yuan . In terms of
performance, from January 2020 to the deadline for bidding (subject to the time of contract signing), the bidder must have the construction performance of one 220kV or above booster station. Consortium bidding is accepted for
this project .
Bidding deadline: 9:00, December 9, 2025.
浙公网安备33010802003254号