On April 14, the EPC general contracting project of the first bid section of Dingtang 300 MW/1200 MWh Shared Energy Storage Power Station Demonstration Project in Tongxin County, Ningxia, issued another extension announcement.
This is also the third time that the EPC tender for the project has been postponed.
On February 14, the first tender announcement of the project showed that the total construction scale was 300 MW/1200 MWh, 60 sets of 5 MW/20 MWh liquid-cooled energy storage units were planned to be built, and a 330kV booster station was built to connect a 330kV line to Dingtang 330kV substation. The total construction period was originally
planned to be 8 months, and the construction was planned to start on April 10, 2026. However, three postponement announcements were issued on March 6, March 23 and April 14. The latest information shows that the deadline for submission of bidding documents and the opening time of the project have been postponed to April 29.