The Digital New Energy DataBM. Com learned from the National Online Approval and Supervision Platform for Investment Projects that on July 4. Guangdong Kaiping Shengyuan Energy Co., Ltd. has passed the examination and approval of the 112841 of 23 kilowatt roof distributed photovoltaic power generation project of public institutions. According to the
data, the project is located in the towns (streets) and Cuishan Lake Management Committee of Kaiping City, Jiangmen City, Guangdong Province, with a total investment of 429 million yuan . The project uses the roofs of 251 public institutions such as Kaiping government units, institutions, educational institutions, medical institutions and state-owned enterprises to lay roof distributed photovoltaic, and the construction unit is Kaiping Shengyuan Energy Co., Ltd .
The equipment plans to use PV modules , brackets, inverters and other products to form a photovoltaic power generation system, with a planned installed area of 565,848.21 square meters. The designed total installed capacity is 112,841.235 kW , and the grid-connected mode adopts the full grid-connected mode. It is estimated that the annual average power generation after the completion of the project will be about 109,203,430 kwh. The
project period is from September 1, 2024 to September 1 , 2026. According to
the data, Kaiping Shengyuan Energy Co., Ltd. was established in March 2024 and is a state-owned enterprise controlled by Guangdong Kaiping Wenlu Development Group Co., Ltd.
It is reported that the 112841 of Kaiping Shengyuan Energy Co., Ltd. 235 kilowatt public institutions roof distributed photovoltaic power generation project EPC general contracting has announced the bidding results on August 21, 2024, the project is led by Wanbang Digital Energy Co., Ltd., and the members are Shenzhen China Net Electric Power Design Institute Co., Ltd.