On June 25, the bidding results of EPC general contracting for the 1.36 million kilowatt photovoltaic power generation project of Xinjiang Oilfield New Energy and Supporting Coal-fired Power and Carbon Capture Integration Project (Phase II) were announced. The project is divided into six bidding sections with a total scale of 1.36 GW. Bid section 1 to bid section 5
of the project have announced the results of winning the bid, and bid section 6 only announced the candidates for winning the bid on June 26. The bid-winning enterprises of
Bid Section 1 to Bid Section 5 are respectively: China Energy Engineering Group Hunan Thermal Power Construction Co., Ltd. , Guiyang Survey and Research Institute Co., Ltd. of China Power Construction Group, China Power Construction Ningxia Engineering Co., Ltd. , CNPC (Xinjiang) Petroleum Engineering Co., Ltd ., and Daqing Oilfield Construction Group Co., Ltd . The bid winning unit price of
bid section 1 to bid section 5 is between 0.68 yuan/W and 0.772 yuan/W.
The tender announcement shows that the project is located in Karamay District, Karamay City, with a total investment of 4,251,807,800 yuan . The construction unit is Xinjiang Oilfield New Energy Co., Ltd. and the rated installed capacity of the construction scale is 1360MW. The installed capacity at the DC side is 1634 14888 MWp (capacity ratio 1: 1.2), with 2,635,724 pieces of 620Wp monocrystalline silicon double-sided double-glass N-type modules installed. The main construction contents of
the project include photovoltaic modules , string inverters, booster box transformers, expansion of the built 750kV interconnection transformer, a 220kV booster gathering station, energy storage station, 220kV line and supporting communication, buildings and structures, etc.
It is reported that the Department of Ecology and Environment of Xinjiang Uygur Autonomous Region has announced the acceptance of the EIA of the project on March 20, 2025.