Four Yangtze River Bridges Under Construction in Hubei "Emerge" from the Ground

2023-05-31 09:30:19

The left bearing platform of No.6 main pier on Jiangling side of Guanyin Temple Yangtze River Bridge, invested by Hubei Trading and Investment Group and constructed by China Railway Construction Bridge Bureau, was completed.

On May 29, after 50 hours of continuous operation, the left bearing platform of No.6 main pier on Jiangling side of Guanyinsi Yangtze River Bridge, invested by Hubei Trading and Investment Group and constructed by China Railway Construction Bridge Bureau, was completed. So far, the construction of the main pier cap on both sides of the main bridge has been completed, and the construction stage of the main tower body has been entered, which greatly reduces the safety risk of construction in flood season.

Guanyinsi Yangtze River Bridge is the key maneuverability project of Jiangling-Songzi Section of Wusong Expressway. It is the world's largest span hybrid steel-UHPC composite girder cable-stayed bridge with double towers and double cable planes. It is also the world's first hybrid highway cable-stayed bridge exceeding kilometers. The Jiangling side needs to pour 4775 cubic meters of concrete at one time, which is technically difficult. In order to solve the problem of hydration heat of mass concrete, the project department of China Railway Construction Bridge Bureau adopted an intelligent temperature control system to control the temperature of concrete before entering the mould. At the same time, five layers of cooling circulating water pipes were laid in the bearing platform to strictly control the temperature of concrete. After testing, there is no crack after pouring.

As the province with the longest main stream of the Yangtze River, Hubei has accelerated the "hard connection" of the three metropolitan areas, and the construction of river-crossing channels is the most important. Since this year, four world-class Yangtze River bridges under construction have raced against the water level of the Yangtze River, ushering in a number of major nodes. On May 13, the construction of the main pier cap on the north bank of Shuangliu Yangtze River Bridge in Wuhan was completed. On May 11, the main pier bearing platform on the north bank of Bailizhou Yangtze River Bridge in Zhijiang was completed, while the main tower of Yanji Yangtze River Bridge was "rising step by step". With the completion of the final underground construction node of the Guanyinsi Yangtze River Bridge, all four Yangtze River bridges in Hubei have "emerged" from the ground and entered the construction of the main tower, which also marks a new stage in the construction of the bridge.

All can be viewed after purchase
Correlation

The foundation of No.2 building of Yuxi Grain Reserve Depot Construction Project (Phase I) in Yunnan Province was successfully poured, with a total of 3514 m ³ of C60 micro-expansive fiber concrete poured.

2023-06-01 11:11:24

Zhonghai Chengdu Tianfu New Area Super High-rise Project completed the mass concrete pouring of 41,000 cubic meters of floor on December 17, 2022. It took only 7 hours for the mass concrete construction technology to break through 10,000 cubic meters and 27 hours for 30,000 cubic meters, and the maximum pouring speed reached 1,600 cubic meters per hour.

2023-06-01 10:41:37

The left bearing platform of No.6 main pier on Jiangling side of Guanyin Temple Yangtze River Bridge, invested by Hubei Trading and Investment Group and constructed by China Railway Construction Bridge Bureau, was completed.

2023-05-31 09:30:19

93 bridge pile foundations, 22 tie beams for bearing platforms, 46 columns and ribbed slabs, 18 bent caps and abutment caps, 42 precast box girders, 3 culverts, concrete construction of cast-in-situ box girders on the left side of Jianshou Bridge, 350,000 m3 of earth and stone excavation and filling, and 1,500 m3 of concrete for subgrade retaining walls have been completed.

2023-05-22 16:03:07

The first bid section of the supporting infrastructure project of Datong Huanghua Industrial Park ushered in the first concrete pouring construction in 2023, and new progress was made in the project construction.

2023-05-17 10:25:05

The one-time pouring volume exceeds 13000 cubic meters of concrete, the pouring diameter exceeds 70 meters, the thickness reaches 3.9 meters, and the C20 concrete is used to complete the one-time pouring, which is equivalent to filling five standard swimming pools.

2023-05-16 16:57:20

On May 8, the first floor of Qingshan Tunnel, which was constructed by YL-YZ4 Project Department of Yilu Expressway of the Fourth Bureau of China Railway, began pouring, marking that the project has entered the construction stage of the main structure in an all-round way.

2023-05-11 14:28:10

With the last concrete in the tank truck entering the formwork, it marks the successful completion of the first aqueduct pier body of the main water conveyance canal (Huangtuling Diversion Sluice ~ Jiangjunling Diversion Sluice) double-track project of Xi'an Wangchuan River Diversion Lijiahe Reservoir Project of China Railway First Bureau.

2023-04-25 09:48:51

The Zhonghe Reservoir Project in Jinzhai County, which was constructed by Hefei Branch of China Anneng First Bureau, successfully extracted the RCC core sample with a length of 20.25 meters and a diameter of 200 millimeters from the No.10 dam section.

2023-03-29 09:43:01

On March 12, the main pier bearing platform of continuous beam across Wangyue Road of Fuhuai Railway Bid 2 began to be poured.

2023-03-15 11:50:47