Over 13000 cubic meters in 40 hours! Yanji Yangtze River Bridge hits new record again

2023-05-16 16:57:20

The one-time pouring volume exceeds 13000 cubic meters of concrete, the pouring diameter exceeds 70 meters, the thickness reaches 3.9 meters, and the C20 concrete is used to complete the one-time pouring, which is equivalent to filling five standard swimming pools.

On the afternoon

of May 13, after 40 hours of hard work day and night, the seventh pouring of core filling concrete for the back warehouse of the "8" shaped north anchorage of Yanji Yangtze River Bridge, which was invested by Hubei Trading and Investment and constructed by China Railway Bridge Bureau, was successfully completed, marking the end of the pouring of core filling concrete for the back warehouse of the north anchorage.

The one-time pouring of core filling concrete in the North Anchorage of Yanji Yangtze River Bridge exceeds 13000 cubic meters of concrete, with a diameter of over 70 meters and a thickness of 3.9 meters, and is completed with C20 concrete at one time, which is equivalent to filling five standard swimming pools. It is a one-time large-scale continuous concrete pouring organized again after the completion of the one-time continuous pouring of about 15000 cubic meters of concrete in 46 hours on April 21.

Since the opening of the pouring on the evening of May 11, a total of 5 concrete production lines, 7 day pumps, 20 concrete mixers and more than 200 construction workers have been put into the core filling pouring of the North Anchorage of Yanji Yangtze River Bridge. At the peak, the concrete production capacity reached 400 cubic meters, and the concrete mixers delivered more than 1300 times back and forth. The concrete was poured into the foundation pit of the anchorage area day and night, and finally the pouring task was completed with high efficiency and quality, and the new "Huanggang speed" was performed again.

In order to effectively cope with the difficulties of large volume, large area, long pouring time and difficult construction organization and coordination, the construction team of Yanji Yangtze River Bridge project carried forward the spirit of "four specialties" of the iron army in the construction of the bridge on the red earth, overcome difficulties, plan ahead and organize meticulously. Before construction, through organizing expert reviews with construction units and supervisors, the construction scheme is repeatedly demonstrated and optimized, and the division of responsibilities of team members in traffic security, material transportation, on-site pouring, concrete curing and other links is clarified. In the process, we should strengthen the management and control of the whole chain, strengthen the control of raw materials, optimize the mix ratio, give full play to the strength of Party members and youth commandos, do a good job in logistical support, arrange mechanical maintenance personnel to stand by at any time, and provide night snacks for night shift construction personnel, so as to ensure the efficient progress of anchor core pouring.

It is understood that after the completion of the pouring, the core filling operation in the north anchorage area of Yanji Yangtze River Bridge was nearly 90% completed. Chen Mingzhe, the site manager of the anchorage work area, said: "We actively carry out labor competitions, keep a close eye on the construction period nodes, reverse the schedule, and fight with wall charts. After the massive concrete pouring, it was completed nearly five months ahead of schedule. According to the current construction schedule, The back cabin of the north anchorage is expected to complete the core filling construction in late May, and at the same time, the construction of the front cabin of the anchorage is also advancing rapidly.

Yanji Yangtze River Bridge is designed with two towers and a single span, with a main span of 1860 meters. It is the first suspension bridge with four main cables of different sag in the world. It is also the first double-deck suspension bridge with four main cables of different sag ratio spans in the world. The north anchorage is the key project with the longest construction period and the largest volume in the whole concrete project of Yanji Yangtze River Bridge, with a total concrete consumption of 420,000 cubic meters and a total weight of more than 1 million tons. For such a double-deck suspension bridge, it can be said to be the "anchor" and its role is extremely critical.

Yanji Yangtze River Bridge is the second river-crossing channel connecting Ezhou and Huanggang, with an expressway on the upper level and an urban expressway on the lower level. The line of the second river-crossing channel (Yanji Yangtze River Bridge and Connection) in Hubei Province is about 26 kilometers long. It is a comprehensive supporting project for Hubei Province to build the fourth and first international logistics hub (Huahu Airport) in the world and the first in Asia. It is the key support for the construction of Huanggang Airport Economic Zone and the comprehensive transportation system for the construction of waterway and air transport in eastern Hubei Province. It is of great significance to give full play to the comprehensive benefits of the core logistics hub, improve the value of land use and investment attraction, stimulate the rapid growth of regional economy, and promote the high-quality development of the integration of Wuhan, Hubei, Huang and Huang.

All can be viewed after purchase
Correlation

The foundation of No.2 building of Yuxi Grain Reserve Depot Construction Project (Phase I) in Yunnan Province was successfully poured, with a total of 3514 m ³ of C60 micro-expansive fiber concrete poured.

2023-06-01 11:11:24

Zhonghai Chengdu Tianfu New Area Super High-rise Project completed the mass concrete pouring of 41,000 cubic meters of floor on December 17, 2022. It took only 7 hours for the mass concrete construction technology to break through 10,000 cubic meters and 27 hours for 30,000 cubic meters, and the maximum pouring speed reached 1,600 cubic meters per hour.

2023-06-01 10:41:37

The left bearing platform of No.6 main pier on Jiangling side of Guanyin Temple Yangtze River Bridge, invested by Hubei Trading and Investment Group and constructed by China Railway Construction Bridge Bureau, was completed.

2023-05-31 09:30:19

93 bridge pile foundations, 22 tie beams for bearing platforms, 46 columns and ribbed slabs, 18 bent caps and abutment caps, 42 precast box girders, 3 culverts, concrete construction of cast-in-situ box girders on the left side of Jianshou Bridge, 350,000 m3 of earth and stone excavation and filling, and 1,500 m3 of concrete for subgrade retaining walls have been completed.

2023-05-22 16:03:07

The first bid section of the supporting infrastructure project of Datong Huanghua Industrial Park ushered in the first concrete pouring construction in 2023, and new progress was made in the project construction.

2023-05-17 10:25:05

The one-time pouring volume exceeds 13000 cubic meters of concrete, the pouring diameter exceeds 70 meters, the thickness reaches 3.9 meters, and the C20 concrete is used to complete the one-time pouring, which is equivalent to filling five standard swimming pools.

2023-05-16 16:57:20

On May 8, the first floor of Qingshan Tunnel, which was constructed by YL-YZ4 Project Department of Yilu Expressway of the Fourth Bureau of China Railway, began pouring, marking that the project has entered the construction stage of the main structure in an all-round way.

2023-05-11 14:28:10

With the last concrete in the tank truck entering the formwork, it marks the successful completion of the first aqueduct pier body of the main water conveyance canal (Huangtuling Diversion Sluice ~ Jiangjunling Diversion Sluice) double-track project of Xi'an Wangchuan River Diversion Lijiahe Reservoir Project of China Railway First Bureau.

2023-04-25 09:48:51

The Zhonghe Reservoir Project in Jinzhai County, which was constructed by Hefei Branch of China Anneng First Bureau, successfully extracted the RCC core sample with a length of 20.25 meters and a diameter of 200 millimeters from the No.10 dam section.

2023-03-29 09:43:01

On March 12, the main pier bearing platform of continuous beam across Wangyue Road of Fuhuai Railway Bid 2 began to be poured.

2023-03-15 11:50:47