On January 4, Zhongcheng Dayou Huizhou Daya Bay Grid Side Independent Energy Storage Power Station Project was terminated. The bidding for the
project was launched on May 13, 2025. The tenderer was Zhongcheng Dayou New Energy (Huizhou) Co., Ltd. and the successful candidate was China Construction Second Engineering Bureau Co., Ltd.
Due to major changes in the implementation conditions of the project, the tenderee and the winning bidder have reached a consensus through consultation, and both parties agree to cancel the bid winning. It is reported that the investment of the independent energy storage power station project is about 200 million yuan, and the original plan is to complete the completion acceptance by the end of June 2025. There are four energy storage device areas in
the whole station, in which an 80MW/160MWh electrochemical energy storage power station is built in the energy storage device area.