On January 22, Taiyuan Precision Control Energy Technology Co., Ltd. invited tenders for EPC project of Taiyuan 500MW/1000MWh New Energy Storage Project. The purchaser of this
project is Taiyuan Precision Control Energy Technology Co., Ltd. This project constructs a 500MW/1000MWh energy storage power station . The project plans to use 220kV voltage level to connect to the power system. A new 220kV booster station will be built in the same period of the project. A 220kV overhead line is newly built in the energy storage power station and connected to the Shenshuli Wind Power Station to the Wuwei 500kV Substation.
This project adopts the EPC general contracting method, and the planned construction period is from March 1, 2026 to December 31, 2026.