On January 9, Shanxi Hejin Shangchu New Energy Technology Co., Ltd. Failing to sign the contract with the tenderee within the specified time according to the requirements of the tender documents.
It is reported that the project will build a battery energy storage system with installed capacity of 400MW/800MWh, PCS booster integrated machine and a new 220 kV booster station. In August
2025, the EPC tender announcement of the project was issued, and the results of the successful candidates were announced on September 12. The first candidate was China Construction Fifth Bureau Power Energy Co., Ltd., with a bid price of 1.019 billion yuan, equivalent to a unit price of 1.275 yuan/Wh, but the bid was rejected because the contract was not signed.