Up 3 billion in half a month! By Telling the Story of "Calculating Electricity Synergy", Does This Photovoltaic Enterprise Really Come Back to Life?

2026-07-07 09:52:46

Shortly after the official announcement of the cross-border computing power center, on the evening of June 29, King Kong Photovoltaic fell again, laying out wind power.

Shortly after

the official announcement of the cross-border computing power center, on the evening of June 29, King Kong Photovoltaic fell again, laying out wind power.

According to the announcement, Jingang Photovoltaic intends to invest 70.7457 million yuan to acquire 70% equity of Jinta Haobo New Energy Power Co., Ltd. 16.

The next day after the news was released, the company's share price continued to rise, closing at 27.

At this time, only half a month has passed since King Kong Photovoltaic took off its hat and got out of trouble . Previously, on June 12, the company officially cancelled the delisting risk warning, and the securities abbreviation was changed from "* ST King Kong" to "King Kong Photovoltaic". On that day, the company's share price closed at 20.

It is noteworthy that on the eve of cap removal, King Kong Photovoltaic just completed its wholly-owned acquisition of Beijing Chaowei Intelligent Computing, and simultaneously disclosed the fixed increase plan. 24.

In this way, in just half a month, the market value of King Kong Photovoltaic has been rising all the way, with a cumulative increase of more than 3 billion yuan , and the market sentiment has been completely ignited. But under the heat can not help but cause deep thought: This just from the edge of life and death out of the difficulties of the photovoltaic enterprises, really back to life? Ccement. Com/news/2607/richtext/IMG/8i7o9k6nwuf1783404737950.png ">

Over 2.3 Billion Losses in 7 Years!"!

However, the competition in the traditional glass industry has intensified, and the company's revenue growth has fallen into a bottleneck. In order to break the business dilemma, Diamond Glass crossed the border into the photovoltaic track in 2021, and bet all the chips on HJT technology. At the beginning of the

transformation, King Kong's photovoltaic layout was full of ambition, and its capacity planning was quite grand. First, the company officially announced an investment of 832 million yuan to build an integrated production line of 1.2G W HJT cells and 0.7 GW modules ; Subsequently, it planned to invest 4.191 billion yuan to build 4.

With its large-scale capacity layout, King Kong Photovoltaic was once regarded as the "cross-border dark horse" of the photovoltaic track.

But the grand blueprint failed to come true after all. According to the annual report of 2025, the company's actual effective HJT battery capacity is only 2.

From the performance point of view, from 2019 to 2025, the company's non-net profit deduction has been negative for seven consecutive years, with a cumulative loss of more than 2.3 billion yuan . Among them, in 2024, the non-net profit loss of Jingang Photovoltaic was as high as 7. By the first quarter of 2026, Jingang Photovoltaic continued to lose 64.05 million yuan .

Soaring 3 billion in half a month!

of the same year, the company started bankruptcy reorganization, and until December, the reorganization was implemented, the financial situation was improved, and the net assets turned from negative to positive. By the end of 2025, the asset-liability ratio of Jingang Photovoltaic had dropped to 34.56%, adding up to 289 million revenue for the whole year. 2.

However, before and after taking off the cap, the photovoltaic cross-border player made frequent moves: before taking off the cap, he raised a lot of money. 24. For a company that has just emerged from the delisting crisis, what is the intention of crossing the border so frequently?

It is not difficult to see that the core of King Kong Photovoltaic is to bet on the track of "calculating electricity synergy". Does the story of

"computing synergy" make sense? Because the core cost of computing power operation is always electricity. The rigid requirements of the policy side make green power the "survival standard" of computing power enterprises .

According to the explicit requirements of the National Data Bureau, the proportion of green power in new computing facilities must reach more than 80%. This means that the computing assets that fail to meet the standards will face the risk of failing to pass the energy consumption approval and prohibiting grid-connected operation. Green power direct connection is the only way for the current computing power center to obtain green power with both cost and compliance. The move of

King Kong Photovoltaic is equivalent to holding both ends of the electricity synergy in their own hands.

The company realizes complementary power generation through its own wind and solar power stations, and then supplies its own computing power center with the green power direct connection mode, which can not only meet 80% of the green power compliance requirements, but also absorb the green power capacity locally, killing two birds with one stone.

Soaring 3 billion in half a month! .

As King Kong Photovoltaic said, "Under the rising trend of compliance costs, the cost advantages and compliance advantages of computing power service providers with self-owned green power assets will be exponentially enlarged.".

In addition, the current photovoltaic industry is in a downward cycle, the company's cross-border layout of wind power can effectively optimize the asset structure, hedge the risk of a single industry cycle, and enhance the overall ability to resist risks. No matter how beautiful the

story is, see the real chapter in the financial report! For Jingang Photovoltaic, which has just stepped out of the delisting crisis and has a weak foundation, the large-scale expansion at this time naturally hides multiple risks .

First of all, the quality of the core target of this acquisition is doubtful. The target company, Jinta Haobo, was established in 2024 for a short time, and has not yet had any business income and is still operating at a loss. According to

the data, the target company lost 83,100 yuan in 2025 and continued to lose 1.

3 billion yuan in half a month This kind of transaction mode is easily questioned by the market as unfair pricing, and there are hidden dangers of interest transmission and development risks of listed companies.

However, the biggest risk comes from the financial and cash flow pressure brought by huge investment.

This equity acquisition needs to pay 70.75 million yuan, and subsequent wind power projects need to invest 16. However, in contrast to the fundamentals of Jingang Photovoltaic, as of the end of the first quarter of 2026, the total assets of the company are 2.969 billion yuan, and the total liabilities are 10. It can be seen that the assets of Jingang Photovoltaic are very thin .

In addition, just out of the delisting crisis, King Kong Photovoltaic has greatly expanded its assets, and the financial pressure has suddenly intensified. In addition to the 1.66 billion yuan wind power project, the company has previously disclosed 24.

Several advances, and the financial pressure of Jingang Photovoltaic is self-evident.

More attention should be paid to the long payback period of the project: the construction period of the 400MW wind power project is 12-18 months, and it is expected to be connected to the grid with full capacity by the end of 2027; the intelligent computing center project also needs long-term construction investment.

This means that Jingang Photovoltaic will be in the stage of "only input, no output" for a long time in the future, and it is difficult to generate substantial income in the short term, and a large amount of liquidity will be occupied for a long time.

In the

short term, King Kong Photovoltaic's bet on "computing synergy" fits the industry trend, and the short-term market value surge is enough to verify the market's recognition of this narrative. But under the long-term construction, how long can story on the tuyere be told?

At present, King Kong Photovoltaic has supported its market value by "calculating electricity synergy", but is this a rebirth or another high-profile capital transfer?

Moreover, as a cross-border photovoltaic player, the company itself has weak technology and unstable foundation compared with the leading photovoltaic enterprises. Now only two months after taking off its hat, it has successively crossed the border between computing power centers and wind power , superimposing the reality of tight funds, and what are the odds of King Kong Photovoltaic ?

All can be viewed after purchase
Correlation

Shortly after the official announcement of the cross-border computing power center, on the evening of June 29, King Kong Photovoltaic fell again, laying out wind power.

2026-07-07 09:52:46

On June 4, at the SNEC Photovoltaic Conference in 2026, the Digital New Energy DataBM. Com interviewed Gao Bin, chairman of Infocom (Zhejiang) Industrial Technology Co., Ltd. to conduct in-depth exchanges on issues related to highlight products, technological innovation and industry pain points.

2026-06-22 09:27:27

In the two weeks (5.30-6.12), the capacity of the announced PV module centralized procurement bidding and shortlisted projects was approximately 8.53 GW, representing a significant increase as compared with 6.29 GW in the previous period. Meanwhile, the total amount of PV module centralized procurement bidding projects was approximately 1.70 GW, representing a slight increase as compared with 1.26 GW in the previous period.

2026-06-15 09:23:00

On June 4, at the SNEC Photovoltaic Conference in 2026, the Digital New Energy DataBM. Com interviewed Huang Pan, sales director of Shaanxi Yidu Intelligent Technology Co., Ltd., focusing on the core technology and product application of precision flow control in the photovoltaic industry, and conducted in-depth exchanges.

2026-06-11 17:08:41

On June 4, at the SNEC Photovoltaic Conference in 2026, the Digital New Energy DataBM. Com interviewed Zhou Min, general manager of Guangzhou Sisenmek New Materials Technology Co., Ltd. to have in-depth exchanges on such topics as photovoltaic nano-functional materials, domestic substitution and self-control of the industrial chain.

2026-06-10 17:18:45

The electricity price mechanism of "unified government pricing, peak and valley according to time", which has been implemented for more than 40 years, is being replaced by real-time bidding in the spot electricity market. This means that when electricity is expensive and when it is cheap is no longer determined by an administrative document, but by supply and demand.

2026-05-28 10:14:36

In the past two weeks, many photovoltaic companies, such as Jingke Energy and Trina Solar, have announced the signing of large orders for photovoltaic and energy storage. Among them, the order size of photovoltaic modules is about 13.01 GW, and the order size of energy storage is about 3.1 G Wh.

2026-05-18 09:05:48

On May 1, Aerospace Mechatronics announced that due to the overcapacity of the photovoltaic industry and the "involution" price competition, the company's Lianyungang Shenzhou New Energy Co., Ltd. (Hereinafter referred to as "Lianyungang New Energy") lacks its own competitiveness and intends to transfer its 81.7552% stake in Lianyungang New Energy.

2026-05-07 18:21:03

In the past two weeks, the market of photovoltaic modules has recovered against the trend. According to the incomplete statistics of the DataBM. Com of Digital New Energy, the capacity of the photovoltaic module centralized procurement bidding and shortlisted projects that had been publicized in two weeks (4.18-4.30) was approximately 11.87 GW, which was significantly higher than that of 0.44 GW in the previous period. Meanwhile, the total capacity of the photovoltaic module centralized procurement bidding projects was 1.93 GW, which was significantly higher than that of 0.38 GW in the previous period.

2026-04-30 14:33:38

Since April, many photovoltaic companies, such as Jingke Energy and Longji Green Energy, have announced the signing of large photovoltaic and energy storage orders. Among them, the order size of photovoltaic modules is about 13.275 GW, and the order size of energy storage is about 5-6G Wh.

2026-04-27 18:07:56

Since last week, the special price components on the market are gradually being digested. This week, domestic spot stocks continued last week's water level, stabilizing between 30-35 GW.

2026-04-22 15:37:20

Digital New Energy DataBM. Com learned that on April 2, the Three Gorges Yunneng Power Generation (Huize) Co., Ltd. was fined 103.502 million yuan for "illegal land occupation", and the penalty organ was Huize County Natural Resources Bureau.

2026-04-13 18:06:52

On April 10, at the 15th China Cement Industry Summit, the Digital New Energy DataBM. Com interviewed He Jingxin, Sales Director of Shanghai Pincheng Jingyao Photovoltaic Technology Co., Ltd. to have in-depth exchanges on market trends, overseas layout and enterprise development.

2026-04-13 14:07:29

In the first half of the week, the price of photovoltaic modules was generally lowered, among which Jingke Energy was all lowered.

2026-04-08 16:56:58

In 2025, the auxiliary materials in the photovoltaic industry chain will continue to bear pressure. Taking photovoltaic quartz crucible as an example, with the market demand shrinking sharply and the price going down all the way, the performance of related enterprises ushered in a "big cooling".

2026-01-29 16:42:01

According to the incomplete statistics of the digital new energy DataBM. Com, the capacity of the photovoltaic module bidding and shortlisted projects that have been publicized in two weeks (1.3-1.16) is about 2.88 GW, but the total amount of the photovoltaic module bidding projects is 0.17 GW.

2026-01-19 09:14:10

Last week, after the implementation of the price adjustment measures of a component leader (the final reduction was 0.03-0.05 yuan/W), the volume of transactions did not increase. At present, buyers are in a strong wait-and-see mood, and it is more likely to continue to the beginning of next year.

2025-11-19 15:14:01

In the first half of the week, the two leading companies raised their quotations one after another, and the price of photovoltaic modules increased significantly.

2025-10-15 16:07:13

Recently, Zhengtai Electric announced that it had decided to terminate the listing of its subsidiary Zhengtai Digital Energy (Zhejiang) Co., Ltd. on the main board of the Shanghai Stock Exchange and withdraw the relevant application documents for listing.

2025-09-16 09:21:25

As the cost of upstream and auxiliary materials continues to rise, the performance of manufacturers is more differentiated.

2025-09-12 15:14:41

In September, the photovoltaic module collection market is expected to continue the warming momentum in August, but whether the traditional "peak season" can come as scheduled is still facing challenges.

2025-09-11 14:21:01

According to foreign media reports, the Indonesian government recently announced an ambitious solar energy development plan aimed at deploying 100 GW solar photovoltaic power generation projects.

2025-08-21 19:27:29

In terms of photovoltaic power generation, we are speeding up the construction of distributed photovoltaic power generation projects on the roof of raw material stacks in cement production enterprises. The second phase of photovoltaic power generation project is to install photovoltaic power generation equipment on the roof of the building, and at the same time to carry out the construction of energy storage projects on the user side, which is expected to further reduce the cost of energy consumption of enterprises.

2024-08-08 13:38:09

Under the leadership of Dong Shihong, Shijing Science and Technology has never forgotten its original intention of "green", firmly anchored the concept of green development in the torrent of the development of the times, and painted a magnificent and vibrant panorama of green ecological industry with practical actions.

2024-06-20 09:47:34

Opening up a new track has become the same choice for many cement enterprises.

2024-01-31 09:04:18

Market share over 30%, valuation 28 billion after five rounds of financing

2023-06-06 09:33:08

Battery module shipments hit another record high

2023-04-28 13:18:46

In 2023, the total contract amount has reached 18.575 billion yuan.

2023-04-17 10:35:59

After the new investment, the total capacity of the project is 8GW, with a total investment of about 4 billion yuan.

2023-02-27 11:38:59

The total construction and installation cost of the two bidding sections is 9.828 billion yuan.

2023-02-24 11:09:09

Eight photovoltaic projects with a total investment of 4.937 billion yuan.

2023-02-24 10:13:34

The operating indicators of GCL Integration continue to improve, and the financing capacity is gradually improved, which can support the orderly construction of GCL Integrated Battery and Component Project as planned.

2023-02-23 09:53:02

Promote Yijing Optoelectronics to form an upstream and downstream production matching pattern of "annual production of 5G W batteries + 10g W components".

2023-02-23 09:22:34

As the national team of traditional energy power construction, China can build new energy construction in recent years.

2023-02-17 09:29:49

In fact, Jiawei Xinneng's abandonment of lithium battery business has already emerged.

2023-02-13 10:18:33

If all the above projects are completed, Hesheng Silicon Industry will form an enterprise in the whole industry chain of silicon material-slice-component-photovoltaic glass-photovoltaic power station.

2023-02-09 17:25:40

Tongwei Helps Leshan City Build China's Green Silicon Valley.

2023-02-08 09:41:12

Jingao Science and Technology also announced a new plan for integrated investment and expansion.

2023-02-07 09:12:25

Shijing Technology won the bid for the process supporting system of the 5.3GW module expansion project of Atlas Sunshine Power (Thailand) Co., Ltd.

2023-02-06 10:29:48

Is the booming market in 2023 ready to jump the gun?

2023-02-03 13:41:51

The total investment of Suzhou Shijing is not more than 11.2 billion yuan to build a 24 GW high-efficiency N-type single crystal TOPCon solar cell project.

2023-01-11 10:07:10