On October 15, the 100000 kilowatt photovoltaic project of increasing production and expanding green in the oil and gas industry of Luntai County, Tarim Oilfield, Xinjiang, was officially started.
According to the previous EPC tender announcement of the project, the total installed DC side capacity of the project is 120.5131 MWp, the AC side capacity is 100 MW, the monocrystalline silicon double-sided double-glass N-type 620 W photovoltaic module is used, and the permanent land is 14.9 mu. 2483 mu of temporary land; 1 set of 10 MW/20 MWh lithium iron phosphate battery energy storage system , 1 110 kV booster station and 5 km of 110 kV transmission line.
The project is scheduled to complete the main project or meet the grid-connected conditions on December 30 this year. The planned grid-connected time is January 30, 2026, and the full-capacity grid-connected time is April 30, 2026. After the
project is put into operation, it will generate 160 million kilowatt-hours of electricity annually, replace 49700 tons of standard coal and reduce 129000 tons of carbon dioxide.